Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 1 Project Management Cost and Schedule Nadine Kurita ANSI/EIA-748-A Standard.

Slides:



Advertisements
Similar presentations
MONITORING OF SUBGRANTEES
Advertisements

Module 8: Government Required Reports
More CMM Part Two : Details.
ANSI/EIA A EIA STANDARD Earned Value Management Systems Overview May 2, 2006 NDIA Program Management Systems Committee Walt Berkey, Lockheed.
Project Cost Management Estimation Budget Cost Control
ACS 567: Software Project Management Spring 2009 Instructor: Dr. John Tanik.
National Aeronautics and Space Administration ANSI/EIA-748-B Earned Value Management Systems (EVMS) 32 Guidelines ANSI/EIA-748-B Earned Value.
Monitoring and Control Earned Value Management (EVM)
Project Management Session 7
Chapter 3: The Project Management Process Groups
Chapter 5: Project Scope Management
Section 4.0 Project Implementation. Factors that Ensure Success  Update the project plan  Stay within scope  Authorized change implementation  Providing.
FRA’s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011 Dean Hoffer Head, Office of Project Management Oversight.
ANSI/EIA -748 EVMS 32 Guidelines National Aeronautics and Space Administration.
Project Cost Management J.-S. Chou, P.E., Ph.D.. 2 Learning Objectives  Explain basic project cost management principles, concepts, and terms.  Discuss.
Module 9 Session 9.2 Visual 1 Module 9 Designing Control and Reporting Systems (Time, Cost, Resources and Scope (Performance and Quality)) Session 9.2Managing.
EVMS Refresher and Update Training
Validating IPMRs, CPRs, and IMS Deliverables NAVY CEVM
Project Management Process Overview
Edward B. Farkas, Managing Director, Project Management Practice
BSBPMG503A Manage Project Time Manage Project Time Unit Guide Diploma of Project Management Qualification Code BSB51507 Unit Code BSBPMG503A.
Dave Bachman DAU / CDSC September 9, 2004
FRA’s Earned Value Management System Overview for Self Assessment Surveillance March 12-14, 2012 Dean Hoffer Head, Office of Project Management Oversight.
Trish Mast External Independent October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October.
PPMT CE-408T Engr. Faisal ur Rehman CED N-W.F.P UET P.
1 Cost Benefit EVM at DOT Presented to: Joint Industry – Government NDIA PMSC session Presented by: H. Giovanni Carnaroli Associate CIO, IT Policy Oversight.
Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management.
Software Project Management (SPM)
Management & Development of Complex Projects Course Code - 706
ISM 5316 Week 3 Learning Objectives You should be able to: u Define and list issues and steps in Project Integration u List and describe the components.
Management & Development of Complex Projects Course Code MS Project Management Earned Value Concepts Lecture # 19.
Lab-Wide Earned Value Management System Project Core Team Kickoff Meeting April 16, 2008 Dean A. Hoffer.
I n t e g r i t y - S e r v i c e - E x c e l l e n c e Business & Enterprise Systems The Integrated Master Plan (IMP) and the Integrated Master Schedule.
Felix Sanchez Estimating the Budget and Cost (Part 1) Project Management for ARA Engineers and Scientists Developing a Bottoms Up Estimate.
Scope Management Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Chapter 5 Learning Objectives After completing this chapter,
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall o P.I.I.M.T o American University of Leadership Ahmed Hanane, MBA, Eng, CMA, Partner.
W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 1 Project Management W. J. Foyt Project Scope Timeline Cost Estimate.
Develop Project Charter
PU-PPPL Earned Value Management System Overview Thomas Egebo October 4-6, 2011 Princeton University Plasma Physics Laboratory EVMS Certification Review.
Felix B. Fernandez LUSI DOE Review August 20, 2008 PMCS Overview p. 1 LCLS Ultrafast Science Instruments (LUSI) Felix B. Fernandez.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science Office of Science Review of the LCLS.
Management & Development of Complex Projects Course Code - 706
Mark Reichanadter LCLS October 9-11, 2007 LCLS BCR Overview and EIR LOIs Project Progress / Status Revised Project Baseline.
The Project Plan Plan Your Work, then Work Your Plan
Strykowsky 1Project Review November 2, 2005 NCSX Project Review November 2, 2005 Cost and Schedule Ron Strykowsky.
Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 1 Project Management Cost and Schedule Nadine Kurita ANSI/EIA-748-A Standard.
6/6/ SOFTWARE LIFE CYCLE OVERVIEW Professor Ron Kenett Tel Aviv University School of Engineering.
DOE Review of LARP – Feb 17-18, 2014 DOE Critical Decision Process Ruben Carcagno February 17,
EARNED VALUE  Earned Value Management Systems  Earned Value Analysis.
Cost and Schedule Breakout Session Paul Weinman Pacific Northwest National Laboratory.
Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
FRA Earned Value Management System January 9, 2009 Dean Hoffer.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
Project Management PTM721S
ANSI/EIA-748-B Earned Value Management Systems (EVMS)
Project Management W. J. Foyt
Project Cost Management
Project Integration Management
EVM 202—Lesson 3 EVMS Guidelines and Compliance
LSST Project EVMS Performance Overview Kevin E
Scope management Chapter 5 Copyright ©2016 Pearson Education, Inc.
CIS12-3 IT Project Management
DOD’S PHASED SYSTEM DEVELOPMENT PROCESS
Linac Coherent Light Source (LCLS)
PMCS Approach - Past and Current Projects
EVMS Status and Overview
Linac Coherent Light Source (LCLS)
Linac Coherent Light Source (LCLS)
Linac Coherent Light Source (LCLS)
Managing Project Work, Scope, Schedules, and Cost
Presentation transcript:

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 1 Project Management Cost and Schedule Nadine Kurita ANSI/EIA-748-A Standard for Earned Value Management Systems Organization Planning, scheduling and budgeting Accounting considerations Analysis and management reports Revisions and data management (not covered) EVMS surveillance ANSI/EIA-748-A Standard for Earned Value Management Systems Organization Planning, scheduling and budgeting Accounting considerations Analysis and management reports Revisions and data management (not covered) EVMS surveillance

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 2 Contributers Patricia Mast (LCLS, Aim Corporation - Deltek) Jeff Chan (LCLS, Aim Corporation - Deltek) Patricia Mast (LCLS, Aim Corporation - Deltek) Jeff Chan (LCLS, Aim Corporation - Deltek)

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 3 EVMS Organization J. Hastings Project Director N. Kurita Chief Engineer WBS 1.4 XCS N. Kurita – acting WBS 1.2 XPP R. Pope WBS 1.3 CXI J.C. Castagna - acting WBS 1.5 Diagnostics N. Kurita WBS 1.6 Controls & Data System G. Haller PMCS B. Foyt – Project Manager H. Leung Organizational Breakdown Structure (OBS)

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 4 EVMS Organization Work Breakdown Structure (WBS)

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 5 EVMS Organization Responsibility Assignment Matrix In process Responsibility Assignment Matrix In process

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 6 Planning, Scheduling and Budgeting (2) Earned value performance. LUSI Project Management Cost & Schedule (PMCS) system is based on, B-Factory Project Award for the Program and Project Management SPEAR3 – 2004 Secretary's Excellence in Acquisition Award GLAST LCLS 60% CAMS previous experience in PEP-II,SPEAR3, GLAST and/or LCLS System requirements D.O.E. Order 413.3A “Program and Project Management” ANSI/EIA-748-A Standard for Earned Value Management Systems Earned value performance. LUSI Project Management Cost & Schedule (PMCS) system is based on, B-Factory Project Award for the Program and Project Management SPEAR3 – 2004 Secretary's Excellence in Acquisition Award GLAST LCLS 60% CAMS previous experience in PEP-II,SPEAR3, GLAST and/or LCLS System requirements D.O.E. Order 413.3A “Program and Project Management” ANSI/EIA-748-A Standard for Earned Value Management Systems

