Bulding 245 schedule update LIU Booster Meeting 27-03-2014 Fulvio Boattini & Michel Obrecht TE-EPC / EN-CV TEEPC.

Slides:



Advertisements
Similar presentations
Engineering Department EN Cooling and Ventilation issues 1 FUTURE EXPLOITATION OF THE EAST AREA EN-CV Michel OBRECHT.
Advertisements

31.March.2004 C. A. Martins, CERN AB/PO 1 Analysis of the possibility of using of a ALICE/LHCb type power converter in TT2A target test by Carlos DE ALMEIDA.
CURRENT STATUS OF CV INSTALLATIONS, WORKS DURING LS1 AND PROBLEMS ENCOUNTERED DURING START-UP NORTH AREA Bill Bannister / Jani Lehtinen EATM – 7 th October.
For more information, please contact 19/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
PSB Main Power Supply Serge Pittet Jean-Paul Burnet, Karsten Kahle, Fulvio Boattini, Max Chamiot-Clerc TE-EPC Serge PITTET LIU-2011 Event, 25/11/2011.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
Power converters implications for Booster Energy Upgrade Jean-Paul Burnet, Serge Pittet LIU day, TEEPC.
IT-4103/EN Bidder’s conference Technical Specification for the Design, Supply, Installation and Commissioning of an HVAC system, a Smoke Extraction system.
PSB MPS Building 245 CV Status EN-CV-PJMichel OBRECHT – Frédéric TEIXEIRA
IMPACTS OF INSTALLING THE REFERENCE MAGNET PLACEMENT IN B december 2014 Fulvio Boattini & Natacha Lopez Hernandez.
EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
ISOLDE: Status report building th ISCC meeting CERN, 31 March 2014 Erwin Siesling, Magda Kowalska.
Electrical & Control Power Supplies Trevor Hartnett.
Cooling Loads. Critical System P&ID Critical system Main issues Oversized chillers Issues with switch over By-pass valve AHU5A/B? Looking at the T and.
Progress with POPS Jean-Paul Burnet TE/EPC IEFC workshop, Feb 2010.
Claudio Bortolin. 1 st June: PT100 electrical connection failure (Temp Chiller water In&Out) 1) it required an access to the cavern to be fixed 2) access.
IT-4082 Design, Supply, Installation and Commissioning of the ventilation of the BAF3 building Alexandre Broche EN-CV-PJ.
ISOLDE: Status report building th ISCC meeting CERN, 22 October 2013 Maria Borge, Erwin Siesling.
19 th November 2010EN/CV/DC Thermosiphon project IV review - Overall cost estimation and planning Michele Battistin Elena Perez Rodriguez 19 th November.
European Organization for Nuclear Research - Organisation européenne pour la recherche nucléaire SSD/SDD Proposal Upgrade 30/08/2012
Bulding 245 schedule update LIU Booster Meeting Fulvio Boattini TE-EPC TEEPC.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1.chilled / mixed.
AD/ELENA (B193) Hall Extension F. Butin. Status The need of a new building for AD was already discussed in 2010, First pre-study shown to GTPE 1st Sept.
COOLING & VENTILATION FOR THE DRIVE BEAM TUNNEL M Nonis – EN/CV – 16/9/2009 CLIC TWO BEAM MODULES REVIEW
BI.DIS10: Magnets & generators R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November
Update on the Laser Beam Line
The Building 180 Cryogenic infrastructure water cooling system Stefano Moccia, EN-CV Coordination meeting 26/09/14.
First results from the study of the LHC cycle power consumption FCC I&O meeting 24 th June 2015 Davide Bozzini With the contribution of G. Burdet, B. Mouche,
The Building 180 Cryogenic infrastructure water cooling system Status Update Stefano Moccia, EN-CV Coordination meeting 14/10/15.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
Thermosiphon project management and quality assurance EN/CV/DC Presentation done by Elena Perez Rodriguez For further information contact
Engineering Department EN 1 IT3853-EN Design, Supply of Ventilation Units and Smoke Extraction Systems for Building 192 Bidder’s conference – 29 th April.
ISOLDE: Status report building th ISCC meeting CERN, 24 June 2014 Erwin Siesling, Magda Kowalska.
For more information, please contact 14/12/2010 EN/CV/DC Technical specification IT-3684 by Elena Perez Rodriguez.
1 S-FRS Magnet Test Bench SuperFRS Magnet Test Bench Power Converter Status H. Thiesen 13 May 2015.
Layout Experimental hall Final status (?) 3rd HIE ISOLDE Physics Coordination Group meeting CERN, 3 September 2012 HIE-ISOLDE Erwin Siesling.
A.Henriques (JCOV meeting 31/5/2001) ATLAS Calorimeter cooling project Goal: u Definition of a common frame work for the cooling of the ATLAS calorimeter.
Serge Pittet (Work-Package holder) Konstantinos Papastergiou (Work-unit: Sirius converters) CERN Technology Department | Electrical Power Converters 12.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/21.
SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 15 th August 2012.
110 th November 2010EN/CV/DC Detector Cooling Project - advancement status of Work Package N3 Thermosiphon project Michele Battistin 18 May 2011.
COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016.
Technical Review EHN1 Extension Cooling Systems and Pipework Jérôme Rodary / EN-CV.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
Two half-day seminars on the remaining work packages to complete the MEDICIS Facility POWER CONVERTERS FOR MEDICIS Davide Aguglia & Julien Parra-Lopez.
V Thermo-siphon Workshop Test protocol Jan Godlewski PH/DT-PO On behalf of thermo-siphon working group
ELENA installation progress F. Butin / ELENA collaboration.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/14.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/02/04.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
S A Griffiths CM42 June 2015 Electrical & Control.
POPS-B Project Update 07 June 2016 POPS-B: Project update and Feedback from POPS Experience LIU-PSB Meeting June 2016 Fulvio Boattini TE/EPC 2.
Update on the PSB Cooling and Ventilation Systems
SR1 extension follow up 27-Mar-17 Marco Ciapetti.
CBETA Technical Review
Building 107 Update Introduction Project team Location Design status
TE/EPC activities for LINAC 2, PSB, PS & TT2 during EYETS
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS EN-CV Planning LS (initial draft)
B245 Modifications & Cabling Update
Cooling systems for HL-LHC (WP17.3)
EN-CV interventions during EYETS for PS and PSB
COOLING & VENTILATION INFRASTRUCTURE
TE-MSC activities in SPS during YETS
PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
Maintenance at ALBA facility: Strategy for the conventional services
Aziz AMAMOU EACM – 21th May 2019
LINAC 3 Meeting ICL machines Injectors
Presentation transcript:

