Detectors installation in the TAN at IR1 and IR5: status and planning A. L. Perrot (TS/LEA-Int) Joint LHC Machine Experiments Workshop on very forward.

Slides:



Advertisements
Similar presentations
1 ZDC Status, 9th December ‘07 Fitting in the TAN slot Getting in and out of the TAN Schedule Trigger Yasar Onel (Michael Murray) for ZDC group.
Advertisements

Observations and next works from the recent tests of the insertion tools of Mini-Drawers at CERN Roméo Bonnefoy and François Vazeille Tilecal Operation.
LHCf: a LHC Detector for Astroparticle Physics LHCf: a LHC Detector for Astroparticle Physics Lorenzo Bonechi on behalf of the LHCf Collaboration * University.
CERN – March 10, 2006TAN Installation Workshop - The LHCf experimentOscar Adriani The LHCf experiment Measurement of Photons and Neutral Pions in the Very.
The LHCf experiment Measurement of Photons and Neutral Pions in the Very Forward Region of LHC Letter Of Intent: May 2004 Technical report: September 2005.
Crab Cavities in IR1 and IR5 Some considerations on tunnel integration What will be the situation in the tunnel after the LHC IR Phase-1 Upgrade. What.
ZDC Remote Handling System March 10, 2011 Project Status and Forward Planning Technical Implementation Group Meeting Paul Debbins University of Iowa.
Experimental Area Meeting V. Bobillier1 Good connection to earth (in many points) of every metallic parts to be installed in the cavern is very.
Addendum to EDMS document “Instruction Manual for inserting the CMS ZDCs using the HXTC crane” In addition to the ZDC detectors in the TAN instrument.
Machine Detector Interface for the HL (MDI) CERN, April 15, 2011 Austin Ball, Helmut Burkhardt, Marzio Nessi.
June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.
Construction and Installation of the CLIC Experimental Area
The LHCf experiment Measurement of Photons and Neutral Pions in the Very Forward Region of LHC Letter Of Intent: May 2004 Technical report: September 2005.
(1/15) 08/05/13 – RadWG meeting J. Mekki M. Brugger PS East Area Update Outline Layout updates of the facility Conveyer options Mock-up preparation and.
RF power & FPC status Eric Montesinos, CERN BE-RF on behalf of all people involved, great thanks to all of them !
Radiation Protection LS1 - Collaboration with CERN Technical Groups - Lessons learnt Stephane Bally (CERN), Sandro Di Vincenzo (CERN) Indico
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
MoEDAL MoU EDMS No Issues from LHCb & CERN  MoEDAL at IP8  Infrastructure  TimePix Deployment  Access & Safety  General Conditions MoEDAL.
13 June 2013Laurent Roy Optical Fibers / Electronics Upgrade -Fibers need for Upgrade -> Installation ? -Two techniques possible for multi fibers installation.
09/03/2010 ADO-PO section meeting Beam Pipe Extraction/Insertion R. Vuillermet.
Experimental equipment interacting with beam operation D. Macina TS/LEA Many thanks to my colleagues both from the experiments and the machine for their.
RADIATION SOURCE Design Review Dmitry Gudkov BE-BI-ML.
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
LHC Insertions Upgrade Working Group (LIUWG) Space available in tunnel Y. Muttoni.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
STATUS REPORT: ALIGNMENT OF COLLIMATORS P. BESTMANN /O. ABERLE Collimation Working Group 26/09/2011.
LHCf: installation & commissioning Measurement of Photons and Neutral Pions in the Very Forward Region of LHC Oscar Adriani INFN Sezione di Firenze - Dipartimento.
R2E Mitigation Project P5 Relocation Options - Discussion R2E Mitigation Project CMS Relocation Options Towards An R2E Baseline 1 M. Brugger for the R2E.