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 7 Planning, Scheduling and Budgeting Documentation LCLS Control Account and Work Package Planning LCLS Project Schedule LCLS Cost Estimating LCLS Earned Value Management System Description Documentation LCLS Control Account and Work Package Planning LCLS Project Schedule LCLS Cost Estimating LCLS Earned Value Management System Description

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 8 Cost Estimate PMCS CAM Chief Engineer Project Director

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 9 Detailed Cost Estimate Report (DCE) Product – sample report

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 10 Project Schedule PMCS CAM Chief Engineer Project Director DOE SSO

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 11 Project Schedule PMCS CAM Chief Engineer Project Director DOE SSO

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 12 Milestone Hierarchy Defined Level 1, 2, 3 and 4 Milestones Level 1 controlled by DOE HQ Level 2 controlled by DOE Stanford Site Office Level 3 controlled by LUSI Project Director Level 4 controlled by System Manager Level 1-3 Milestones are under formal CCB control Defined Level 1, 2, 3 and 4 Milestones Level 1 controlled by DOE HQ Level 2 controlled by DOE Stanford Site Office Level 3 controlled by LUSI Project Director Level 4 controlled by System Manager Level 1-3 Milestones are under formal CCB control

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 13 Work Authorization

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 14 Resource Loaded Schedules Integrate schedules

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 15 Accounting Considerations All financial transactions are documented, approved, and recorded properly in the financial accounting system on a consistent and timely basis in accordance with Generally Accepted Accounting Principles (GAAP) and applicable Cost Accounting Standards. Actual costs are collected from the financial accounting systems and imported into the EVMS each month. Actuals are collected in the EVMS in four basic cost elements Labor Non-Labor (materials, Subcontracts, etc) Shops Travel Direct and indirect costs are recorded in a manner consistent with the budgets. All financial transactions are documented, approved, and recorded properly in the financial accounting system on a consistent and timely basis in accordance with Generally Accepted Accounting Principles (GAAP) and applicable Cost Accounting Standards. Actual costs are collected from the financial accounting systems and imported into the EVMS each month. Actuals are collected in the EVMS in four basic cost elements Labor Non-Labor (materials, Subcontracts, etc) Shops Travel Direct and indirect costs are recorded in a manner consistent with the budgets.

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 16 Analysis and Management Reports Documentation LCLS Earned Value Management System Description LCLS Monthly Status and Reporting Documentation LCLS Earned Value Management System Description LCLS Monthly Status and Reporting

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 17 Monthly Status and Reporting PMCS CAM Chief Engineer Project Director

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 18 Monthly Status and Reporting PMCS CAM Chief Engineer Project Director

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 19 CPR Drilldown (Level 2)

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 20 CPR Drilldown (Level 3)

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 21 CPR Drilldown (CA Level)

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 22 CPR Drilldown (Milestone Level)

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 23 CPR Drilldown (Labor Detail)

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 24 CPR Drilldown (Cost Detail)

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 25 Variance Analysis Form

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 26 LCLS PMCS Utilities (The Hammer)

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 27 BCWS, BCWP,ACWP Report (SPA)

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 28 Obligation Report (OSCUM)

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 29 Total Float Report Level 3 milestones

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS Actual cost and commitments are collected, via code of accounts, at the 3 rd or 4th level of the WBS 1. The cost estimating information was transferred to Primavera for initial budget & obligation time- phasing 2. Progress information is gathered from the CAMS and input into the scheduling system for baseline variance and critical path analysis 3. Progress information is transferred from the scheduling system into the cost processor for Earned Value calculations 5. Accounting files are transferred electronically to the PMCS group and imported into Cobra. Reconciled every month. 6. Technical/Cost/Schedule Baseline changes are controlled and documented through the change control process 7. Utility tools for CAMS and management. View Gant charts, plot performance, trending reports, CPR drilldown

