Optoboards dependence on Temperature C. Gemme, T.Flick detector meeting, April 2 nd 2009 Motivations Test in SR1 thanks to K. Lantzsch, L.Masetti, J.Moss,

Slides:



Advertisements
Similar presentations
André Augustinus 15 March 2003 DCS Workshop Safety Interlocks.
Advertisements

BCAL Interlock System US BCAL Chiller US BCAL MPOD 1 US BCAL PLC Pulsed Output from Flow meter to PLC From US BCAL cooling loop US BCAL MPOD 1 RS485 from.
SPD commissioning Ricci, Míriam, Daniel, Edu, Hugo et al. from 1.
LHC progress Thursday 30 th April 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Slide 1UCSB CMS Weekly Status MeetingCMS 4-Hybrid Test System Sam Burke EE UCSB 4-Hybrid Thermal Test System Status Peltier T/E Element Failures 3 September.
Atlas SemiConductor Tracker Andrée Robichaud-Véronneau.
Cluster Threshold Optimization from TIF data David Stuart, UC Santa Barbara July 26, 2007.
2011 HV scan SF6 flow-meter accident 2011 Results comparison RPC HV efficiency scan Pigi Paolucci on behalf of RPC collaboration.
UM PPS Lab Activities - HV Readout Long Run - Single Source Saturation Test PPS meeting April 30, 2012.
PP2 Status F. Bellina. Problem solved.. Problem with inhibit and reading temperature and many crazy behavior Solved with a new FPGA firmware: the hardware.
CMS FPIX Reinstallation/Commissioning Lorenzo Uplegger 4/20/091.
Gusev Konstantin, Kurchatov Institute / JINR , Gerda meeting Some technical aspects of testing and adaptation of existing detectors.
Session th January 2010 R.Schmidt TE/MPE Hardware Commissioning 2010 and beyond R.Schmidt.
Dogleg Thermal Tests : Configuration 7 6 AiN plate side Jan SM+LB 8 Dogleg side Heater (0.4W) flow 2 Temperature sensors located.
TAU status 14/2/2012. Temperature behavior in red Delayed response No A/C T=24-25 C 19 o C Cold A/C T=19-20 C 30 o C Hot A/C T=28-32 C 16:30 18:00 04:00.
Performance Tests and Control for the TRD-HV A. Markouizos, A. Petridis, S. Potirakis, M. Tsilis, M. Vassiliou Athens University ALICE DCS Workshop CERN.
Low Voltage LB status RPC detector and trigger group.
Status of NA62 straw electronics and services Peter LICHARD, Johan Morant, Vito PALLADINO.
Id week, , Kerstin Lantzsch Joachim Schultes University of Wuppertal FSM configuration and functionality - current status - plans.
Evaporative Heater Design, qualification and planning M.Olcese PRR SCT off-detector cooling PRR SCT off-detector cooling March March 2005.
Commissioning and Operation of the CMS Tracker analogue optical link system at TIF with CMSSW: R.Bainbridge, A.Dos Santos Assis Jesus, K.A.Gill, V. Radicci.
26JUN08Calo Piquet Training Session - Xvc1 DCS and DSS Xavier Vilasis.
Ideas about Tests and Sequencing C.N.P.Gee Rutherford Appleton Laboratory 3rd March 2001.
Status of the Remote HV System 10 June 2015 TileCal week, upgrade session Roméo Bonnefoy, Romain Madar and François Vazeille ● Summary of performances.
Calo Piquet Training Session - Xvc1 DCS and DSS Cuvée 2015 – RUN2 Xavier Vilasís-Cardona.
IDE DCS development overview Ewa Stanecka, ID Week, CERN
START NICMOS COOLING SYSTEM ACTIVITY SUMMARY. 1/25/01Ken Pulkkinen2 START NCS ACTIVITY Applicable SMOV Requirements: J NICMOS Cooling System.
Power Up of the First VELO Module at IP8 Eddy & Olaf on behalf of the VELO group.
TIPS - Oct 13, 2005 M. Sirianni Temperature change for ACS CCDs: initial study on scientific performance M. Sirianni, T. Wheeler, C.Cox, M. Mutchler, A.
CERN, CT Workshop, ID Week, July 2 nd, 2007 Problems and solutions during the integration. Unconformities in the detector Claudia Gemme, CERN - INFN Genova.