K. Foraz & Perrot A. L., EN/MEF - R2E Project LMC 25th May 2011 Thanks to EN/EL, EN/HE, EN/MEF, equipment owners the LHC integration team & the R2E team.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
Radiation Protection aspects for SHIP Doris Forkel-Wirth, Stefan Roesler, Helmut Vincke, Heinz Vincke CERN Radiation Protection Group 1 st SHIP workshop,
TAS at IP5 Present situation and plans François BUTIN TS/LEA.
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
DCS meeting27.Sep.2002 Serguei Zelepoukine (IHEP, Protvino) Contents: 1. Front-end electronics: problems & solutions. 2. DCS cabling outside the ECAL detector.
Experimental Areas Studies Lessons learnt at CMS M Gastal & CMS Technical Coordination (A Ball, W Zeuner)
Transport & Handling of Detectors TAN Workshop S. Prodon –
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
HIGH RADIATION TO MATERIALS: EXPERIMENTAL AREA HiRadMat Users meeting, 14/7/2011 Outline  Location  Test zone  Test tables geometry and position  Services.
HIGH RADIATION TO MATERIALS: HIRADMAT STATUS HiRadMat Scientific Board, 23/4/2012 Outline  Location  Status  Beam line  Infrastructure  Exp. Area.
LHCf Detectors Sampling Calorimeter W 44 r.l, 1.6λ I Scintilator x 16 Layers Position Detector Scifi x 4 (Arm#1) Scilicon Tracker x 4(Arm#2) Detector size.
Status of the PSD upgrade - Status of the PSD cooling and temperature stabilization system - MAPD gain monitoring system - PSD readout upgrade F.Guber,
Overview on the Proposal for a new Gamma Irradiation Facility at CERN GIF++ Mar CAPEANS April 29 th, 2009 April 29, 091M.C.
LHC forward detectors EN/MEF roles & responsibilities MEF group meeting, 24 th November 2010 A. L. Perrot- EN/MEF-LE.
R ADIATION P ROTECTION ASPECTS LSS1 - TAN REGION Cristina Adorisio (CERN - DGS/RP)
Interface of FP420 to LHC FP420 meeting 28-Sep-2006.
R ADIATION P ROTECTION ASPECTS LSS1 LHC f RE - INSTALLATION Cristina Adorisio (CERN - DGS/RP) LTEX Meeting – May 10 th, 2012.
1 st LTEX meeting Protecting the experimental caverns and personnel from a "sector 34 like" incident: work planned in the LHC tunnel Prepared by M GASTAL.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
SuperB Integration SuperB Experimental hall. Related topics of Slac D&D activities.
DCal-ALICE integration and installation plan and status A. Tauro.
Joint LHC Machine-Experiments Workshop on Very Forward Detectors Summary D. Macina (CERN) Joint LHC Machine-Experiment Worshop on the Luminosity Monitoring.
Test beam check list Michael JECKEL EN-EA-EC. Content: Safety & Radiation Protection Arrival Access Installation Departure Michael JECKEL EN-EA-EC.
BRAN at IR2 and IR8: status, commissioning and operation Enrico Bravin AB-BI Joint LHC Machine-Experiments Workshop on Very Forward Detectors 25 January.
Integration of forward physics detectors into the LSS of the LHC D. Macina (TS/LEA) Technical Support 2004 Workshop.
Fire and Oxygen Deficiency Detection Systems Risk Analysis S. Grau GS-ASE-Alarm Systems R2E Workshop, Tuesday Session 2: Equipment inventory,
ELENA installation progress F. Butin / ELENA collaboration.
LHCf: Integration and compatibility with the luminosity monitor
TAXS and TAXN ABSORBERS - OVERVIEW
Installation of an Instrument on a CERN machine
INSTALLATION SEQUENCE
A.-L. Perrot, TS/LEA-int LEMIC A.L. Perrot – TS/LEA/int LEMIC
CMS Area Working Group Meeting
Components for the Machine-Interface Regions
LHC Experimental Vacuum Systems Status October ‘07
Accelerator and Experiment Interface Session: LS2, LS3
LS2 LHC forward experiments
Collimator Control (SEUs & R2E Outlook)
BRAN: LS2-plans TREX M. Palm, E. Bravin, BE-BI-PM.
Presentation transcript:

Detectors installation in the TAN at IR1 and IR5: status and planning A. L. Perrot (TS/LEA-Int) Joint LHC Machine Experiments Workshop on very forward detectors, CERN, 25 January 2007

4 Target Absorbers Neutrals (TANs) D2 Q4 XRP2 XRP3 XRP1 XRP2 XRP1 XRP3 D2 Q4 TAN Q2 Q3 Q1 Q2 Q3 D1 USC55 UJ53 UJ57 R57 Point 5 D2 Q4 TAN Q4 D2 UJ13 UJ14 US15 UJ16 UJ17 USA15 Q1 Q2 Q3 D1 RI13 RI17 TAN Q2 Q3 D1 Q1 Point 1

In each TAN 1 slot with 10 movable Cu bars Possibility to add instrumentation Slot : l1000 x w95 x h605

LHCf ATLAS ZDC BRAN Point 1 LHCf: LHC forward physics BRAN: Beam RAdiation Neutrals monitor ZDC: Zero Degree Calorimeter Point 5 HCAL BRAN ECAL CMS ZDC ECAL = Electromagnetic CALorimeter HCAL = Hadronic CALorimeter Courtesy of D. Macina

Installation of detectors in TAN - introduction - Space allocation around the TAN in the LHC tunnel - Services - Handling / Transport - LHCf and BRAN first installation - Integration in LHC schedule - Radiation monitoring close to the TAN Several teams involved in the installation: - radio-protection (SC/RP), - transport (TS/IC), - gas installation (TS/LEA), cabling (TS/EL, TS/LEA), - LHC operators (AB/OP), - LHC planning and commissioning teams (TS/IC, TS/HDO), - scientific collabs. (LHCf, BRAN, CMS-ZDC, ATLAS-ZDC). Coordination (TS/LEA-int)

Space allocation in the TAN surrounding monorail space for transport space for survey All the experiments use about 30 cm above the TAN top surface Ok with the survey team Survey team => move the 3 alignment target spheres (fiducials) located on each TAN top surface

Services integration inside the LHC, ATLAS & CMS environments Work performed on TAN: holes drilling for patch-panels installation of LHCf and BRAN (TS/IC,TS/LEA). Common to all experiments: - cabling and fibers pulling from the location in the tunnel to the rack control rooms of ATLAS and CMS experiments (TS/EL, TS/LEA). LHCf + ATLAS ZDC ( & ATLAS RP): - cables follow different paths: request of expts.: shorter path especially for trigger cables; compatibility with the cables already installed/foreseen for the machine and the ATLAS experiment. - additional cable trays installation in UPS galleries, machine areas and ATLAS cavern (TS/EL and TS/LEA), - use of cables trays already installed in the ATLAS experimental cavern (UX15) to surround the ATLAS detector. Services installations = integrated in the LHC schedule Constant contact with the planning officers (TS/IC, TS/LEA) and the hardware commissioning team (TS/HDO).

D2 Q4 TAN Q4 D2 UJ13 UJ14 US15 UJ16 UJ17 USA15 Q1 Q2 Q3 D1 RI13 RI17 TAN Q2 Q3 D1 Q1 Point 1 LHCF and ATLAS ZDC racks Cabling paths from TANs to LHCf and ATLAS ZDC racks road 1 road 2

Cables trays inst. and cabling for LHCf and ATLAS ZDC LSS1 UJ13 ATLAS exp. cavern

Services integration inside the LHC, ATLAS & CMS environments LOCKED CAGE TAN Gas distribution at Point 1 Special agreement with safety dept. to have gas bottles underground Future interventions: replacement of a set of gas bottles LHCf: - plugs installation in the tunnel (TS/EL), - cooling study for LHCf arm#2 (TS/CV) BRAN: - cabling by TS/EL; coordination by AB/BI. - gas installation and distribution (TS/LEA/gas section) locked caged area + change over panel (Pt1-US15 and Pt5-UJ56) gas distribution network between the caged area and the TAN

CMS-ZDC (&TOTEM): - additional cable trays installation from UL55 to USC55 (CR and Laser room) (TS/EL), in UJ53 and UJ57 (TS/LEA), in LSS5 (TS/EL). - use of cables trays already installed in the machine and rack room area Services integration inside the LHC, ATLAS & CMS environments XRP2 XRP3 XRP1 XRP2 XRP1 XRP3 D2 Q4 TAN Q2 Q3 Q1 Q2 Q3 D1 USC55 UJ53 UJ57 R57 Point 5 CMS-ZDC rack UL55 laser room

Handling With which device? Guide line: simplicity + use the same device for Cu bars and all the detectors Experiments request: insertion of the detectors in the TAN in 1 ‘block’ (taking into account the height of electronics, manipulator) => faster installation. 1 rst step: mock-ups construction (TAN TS/LEA –detectors physicists coll.) 2 nd step: simulations 3 rd step: dry run with the first TAN at Pt5 (Apr. 2006) 4 th step: adaptation of the forklift arm (design and construction- TS/IC) BRAN mock-up inserted inside TAN mock-up Courtesy of F. Delsaux (TS/MME) Yale 3.5 t at Pt1