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 31 Surveillance Continuous self assessment is performed by the project director, and project controls personnel, who are trained in the correct use of the LCLS EVMS, and are held accountable for proper implementation. Conduct external audit yearly LCLS Surveillance of EVMS Continuous self assessment is performed by the project director, and project controls personnel, who are trained in the correct use of the LCLS EVMS, and are held accountable for proper implementation. Conduct external audit yearly LCLS Surveillance of EVMS

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 32 Summary Consistent with the 32 critical criteria as described in ANSI/EIA- 748-A Applying the existing LCLS documentation for Planning, scheduling and budgeting Accounting considerations Analysis and management reports Revisions and data management PMCS staff is from LCLS CAMS have experience with PMCS – training will continue to ensure compliance with the ANSI standard Have a detailed resource loaded schedule for CD4a deliverables Detailed resource loaded schedule for the remainder items in process Need to work on the interface with partner labs LUSI staff is ready to baseline the project! Consistent with the 32 critical criteria as described in ANSI/EIA- 748-A Applying the existing LCLS documentation for Planning, scheduling and budgeting Accounting considerations Analysis and management reports Revisions and data management PMCS staff is from LCLS CAMS have experience with PMCS – training will continue to ensure compliance with the ANSI standard Have a detailed resource loaded schedule for CD4a deliverables Detailed resource loaded schedule for the remainder items in process Need to work on the interface with partner labs LUSI staff is ready to baseline the project!

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 33 End of Presentation

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 34 Execution and Control Project Office Monthly Reporting Contents Cost Drill Down Approach Top Level SPA Chart Cost Report – WBS Level 2 (C/SSR) System Level Cost Report – WBS Level 3 Work Package Detail Cost Report Detailed Accounting Report Schedule Drill Down Approach Top Level Cost Report – WBS Level 2 System Level Cost Report – WBS Level 3 Work Package Detail Cost Report Detailed Schedule Report Traditional Schedule Analysis Critical Path, Detailed Baseline Schedule Variance Comparison, Milestone Chart Project Office Monthly Reporting Contents Cost Drill Down Approach Top Level SPA Chart Cost Report – WBS Level 2 (C/SSR) System Level Cost Report – WBS Level 3 Work Package Detail Cost Report Detailed Accounting Report Schedule Drill Down Approach Top Level Cost Report – WBS Level 2 System Level Cost Report – WBS Level 3 Work Package Detail Cost Report Detailed Schedule Report Traditional Schedule Analysis Critical Path, Detailed Baseline Schedule Variance Comparison, Milestone Chart

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 35

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 36 Revisions and Data Management Documentation LCLS Earned Value Management System Description LCLS Change Control Documentation LCLS Earned Value Management System Description LCLS Change Control

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 37 Revisions and Data Management Level 4 up to 100K, system Level 3, project office

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 38 CCB Presentations PBCR presentations to the CCB will address the following; Background Problem Solution Other Solutions Considered Stakeholders Review Other System Managers, Int/Inst, QA, Accel Team, QA, Linac Dept Hd (if applicable) Impact of this BCR (technical, resources, funding, etc.) Must this come from contingency? Any impact to L2 or L3 milestones? Integrated Schedule Analysis Impact of not approving this BCR Affected drawings, parts or requirements Is there anything else we should know? PBCR presentations to the CCB will address the following; Background Problem Solution Other Solutions Considered Stakeholders Review Other System Managers, Int/Inst, QA, Accel Team, QA, Linac Dept Hd (if applicable) Impact of this BCR (technical, resources, funding, etc.) Must this come from contingency? Any impact to L2 or L3 milestones? Integrated Schedule Analysis Impact of not approving this BCR Affected drawings, parts or requirements Is there anything else we should know?

