OFFICE OF SCIENCE Stephen W. Meador, Chairperson DOE/SC Review Committee Office of Science, U.S. Department of Energy Closeout.

Slides:



Advertisements
Similar presentations
OFFICE OF SCIENCE Kurt W. Fisher Review Committee Chair Office of Science, U.S. Department of Energy 1 Closeout Report.
Advertisements

OFFICE OF SCIENCE Stephen W. Meador, Chairperson DOE/SC Review Committee Office of Science, U.S. Department of Energy Closeout.
OFFICE OF SCIENCE Stephen W. Meador, Chairperson DOE/SC Review Committee Office of Science, U.S. Department of Energy Review.
OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
OFFICE OF SCIENCE Kin Chao, Chairperson DOE/SC Review Committee Office of Science, U.S. Department of Energy Review Committee.
1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
Trip Report on the visit to ICST of HIT, Harbin, China Derun Li Mike Green Steve Virostek Mike Zisman Lawrence Berkeley National Laboratory (from December.
Jess Albino Facility Advisory October 29, 2007 FACILITY ADVISORY COMMITTEE PLENARY CONVENTIONAL FACILITIES UPDATE October.
OFFICE OF SCIENCE Review of Critical Decision 2 for the Large Liquid Argon Detector for Neutron Physics (MicroBooNE) at Fermi National Accelerator Laboratory.
OFFICE OF SCIENCE Review Committee for the NuMi Off-Axis Neutrino Appearance (NO A) Experiment at the Fermi National Accelerator Laboratory August 9, 2011.
XII- COST CONTROL, MONITORING & ACCOUNTING
M. Scharfenstein - ES&H Coordinator 8 June 2009
GlueX Solenoid Update George Biallas May 12, 2010 GlueX Collaboration Meeting.
Office of Project Management Metrics Report Presentation
Project Management Methodology Project monitoring and control.
Project Risk Management. The Importance of Project Risk Management Project risk management is the art and science of identifying, analyzing, and responding.
1 BROOKHAVEN SCIENCE ASSOCIATES Authorization Basis Plan Steven Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting December 10 – 11, 2009.
NIST Special Publication Revision 1
Project Tracking. Questions... Why should we track a project that is underway? What aspects of a project need tracking?
1 UK PM Report Costs & Schedule Alan Grant, STFC.
OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
Project Overview Ron Strykowsky Princeton Plasma Physics Laboratory NSTX Upgrade Project Office of Science Review LSB B318 February 4th, 2014 NSTX-U Supported.
Princeton University Plasma Physics Laboratory EVMS Certification Review NSTX Project Overview Ron Strykowsky October 4-6, 2011.
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
Quality Assurance Readiness for Operations Review Judy Malsbury, Head of QA Princeton Plasma Physics Laboratory NSTX Upgrade LSB B318 December 9-11, 2014.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
Silicon Inner Layer Sensor PRR, 8 August G. Ginther Update on the D0 Run IIb Silicon Upgrade for the Inner Layer Sensor PRR 8 August 03 George Ginther.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Status & Charge to ASAC Steve Dierker Associate Laboratory Director for Light Sources, NSLS-II Project Director.
February NSTX-U Team Meeting. Engineering Operations Feb. 11, 2014 NSTX-U In-Vessel installations and Calibrations to conclude in late March (3/28/2014)
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Edward T. Lessard ESHQ.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
1 BROOKHAVEN SCIENCE ASSOCIATES ASD Procurements Gregory Fries Liaison/Manufacturing Engineer NSLS-II ASAC October 22-23, 2009.
1 NSTX Upgrade Progress Report May 7 th, 2013 Ron Strykowsky, Erik Perry, Tim Stevenson, Larry Dudek, Steve Langish, Tom Egebo, Mike Williams and the NSTXU.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