monorail 796 for IP1 786 for IP5 Constraints Tunnel Point 1: TAN top surface - monorail= 926 mm TAN top surface - hook = 796 mm Point 5: TAN top surface - monorail= 916 mm TAN top surface - hook= 786 mm Cu bar and detectors dimensions and weight COPPER BAR 46 kg l=98mmw= 94mm h= 605mm DETECTORS LHCf 20kgl=290mmw= 90mmh=608mm (+ 362 mm for the manipulator) BRAN 41kgl=99mmw= 94mmh=853mm to the top of the hoist ring CMS ZDC ECAL 65 kgl=116mmw= 92mmh=705mm (+ 150 mm for the electronics) CMS ZDC HCAL 200 kgl=711mmw= 92mmh=705mm (+150mm for the electronics) ATLAS ZDC ECAL 80 kgl=123 mmw= 93.8 mmh=738 mm ATLAS ZDC HCAL 240 kgl=450 mmw= 93.8 mmh=738 mm Handling

Transport team (TS/IC) solution extension of the usual forklift arm =>enhancement of the available space above the TAN top surface. Transport team (TS/IC) request M12 screwed hole on top surface of each detector. Courtesy of P. Minginette (TS/IC) Total gain in height ~ 31cm. Handling

Usual forklift arm New extension arm for the usual forklift Handling

Courtesy of P. Minginette (TS/IC) Transport team proposal for CMS-ZDC - not possible to have the required M12 screwed hole on top surface of detector because of electronics boxes all along the surface. - TS/IC: draft design of 2 supports. - CMS-ZDC team: final design and construction of the 2 new supports - Tests performed at CERN with the new supports on 8 Dec and on 23 Jan. 2007(TS/IC, CMS-ZDC and TS/LEA) Handling

Point 1 (RI132-RI171) - Access by Pt1: Shielding between UJ13-UJ14, and between UJ16-UJ17 => forklift too large to pass - Access by Pt 2 and Pt8: ok Travel underground until TANS= ok (study by O. Choisnet TS/MME) Courtesy of O. Choisnet (TS/MME) Transport

Pt5 (UJ53 –R571) - Access by Pt5: only a ‘normal persons’ lift => forklift too large to pass - Access by Pt4 and Pt6: ok Travel underground until TANS ok Transport

Departure from USA15 Installation of the threaded rod Slot on the TAN top surface LHCf first installation on 15 January 2007

Detector hold on the forklift arm Removal of the detector chassis and support elevator Holding of the detector towards the TAN slot

Insertion inside the slot ( guide lines) Insertion inside the slot Removal of the threaded rod LHCf detector inside the TAN

Cable tray view Installation of the preamplifier (patch-panel) Successful installation Points to optimise: - removal of the detector from the chassis (less screws!) Transport team proposal: a box with the shape of the actual chassis - displace one screw hole than is difficult to reach when BRAN is in TAN. Manual help to insert/remove the detector inside/from the slot = difficult to be avoided => to be minimised for the installation during LHC runs

BRAN housing first installation on 22 January 2007 In shipping boxRemoval of the routing box protection Installation of the 12 mm thread adapterDetector hold on the forklift arm

Installation of ceramic spacer (rust!) Installation of ceramic spacer Holding of the detector towards the TAN slot

Insertion inside the slotStuck during insertion inside the slot!! Removal of a screw

Insertion inside the slot BRAN and LHCf detectors inside the TANBRAN detector inside the TAN Final position and removal of the threaded rod

Installation has been performed but some points have to be optimised: - decrease the thickness to allow the detector to ‘slide’ inside the TAN slot and to reach the bottom surface of the slot. - move the gas connections from the tunnel side to the machine side (cryo line side); - move the cables connectors on the routing box towards the machine side; - clean all the TAN holes that will be used to fix the BRAN detectors (ceramic spacer); - finalise the cables arrival to the detector. Manual help to insert/remove the detector inside/from the slot = difficult to be avoided => to be minimised for the installation during LHC runs BRAN first installation on 22 January 2007

- SC/RP agreed use of forklift for start-up installation and low luminosity run (L<10 30 cm -2 s -1 ) - for higher doses rates => - study to optimise the intervention - remote procedure study Contact with integration team in charge of the remote handling for the LHC element (TS/IC- K.Kershaw) Comments of Radioprotection team

LSS1 2 induced radioactivity monitors (PMI) which can be read out remotely TAN LSS5 2 induced radioactivity monitors (PMI) which can be read out remotely TAN Radiation monitoring in the TAN surrounding SC/RP + RSO - def. work procedure - radiological survey before any interventions - RAMSES monitoring close to TANs Help for - design of containers for detect. and Cu bars storage - agreement for storage locations on surface Courtesy of S. Roesler (SC/RP)