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 39 Revisions and Data Management

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 40 BCR Form

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 41 Revisions and Data Management

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 42 Approval Thresholds

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 43

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 44 Resource Breakdown Structure RBS - BE WBS FUND

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 45 Accounting Considerations Direct and indirect costs can be summarized from control accounts into the WBS without allocation of a single control account to more than one WBS element. Direct and indirect costs can be summarized by the project’s organizational elements without allocation of a single control account to more than one organizational element. Indirect costs are applied to each project at the current approved annual rates. Encumbrances are recognized at the point an approved order is placed. Equipment and material costs enter the general ledger through the accounts payable system. Retroactive adjustments to previously reported actual costs are prohibited. Adjustments are reported monthly, consistent with GAAP. Direct and indirect costs can be summarized from control accounts into the WBS without allocation of a single control account to more than one WBS element. Direct and indirect costs can be summarized by the project’s organizational elements without allocation of a single control account to more than one organizational element. Indirect costs are applied to each project at the current approved annual rates. Encumbrances are recognized at the point an approved order is placed. Equipment and material costs enter the general ledger through the accounts payable system. Retroactive adjustments to previously reported actual costs are prohibited. Adjustments are reported monthly, consistent with GAAP.

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 46 More on reporting

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 47 Milestone Dictionary

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 48 Responsibility Assignment Matrix (RAM)

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 49 Corrective Action Log

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 50 Estimate at Complete (EAC)

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 51 Risk Registry

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 52 CCB Log of Proposed BCRs

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 53

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 54 PMCS Baseline Development Baseline Development Step 1 Detailed Schedule Development Step 2 Schedule Integration Step 3 Establish the Performance Measurement Baseline Step 4 Funding Reconciliation Step 5 Integrate the Cost and Schedule Baseline Baseline Development Step 1 Detailed Schedule Development Step 2 Schedule Integration Step 3 Establish the Performance Measurement Baseline Step 4 Funding Reconciliation Step 5 Integrate the Cost and Schedule Baseline

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 55 PMCS Baseline Development (2) STEP 1 – Detailed Schedule Development 100% of scope covered for CXI and XPP Simplest approach is to schedule the WBS Logic-driven schedule networks Consistent use of calendars, units and resources for reliable calculations Identify interfaces (Needs and Avails) with other systems Proper activity coding for reporting and summarization STEP 1 – Detailed Schedule Development 100% of scope covered for CXI and XPP Simplest approach is to schedule the WBS Logic-driven schedule networks Consistent use of calendars, units and resources for reliable calculations Identify interfaces (Needs and Avails) with other systems Proper activity coding for reporting and summarization

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 56 PMCS Baseline Development (3) STEP 3 – Establishing the PMB Develop the work packages Cost load the schedule to establish the budget and obligation profiles Identify performance measurement techniques STEP 4 – Funding Reconciliation Typically, the ‘bottoms-up’ plan yields a different funding requirement than what has already been established from the ‘Top-down’, requiring schedule iterations Identify and correct funding issues at lowest level of detail plan fit within the existing funding constraints STEP 3 – Establishing the PMB Develop the work packages Cost load the schedule to establish the budget and obligation profiles Identify performance measurement techniques STEP 4 – Funding Reconciliation Typically, the ‘bottoms-up’ plan yields a different funding requirement than what has already been established from the ‘Top-down’, requiring schedule iterations Identify and correct funding issues at lowest level of detail plan fit within the existing funding constraints

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 57 PMCS Baseline Development (4) STEP 5 – Integrate Cost/Schedule Baseline

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 58 Resource Breakdown Structure RBS - BE WBS FUND

Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 59 Green : CPI or SPI between 0.90 and 1.15 Yellow: CPI or SPI between 0.85 and 0.89 Red: CPI or SPI below 0.85 or above 1.25 Blue: CPI or SPI between 1.16 and 1.25 The ones that aren't shaded in are variances that are less than $10,000 (too small to worry about). These thresholds (except for the Blue one) are the same as the PARS System thresholds. We require our CAMs to write VARs for all reds, yellows and blues at WBS level 3. Green : CPI or SPI between 0.90 and 1.15 Yellow: CPI or SPI between 0.85 and 0.89 Red: CPI or SPI below 0.85 or above 1.25 Blue: CPI or SPI between 1.16 and 1.25 The ones that aren't shaded in are variances that are less than $10,000 (too small to worry about). These thresholds (except for the Blue one) are the same as the PARS System thresholds. We require our CAMs to write VARs for all reds, yellows and blues at WBS level 3.