Bulding 245 schedule update LIU Booster Meeting Fulvio Boattini & Michel Obrecht TE-EPC / EN-CV TEEPC

Building 245 position 2 TEEPC b245 27/03/2014 Fulvio Boattini & Michel Obrecht

physicsLS1physicsLS2physics May 2016 Building Ready No resources Services Integration (EL, CV,..) GS/SE studies and procurement Building construction October 2013 April 2014 March 2015 FC April 2017 Start Commissioning on dummy load MPSB Time Schedule Switching cabinets and cabling installation 3 TEEPC Magnet switch cables. Paths A, C, D Magnet switch cables: Paths B Main AC Power Cables B367 Dummy load Cables B245 aux power cables Cable purchase Cabling integration studies 27/03/2014 Fulvio Boattini & Michel Obrecht

Review of cooling and HVAC requirements for Booster MPS 27/03/20144 TEEPC All circuits are aluminium A 20um mechanical filter is required before entering the converters Water flow will be adjusted to its nominal value during commissioning by means of dedicated regulation valves During operation one of the 3 sets of circuits (and/or the spare circuit) could be disconnected. The flow in the other circuits shall remain the same (regulation and on-off valves separated). ADDED Fulvio Boattini & Michel Obrecht

Review of cooling and HVAC requirements for Booster MPS 27/03/20145 TEEPC Fulvio Boattini & Michel Obrecht

Building 245 CV Conceptual Design URS inputs Cooling power on water: confirmed 470 kW = 2 units at 100% + 30% of the third unit Flow rate, delta T of 2.3 °C, Conductivity of the water confirmed, maxi 0,8 micro S/cm at 30 °C, Need to run independently : 2 fully independent stations for cooling located in the new building, Requirements for internal temperature revised, 26 °C in summer with maxi of 30 °C during limited periods Conceptual Design based on : Independent cooling station : Cost optimised Air conditioning system : No chilled water, Units placed on the roof, 27/03/2014 Fulvio Boattini & Michel Obrecht 6 TEEPC

27/03/2014 Fulvio Boattini & Michel Obrecht 7 TEEPC Building 245 CV Conceptual Design

27/03/2014 Fulvio Boattini & Michel Obrecht 8 TEEPC Building 245 CV Conceptual Design

27/03/2014 Fulvio Boattini & Michel Obrecht 9 TEEPC Building 245 CV Conceptual Design

27/03/2014 Fulvio Boattini & Michel Obrecht 10 TEEPC CV Integration

27/03/2014 Fulvio Boattini & Michel Obrecht 11 TEEPC CV Integration

27/03/2014 Fulvio Boattini & Michel Obrecht 12 TEEPC CV Integration

27/03/2014 Fulvio Boattini & Michel Obrecht 13 TEEPC CV Integration

B245 Integration Milestones 14 TEEPC Update of the Electrical Power Consumption: 17th March /03/2014 Fulvio Boattini & Michel Obrecht Update of the Electrical Network schematic: 28th March 2014 Final Decision on Dummy Load by TE/EPC: 17th March 2014 Decision on number of galleries between b271 and b245: 24th March 2014 Integration of major CV 3D components in the b245 model: 28th March 2014 Update of integration of EN/EL cabinets: 28th March 2014 Final Modification of b245 structure: 11th April 2014 Integration of pipes, cables ladders and others: 25th April 2014