Anthony Indelicato DOE-Princeton Site Office May 2012 Construction Progress Review for the NSTX Upgrade Project Construction Progress Review for the NSTX.
PU-PPPL Earned Value Management System Overview Thomas Egebo October 4-6, 2011 Princeton University Plasma Physics Laboratory EVMS Certification Review.
Fermilab Presentation Greg Bock, Pepin Carolan, Mike Lindgren, Elaine McCluskey 2014 SC PM Workshop July 2014.
Project Management Methodology
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
OFFICE OF SCIENCE Stephen W. Meador, Chairperson DOE/SC Review Committee Office of Science, U.S. Department of Energy Review.
OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
11/2/2005Mike Viola1 November Lehman Review November 2, 2005 NCSX VVSA NCSX Vacuum Vessel Fabrication Major Tool and Machine – S F 3 120° segments.
U.S. Department of Energy’s Office of Science National Compact Stellarator Experiment (NCSX) Princeton Plasma Physics Laboratory (PPPL) CLOSEOUT PRESENTATION.
Request for Service (RFS) Process and Metrics Update June 24, 2008.
OFFICE OF SCIENCE 1 Closeout Report on the DOE/SC CD-3b Review of the Utilities Upgrade Project (UUP) Fermi National Accelerator Laboratory August 11-12,
PPPL is Committed to the Success of NCSX Rob Goldston, Director Princeton Plasma Physics Laboratory August 15, 2007.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
Strykowsky 1Project Review November 2, 2005 NCSX Project Review November 2, 2005 Cost and Schedule Ron Strykowsky.
Tom Egebo PPPL Review of the NSTX TF Coil Repair Effort September 3 - 4, 2003 Cost & Schedule to Completion Supported by Columbia U Comp-X General Atomics.
Closeout Report on the Review Committee (CD-1) for the Long Baseline Neutrino Experiment (LBNE) Project at Fermi National Accelerator Laboratory October.
Anthony Indelicato DOE-Princeton Site Office February 2014 Construction Progress Review for the NSTX Upgrade Project Construction Progress Review for the.
Anthony Indelicato DOE-Princeton Site Office October 2013 Construction Progress Review for the NSTX Upgrade Project Construction Progress Review for the.
Strykowsky 1Office of Science Review August 15, 2007 Office of Science Project Review NCSX August 15-17, 2007 Cost and Schedule Ron Strykowsky.
BSBPMG501A Manage Project Integrative Processes Manage Project Integrative Processes Project Integration Processes – Part 2 Diploma of Project Management.
Assembly 12/14/06 #1 Assembly and Commissioning Paul Huffman.
OFFICE OF SCIENCE Closeout Report by the Review Committee for the LHC-CMS Detector Upgrade Project Fermi National Accelerator Laboratory August 27, 2013.
NCSX Strykowsky 1Independent Project Review (IPR) June 8-9, 2004 NCSX Project Review June 8-9, 2004 Cost, Schedule, and Project Controls Ron Strykowsky.
Anthony Indelicato DOE-Princeton Site Office December 2012 Construction Progress Review for the NSTX Upgrade Project Construction Progress Review for the.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
SC Project Review of NCSX, April 8-10, 2008 C. A. Gentile NCSX Startup (WBS 85) C.A.Gentile NCSX CD-4 Startup.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
OFFICE OF SCIENCE DOE/SC CD-2/3b Review of the Muon to Electron Conversion Experiment (Mu2e) Project Fermi National Accelerator Laboratory February 4,
OFFICE OF SCIENCE DOE/SC CD-3c Review of the Muon to Electron Conversion Experiment (Mu2e) Project Fermi National Accelerator Laboratory June 14-16, 2016.
Camera PDR/CD1 Planning 19 September 2008
Managing Project Work, Scope, Schedules, and Cost
Conventional Facilities
SNS-PPU upgrades the existing accelerator structure
Presentation transcript:

OFFICE OF SCIENCE Stephen W. Meador, Chairperson DOE/SC Review Committee Office of Science, U.S. Department of Energy Closeout Report for the National Spherical Torus Experiment (NSTX) Upgrade Project Princeton Plasma Physics Laboratory October 2-3, 2013

OFFICE OF SCIENCE Review Committee 2 Stephen Meador, DOE/SC, Chairperson Review Committee SC 1–Technical Approach *Arnie Kellman, General Atomics Will Oren, TJNAF SC 2–Cost and Schedule *Kin Chao, DOE/SC Tim Maier, DOE/BHSO SC 3–Management and ES&H *Frank Crescenzo, DOE/BHSO Mike Epps, DOE/TJSO Robin Noyes, DOE/APM *Lead Observers Joe May, DOE/SC Barry Sullivan, DOE/SC Tony Indelicato, DOE/PSO

OFFICE OF SCIENCE 3 Charge Questions 1.Construction Efforts: Are construction efforts being executed safely? Does the project have adequate resources and the appropriate skills mix to execute the project per the plan? 2.Baseline Cost and Schedule: Are the current project cost and schedule projections consistent with the approved baseline cost and schedule? Is the contingency remaining adequate for the risks that remain? 3.Management: Evaluate the management structure as to its adequacy to deliver the scope within budget and schedule. Are risks being actively managed? Has the project responded satisfactorily to the recommendations from the previous project reviews? 4.Transition to Operations: Is the Project appropriately aligned for completion of construction efforts and transitioning to NSTX-U for CD-4 approval?

OFFICE OF SCIENCE 4 2. Technical Status A. Kellman, GA*/W. Oren, TJNAF 1.Construction Efforts: Are construction efforts being executed safely? Does the project have adequate resources and the appropriate skills mix to execute the project per the plan? Yes. The project is being executed safely. In most areas, adequate resources and the appropriate skills mix are available to complete the tasks per plan. Additional resources were added to the project to address some tasks that were falling behind, such as the Digital Coil Protection System (DCPS). Additional personnel on the CS fabrication has helped, but this task continues to use contingency and additional time and resources may be required for timely completion of this effort. 4.Transition to Operations: Is the Project appropriately aligned for completion of construction efforts and transitioning to NSTX-U for CD-4 approval? Yes, the project is beginning the process of transitioning from construction to operations by preparing for a two step Operational Readiness Assessment based on established NSTX startup procedures.

OFFICE OF SCIENCE 5 2. Technical Status A. Kellman, GA*/W. Oren, TJNAF Findings The safety record of the project continues to be outstanding with only one recordable incident and no DART cases since the December 2012 review. Excellent progress has been made on the CS fabrication since the last review. Major tasks with considerable technical risk have been completed successfully including the fabrication and VPI of all four TF quadrants and the full TF bundle, two new TF coils, delivery of major tooling for the OH solenoid, and the preparation of the OH winding facility, including the pivot beam and CS tilt fixture. Fabrication of the inner PF coils (1A, B, C) was delayed by several months due to a subcontractor problem with the prime vendor, but the delivery will not affect critical path.

OFFICE OF SCIENCE 6 2. Technical Status A. Kellman, GA*/W. Oren, TJNAF Findings Overall, the NB project is progressing on task, under cost (SPI=1.06) and on time (CPI=1.0). −Beamline #2 (BL2) internal component relocation is complete, the J-K port welding is complete, the NB duct and Torus Vacuum Pumping System duct fabrications are complete, leak checked and ready for installation. −Cryogenic and water piping installation are complete. Relocation of three High Voltage Enclosures (HVE) for BL2 is complete. Installation schedules in machine hall are based on 5 day work week with options for increasing the number of shifts as necessary.

OFFICE OF SCIENCE 7 2. Technical Status A. Kellman, GA*/W. Oren, TJNAF Findings Additional manpower (5.5 FTE) has been provided to the DCPS system in response to a recommendation from the December 2012 review. Good progress has been made and full system commissioning is scheduled to begin in June 2014 to be ready to support Integrated System Testing in Fall The DCPS system must be in place before operations can begin. Secondary passive plates in Bay A/L were found to be weaker than acceptable for the higher NSTX-U parameters. A new design using e-beam welding has been developed to address the problem. Installation is anticipated for July ‘14. CD-4 can be completed even if this installation slips. A Facility Startup plan was presented in response to a recommendation from the December 2012 review. The startup plan presented utilizes the system developed and used successfully over the past 13 years of NSTX operation.

