H.TauregTB December B-Field Mapping
H.TauregTB December Schedule Install equipment: May 2005 Start mapping: mid June 2005 Finish mapping: August 2005, latest
H.TauregTB December Mapping programme L3 and dipole at two polarities –Only ++ and -- combination L3 at 0.2 and 0.5 Tesla –Dipole powered always at same level L3 alone –At 0.2 and 0.5 Tesla and both polarities In L3 –Space Frame volume –EMC, HMPID, PHOS volume
H.TauregTB December Grid size Dipole –80 mm in x, y, z L3 –100 mm in r and z –2° in φ for r > 2 m –4° in φ for r < 2 m
H.TauregTB December Grid size Fine grid as above Coarse grid –Increase step size by factor 3 In φ and z for L3 In z for dipole
H.TauregTB December Mapping scheme
H.TauregTB December Mapping work Continuous, 24 h / 24 h Team of at least 3 Set up changes during normal working hours Time estimate to be worked out
H.TauregTB December Hardware Support structure to be adapted for dipole Support structure to be adapted for L3 Measuring arms to be constructed for L3