Integration in the LHC installation schedule Detectors status: LHCf arm#1= ready; LHCf arm#2= will be ready beginning of April BRAN= 2 first units ready in April; 2 last units ready in June. CMS-ZDC= 1 set is ready; the second one will be assembled at CERN in March. Point 1 LHCf and BRAN simultaneously LSS1L: first installation / commissioning: 8/01-26/01/2007 bake-out of the machine  removal on 24/01/2007 LSS1R: first installation / commissioning: 23/04-11/05/2007 bake-out of the machine  removal at the end of the period Point 5 CMS-ZDC and BRAN simultaneously 1 final installation / commissioning period (no prior period)

Final installations of all the detectors: dates under discussion (draft dates to be re-discussed) Constant discussion with - the planning team (TS/IC) and hardware commissioning team (TS/HDO) in view of the advancement of the machine installation/commissioning status - the experiments in view of a possible combined test beam in the SPS extracted lines We should keep in mind: - LHCf, ATLAS ZDC, CMS ZDC => installs./removals during LHC runs - BRAN = always in the TANs - Temporary removal if bake-out needed to restore good vacuum conditions Integration in the LHC installation schedule

Many thanks for collaboration and help to SC/GS: R. Magnier, SC/RP: S. Roesler, M. Brugger, TS/CV: M. Kuhn, TS/EL: JP Billon-Grand, L. De Jonge, JC Guillaume, A. Feron TS/HDO: hardware commissioning team: B. Perea Solano, R. Saban, TS/IC: - transport /handling team: C. Bertone, P. Minginette, S. Pelletier, J. Sakkinen - TAN team (coord. inst.): S. Bartolomé-Jimenez, G. Trinquart - infrastructure support: R. Valbuena, K. Kershaw, K. Artoos - machine planning officer: K. Foraz, H. Gaillard, S. Weisz - designers: JM Bianco, JP Corso, Y. Muttoni, E. Sabin TS/MME: O. Choisnet, F. Delsaux TS/LEA: - cabling: C. Dechelette, M. Wilhelmsson, - workshop: F. G. Murino and his team - experiments planning officer: M. Gastal - gas inst.: D. McFarlane, M. Wilhelmsson - designer: P. A. Préau TS/SU: H. Mainaud-Durand, JP Quesnel, Laure Sandri, D. Missaen AB/OP: H. Burkhardt, R. Bailey BRAN, CMS-ZDC, LHCf, ATLAS & CMS collaborations.

addendum

Installation of the detectors - run scenario Point 1 LHCf : Phase-1: Parasitic running during LHC commissioning at L< cm -2 s -1 (radiation hardness => LHCf removed when L=10 30 cm -2 s -1 ) Phase 2: Parasitic running with TOTEM (L=10 28 cm -2 s -1 ) (radiation hardness => LHCf removed at the end of the run) BRAN: Installation before LHC closure - run during all LHC lifetime ATLAS ZDC: Under discussion (rad.hard. tests to be performed this summer) Point 5 CMS ZDC: Low L pp runs (10 32 cm -2 s -1 ) + heavy ions runs BRAN: Installation before LHC closure - run during all LHC lifetime LHCf, ATLAS ZDC, CMS ZDC => installs./removals during LHC runs BRAN= always in the TANs

Radiation environment at the TAN during LHC runs TAN average residual dose vs time at L=10 34 cm -2 s -1 Courtesy of N. Mokhov (Fermilab) Simulations by N. Mokhov Radiation protection: Intervention doses: ALARA => def. of cooling period (SC/RP) CERN design criterion: 2 mSv/person/intervention 1h 1 day 1 month 1wk year days 1 month1wk1day1 hour coolig irrad. all values in  Sv/h year days 1 month1wk1day1 hour cooling irrd. all values in m Sv/h 1h 1 month 1day 1wk Averaged over aisle side of the shielding Averaged over copper bars

Co-activity of transport, LHCf and operation teams time Machine open Install. detect 2. Back to surface Go to other access point Back to surface Install. facilities + hardware commiss. detect2 Control patrol for side detect 2 Install. facilities + hardware commiss. detect 1 Back to surf. 02h4h306h307h309h3010h12h00 Control patrol for side detect 1 16h3014h30 Install. detect 1. Operation team LHCf team Transport team LHCf detectors installation (sequential mode) – first proposal Dry run of the installation in the tunnel and commissioning of the all detectors => should be performed before the LHC machine closure