OFFICE OF SCIENCE 8 2. Technical Status A. Kellman, GA*/W. Oren, TJNAF Comments Installation planning and scheduling of activities in the test cell are well thought out. Schedules are realistic with built-in contingency anticipating possible fit-up problems. CS fabrication continues to be critical path. Work to date has been of high quality but the task continues to use schedule contingency. Care must be exercised not to risk technical success of the overall project in order to improve schedule margin. However, management should identify lower risk tasks (non-winding) that might be more amenable to being performed by additional personnel to gain schedule contingency. A comprehensive electrical test plan for the TF bundle to Ohmic Heating (OH) coil and for the OH coil alone needs to be finalized soon to assure readiness of the test equipment and setup when needed.

OFFICE OF SCIENCE 9 2. Technical Status A. Kellman, GA*/W. Oren, TJNAF Comments The project identified three areas with poor quality welds from the same vendor after delivery to PPPL. All welds were ground out and re-welded in house. This emphasizes the importance of evaluating vendor quality performance in process and before deliver to PPPL. In this regard, we support the planned weekly visits to Everson-Telsa during the fabrication of the inner PF coils and commend the project for continuing to support additional QA oversight for vendors. Because the new DCPS is required for NSTX-U operations to begin, a reduced scope or simplified version of the DCPS should be considered that has a very high probability of completion well before the planned start of operations and testing.

OFFICE OF SCIENCE Technical Status A. Kellman, GA*/W. Oren, TJNAF Comments Components in NSTX-U will experience higher forces, torques, power and energy fluxes due to the installation of new or upgraded systems and most will not be fully realized for 2-3 years. It is suggested that NSTX-U management begin the process of how to confirm that all new systems are performing as expected before parameters are raised. This would include (1) evaluations of measurement techniques, (2) simulations with which to compare the measurements, and (3) when during the multi-year system commissioning period key evaluations should be performed.

OFFICE OF SCIENCE Technical Status A. Kellman, GA*/W. Oren, TJNAF Recommendations Identify lower risk CS tasks that can be performed by additional personnel or off-shift to gain schedule contingency. Generate an interim milestone for DCPS for earlier commissioning of a reduced scope system able to support all system testing and initial machine operation.

OFFICE OF SCIENCE 2.Are the current project cost and schedule projections consistent with the approved baseline cost and schedule? Is the contingency remaining adequate for the risks that remain? Yes, the projections by the project is consistent with the approved cost and schedule baseline. The contingency remaining is probably adequate for the risks that remain, however, the continuing trend in contingency usage is a concern. 4.Is the Project appropriately aligned for completion of construction efforts and transitioning to NSTX-U for CD-4 approval. Yes Maier DOE/SC 3. Cost and Schedule K. Chao, DOE/SC and T. Maier DOE/SC

OFFICE OF SCIENCE 1.PROJECT STATUS as of August 30, 2013 Project TypeMIE CD-1Planned: Dec 2009Actual: Apr 2010 CD-2Planned: Dec 2010Actual: Jan 2011 CD-3Planned: Jan 2012Actual: Dec 2011 CD-4Planned: Sep 2015Actual: on schedule TPC Percent CompletePlanned: 74%Actual: 72% TPC Cost to Date $63.4M TPC Committed to Date $65.5M TPC $94.3M TEC $83.5M Contingency Cost (no Mgmt Reserve)$7.1M 29% to go Contingency Schedule on CD months 78.7% to go CPI Cumulative 0.98 SPI Cumulative 0.97

OFFICE OF SCIENCE Cost and Schedule K. Chao, DOE/SC*/ SC-2 Findings The critical path for the project remains the TF coils, the CS, digital coil protection, and vessel closure and pump down activities. The standing army cost is approximately $250K per month. However, it is expected to be reduced to ~$150K to $100K for the remainder of the project as activities are completed and personnel no longer charge to the project. Since the last review in December 2012, the project has utilized additional 3.5 months of schedule contingency for magnet activities. The project EAC estimate in July 2013 is $87.6M with November 2014 forecast CD-4 date. The project analysis indicate that the project may consume bulk of the contingency by May 2015, which is 6 months beyond the November 2014 forecast CD-4 early finish date.