B245 Integration Milestones 15 TEEPC Update of the Electrical Power Consumption: 17th March /03/2014 Fulvio Boattini & Michel Obrecht USERPOWER [kW]COMMENTREFERECENCE EN/CV135 Water cooling and towers b.245 M.Obrecht 08/03/2013 TE/EPC392Auxiliaries F.Boattini 22/11/2013 QTR power converters + all Converters and capacitor rooms aux TE/EPC6750 N.3 transformer 2.7 MVA F.Boattini 22/11/2013 EN/EL70 Lights, sockets, OH crane - b.245 F.Boattini 22/11/2013 EN/CV153HVAC b.245M.Obrecht 08/03/2013 TE/EPC15Auxiliaries which need UPSF.Boattini 22/11/2013 EN/CV8Smoke extractionM.Obrecht 08/03/2013 EN/EL25Emergency light, fire detectionF.Boattini 22/11/2013 P. Converters power: 6750kW Auxiliaries EPC: 392kW+15kW UPS Auxiliaries CV: 288kW B245:103kW

B245 Integration Milestones 16 TEEPC Update of the Electrical Power Consumption: 17th March /03/2014 Fulvio Boattini & Michel Obrecht Update of the Electrical Network schematic: 28th March 2014 Final Decision on Dummy Load by TE/EPC: 17th March 2014 Decision on number of galleries between b271 and b245: 24th March 2014 Integration of major CV 3D components in the b245 model: 28th March 2014 Update of integration of EN/EL cabinets: 28th March 2014 Final Modification of b245 structure: 11th April 2014 Integration of pipes, cables ladders and others: 25th April 2014

B245 Integration Milestones 17 TEEPC 27/03/2014 Fulvio Boattini & Michel Obrecht Final Decision on Dummy Load by TE/EPC: 17th March 2014 Approved by Serge Deleval

B245 Integration Milestones 18 TEEPC Update of the Electrical Power Consumption: 17th March /03/2014 Fulvio Boattini & Michel Obrecht Update of the Electrical Network schematic: 28th March 2014 Final Decision on Dummy Load by TE/EPC: 17th March 2014 Decision on number of galleries between b271 and b245: 24th March 2014 Integration of major CV 3D components in the b245 model: 28th March 2014 Update of integration of EN/EL cabinets: 28th March 2014 Final Modification of b245 structure: 11th April 2014 Integration of pipes, cables ladders and others: 25th April 2014

B245 Integration Milestones 19 TEEPC 27/03/2014 Fulvio Boattini & Michel Obrecht Decision on number of galleries between b271 and b245: 24th March _V1_Booster_2GeV_cabling docx (2 Mb) pdf (923 Kb)docxpdf

B245 Integration Milestones 20 TEEPC Update of the Electrical Power Consumption: 17th March /03/2014 Fulvio Boattini & Michel Obrecht Update of the Electrical Network schematic: 28th March 2014 Final Decision on Dummy Load by TE/EPC: 17th March 2014 Decision on number of galleries between b271 and b245: 24th March 2014 Integration of major CV 3D components in the b245 model: 28th March 2014 Update of integration of EN/EL cabinets: 28th March 2014 Final Modification of b245 structure: 11th April 2014 Integration of pipes, cables ladders and others: 25th April 2014

B245 Integration Milestones 21 TEEPC 27/03/2014 Fulvio Boattini & Michel Obrecht Update of the Electrical Network schematic: 28th March 2014 DGS-SEE would like to have an UPS for smoke extraction. EN-EL replies it is not justified and not “CERN standard”.

B245 Integration Milestones 22 TEEPC Update of the Electrical Power Consumption: 17th March /03/2014 Fulvio Boattini & Michel Obrecht Update of the Electrical Network schematic: 28th March 2014 Final Decision on Dummy Load by TE/EPC: 17th March 2014 Decision on number of galleries between b271 and b245: 24th March 2014 Integration of major CV 3D components in the b245 model: 28th March 2014 Update of integration of EN/EL cabinets: 28th March 2014 Final Modification of b245 structure: 11th April 2014 Integration of pipes, cables ladders and others: 25th April 2014

WU baselines 23 TEEPC 27/03/2014 Fulvio Boattini & Michel Obrecht Excel file

24 THANKS FOR THE ATTENTION QUESTIONS? Bulding 245 schedule update TEEPC 27/03/2014 Fulvio Boattini & Michel Obrecht

Building 245 layout 25 TEEPC 27/03/2014 Fulvio Boattini & Michel Obrecht

Building 245 layout 26 TEEPC 27/03/2014 Fulvio Boattini & Michel Obrecht

Building 245 layout (b271 side) 27 TEEPC 27/03/2014 Fulvio Boattini & Michel Obrecht

Building 245 layout (Isolde side) 28 TEEPC 27/03/2014 Fulvio Boattini & Michel Obrecht

Building 245 layout 29 TEEPC 27/03/2014 Fulvio Boattini & Michel Obrecht

Building 245 layout 30 TEEPC 27/03/2014 Fulvio Boattini & Michel Obrecht

Building 245 layout 31 TEEPC 27/03/2014 Fulvio Boattini & Michel Obrecht

Building 245 layout 32 TEEPC 27/03/2014 Fulvio Boattini & Michel Obrecht