OFFICE OF SCIENCE Cost and Schedule K. Chao, DOE/SC*/ SC-2 Findings The project provided to the review committee the risk registry, Engineering Change Proposal (ECP) log, the latest resource loaded schedule, etc. Of the ~$17M of contingency, the risk register identified ~$6.1M. The remaining risks in the risk registry is ~$3.7M

OFFICE OF SCIENCE Cost and Schedule K. Chao, DOE/SC*/ SC-2 Comments The EAC estimate appears optimistic. There appears to be events that has high probability of occurrence and thus should be included in the EAC estimates (i.e., January 2015 CD-4 date instead of November 2014, overhead rate credit, PF quality issues, OH winding takes longer). The ECP log contains cost impact of the proposed changes, but not the schedule impact in durations. As a result, it is difficult to determine what the actual delays in the activities are. The risk identification, analysis, and tracking should be more rigorous. For example, most of the risks in the risk registry have not been updated recently. Any new risk that has been identified is not captured in the registry. Instead, the cost impacts are directly included in the EAC. Most of the contingency usage were from activities not identified in the registry.

OFFICE OF SCIENCE Cost and Schedule K. Chao, DOE/SC*/ SC-2 Recommendations Include schedule contingency impacts in the ECP forms for the future ECPs. The EAC calculation should include items and activities that are likely to occur. Ensure risk register is updated and maintained

OFFICE OF SCIENCE Management and ES&H Crescenzo, DOE/BHSO; Epps, DOE/TJSO, Noyes DOE/APM 1.Construction Efforts: Are construction efforts being executed safely? Does the project have adequate resources and the appropriate skills mix to execute the project per the plan? YES 2.Management: Evaluate the management structure as to its adequacy to deliver the scope within budget and schedule. Are risks being actively managed? Has the project responded satisfactorily to the recommendations from the previous project reviews? YES but see comments in cost and schedule above. 3.Transition to Operations: Is the Project appropriately aligned for completion of construction efforts and transitioning to NSTX-U for CD-4 approval? YES

OFFICE OF SCIENCE Findings Fabrication of major technical components (center stack, neutral beam, ancillary systems) is making good progress. The critical path runs through fabrication and installation of the center stack (CS). There remains some low likelihood, high risk associated with fabrication and assembly of the CS (e.g. electrical failures). This will be mostly retired upon delivery of the CS to the test cell now scheduled for May Installation and construction reports excellent progress. Re- assembly is well underway. There was one recordable injury and no radiological incidents since the last review Management and ES&H Crescenzo, DOE/BHSO; Epps, DOE/TJSO, Noyes DOE/APM

OFFICE OF SCIENCE Findings The project sought external expert advice (National Magnet Lab) on plans for the CS. Planning for startup and transition to operations is well underway with external independent oversight planned Management and ES&H Crescenzo, DOE/BHSO; Epps, DOE/TJSO, Noyes, DOE/APM

OFFICE OF SCIENCE Comments The project has performed well since CD-3 as measured by EVMS data. Installation and construction appear very well planned and executed so far. Safety performance is excellent. High quality assembly of the CS is critical for risk mitigation. Planning for facility readiness for operation appears good. Earlier project challenges related to funding and critical skills were resolved satisfactorily Management and ES&H Crescenzo, DOE/BHSO; Epps, DOE/TJSO, Noyes DOE/APM

OFFICE OF SCIENCE Comments The project appears on a track to successful completion based on performance to date, remaining cost and schedule contingencies, and risk analysis. The May 2014 milestone for delivery of the CS to the test cell and November 2014 early finish appear overly optimistic. Performance of the CS to date has shown a steady draw on cost and schedule contingencies. As noted by the Cost and Schedule committee, there are credible analyses to show there may be less than 28% cost contingency available to the project. The facility should consider whether there are elements of the DOE Accelerator Safety Order that are absent from NSTX that could add quality to startup and operations Management and ES&H Crescenzo, DOE/BHSO; Epps, DOE/TJSO, Noyes DOE/APM

OFFICE OF SCIENCE Recommendations Evaluate a broader range of likely project outcomes to better understand and communicate with DOE the limits of cost and schedule contingencies to ensure project success by November 1, Work with the Site Office and program develop a focused “end game plan” to monitor and communicate critical project activities to better ensure project success by November 1, Action Item Site Office to schedule a status review in mid-January Management and ES&H Crescenzo, DOE/BHSO; Epps, DOE/TJSO, Noyes DOE/APM