Report from Florence Bonding of Modules L12p Mirko Brianzi 20 April 2004.
Pixel DQM Status R.Casagrande, P.Merkel, J.Zablocki (Purdue University) D.Duggan, D.Hidas, K.Rose (Rutgers University) L.Wehrli (ETH Zuerich) A.York (University.
1 Calorimeters LED control LHCb CALO meeting Anatoli Konoplyannikov /ITEP/ Status of the calorimeters LV power supply and ECS control Status of.
Oct/07/2010Pixel PP0 opto replacement issues1 1 1 PP0 Opto Replacement Issues Philippe Grenier, Martin Kocian, Dave Nelson, Marco Oriunno, Su Dong, Charlie.
24/03/2010ALICE TOF General Meeting March TOF hardware and data taking 2010 Andrea Alici Museo Storico della Fisica e Centro Studi e Ricerche “Enrico.
1 Chapter 9 Tuning Table Access. 2 Overview Improve performance of access to single table Explain access methods – Full Table Scan – Index – Partition-level.
FE-I4 irradiated chip tests at low temperature M. Menouni, P. Breugnon, A. Rozanov (CPPM - Aix-Marseille Université)
1 13 Octobre 2011 Laurent Roy ATCA Crate / Infrastructure in place -Rack in D3: dimension -Electrical power availability -Tell1 racks running in D3 (air.
UM PPS Lab Activities Mid-size Panel Tests PPS meeting January 15, 2012 Claudio, Curtis, Dan, Ethan, Riley.
Analysis for QA (temporary) Hideyuki Sakamoto 1 st October 2007 MICE Tracker Phone Meeting.
CERN, CT Workshop, ID Week, July 2 nd, 2007 Connectivity Workshop Conclusions: Lessons learned C12 Test Next future Claudia Gemme, CERN - INFN Genova Connectivity.
Tracker Goals o Main issue is to be able to run cold as more radiation is accumulated. o Due to “uncontrolled” humidity behavior, our present limit is.
Opto temperature experience in the Pixel detector C. Gemme IBL meeting, 17 March 2009.
Aachen Status Report: CO 2 Cooling for the CMS Tracker at SLHC Lutz Feld, Waclaw Karpinski, Jennifer Merz and Michael Wlochal RWTH Aachen University, 1.
Summer Student 2003Ferro Livia1. Summer Student 2003Ferro Livia2 Contents Experimental setup Thermal behaviour and cooling performance of the TOB structures.
R. Fantechi 2/09/2014. Milestone table (7/2014) Week 23/6: L0TP/Torino test at least 2 primitive sources, writing to LTU, choke/error test Week.
Roberto Silva #65330 February 13,2016 Prof. Eduardo Cabrera.
Mauro Citterio Milano, PP2/Services - an update - Mauro Citterio INFN Milano Type II cables  Layout in progress  Duplication of VVDC wires.
All Freezer Advance. When the Freezer is first supplied with power or if a power outage occurs, the display will indicate this by flashing the temperature.
Noise results from SR1 combined SCT barrel tests Summary of some initial results Alan Barr, UCL Pepe Bernabeu, Valencia.
CMS Upgrade CERN April 27, 2010 W. Bertl PSI Power & Cooling: Design Status of BPIX.
SCT Links Operation Performance from QA and operation
Status CO2 Cooling IBBelle: Reconnection after Belle II Roll in
Cooling channel Status
Tracker cooling loop “check out” draft for discussion
Aachen Status Report: CO2 Cooling for the CMS Tracker
Prototype activities update
Aachen Status Report: CO2 Cooling for the CMS Tracker at SLHC
Recirculating CO2 System
ROD assembly and test in US
Detective Quantum Efficiency Preliminary Design Review
Aachen Status Report: CO2 Cooling for the CMS Tracker
An Optimal Procedure for RF Conditionning at the FREIA Laboratory
Input-Output-Process Demo
Temp determinations Daily mean temp Daily temp range Monthly mean temp
Box and Whisker Plots and the 5 number summary
System tests at CEA O. Piquet 19/03/2019
System Specifications Lab Tests
Egyptian Atomic Energy Authority (EAEA), Egypt
Presentation transcript:

Optoboards dependence on Temperature C. Gemme, T.Flick detector meeting, April 2 nd 2009 Motivations Test in SR1 thanks to K. Lantzsch, L.Masetti, J.Moss, S. Strandberg for helping in setting up the system Conclusions

Opto Temperature dependence in 2008 We have some experience of temperature dependence in the pit: 1.In early August Opto BPR set to 3.5 bar (~-5C ); optoheater setting to 5C. Optoboards temperature ~5-10 C:  Many problems in operating the detector! Precise quantification is difficult as the optotuning procedure was also not optimized yet. 2.BOC Scans vs temperature settings on part of the detector (Sep 9/10):  Only 6 PP0s all failing at 10C  Optoheaters settings at ~10C-13C-16C-19C-22C  Data not exactly what we need: 2D scans with some optotuning in between potentially changing Viset, etc..  DECIDED TO REDO THE TEST IN SR1

SR1 test (March 27/28) Setup 14 optoboards with 71 modules enabled (19 modules disabled due to various problems) Optoheaters to warm up (careful not to hit the software interlock) Chiller to go down in opto temperature Scans => ~40 min for each set of measurement including reaching temp stability Inlink/Outlink: BOC_INLINKOUTLINK, Base. 2D_DSP: BOC_THR_DEL_DSP, Preset (DEL 0-24 in 25 steps, THR in 21 steps) 3D_DSP: BOC_THR_DEL_DSP, Optotest_3D (same as 2D, 15 Viset steps ) 3D_FAST: BOC_THR_DEL_FAST, Optotest_3D (same as 2D, 8 Viset steps ) 2D_DSP done only because the analysis should be ready to compare different scans Procedure Day 1: from nominal Temp, go up in temperature with optoheaters Day 2: from minimum T to nominal by varying the chiller set T

Day 1 warm tests Optoheaters powered by deskop PS. No DCS control, no feedback… not very safe  Not possible to go up to higher optoboard temperatures as there is a software interlock at 35C (and a hardware at 40C). B boards went were close to the maximum. Temperature changes during the scans due to scan on Viset changing VDC_current. MeaurementOptoheaters V ChillerMean T opto (D/B) #1OFF ~26/~28.5C #211 VOFF~28C/~30.5C #315 VOFF~30C, ~32C interlock #1 #2 #3 #1 #2 #3

Day2: cold tests Hygronometer to check the dew point (-15C inside the ~sealed Toothpix setup). Minimum temperature reachable by the chiller -23C and not very efficient thermal coupling with the optoloop. Opts heaters Chiller Temp (C) T before opto T opto (D/B) 1OFF /13 2OFF /14.6 3OFF /17 4OFF /18.9 5OFF /20.4 6OFF /23.0 7OFF /26.5 8OFF / OFF /31.3

Day2: cold tests L2_B27_S1_C6 T opto

Results Decrease of EFR well visible both for low and high temperature as expected. However: Max reachable temperature is not as high enough to study the upper limit of the working range due to the software interlock. At the min testable temperature with the test setup, only three boards have serious problems, having few ch. each that misbehave. BAD boards L2_B99_S2_A7, Topto= 8.2C L2_B99_S2_C6, Topto= 13.2C L2_B27_S1_C7, Topto= 9.4C Optoboards temperatures for the Coldest, SR1 default and warmest set points

Summary range PP0 Typ e ColdestMin GoodDefaultWarmest Operative range (warmest-min) L0_B12_S1_A6D L0_B12_S1_C7B L0_B12_S2_A7B L0_B12_S2_C6B L2_B27_S1_A6D L2_B27_S1_C7D L2_B27_S2_A7D L2_B27_S2_C6D L2_B99_S1_A6D L2_B99_S1_C7D L2_B99_S2_A7D L2_B99_S2_C6D D1A_B01_S1D D1A_B01_S2D

L2_B27_S2_C6: GOOD! S17684 S17638 S17646 coldest Sr1 default warmest 15 steps in Viset for each scan ( mV)

L2_B27_S1_C7: BAD S17684 S17638 S17646 coldest Sr1 default warmest 15 steps in Viset for each scan ( mV)

L2_B99_S2_A7: BAD S17684 S17638 S17646 coldest Sr1 default warmest 15 steps in Viset for each scan ( mV)

L2_B99_S2_C6: BAD S17684 S17638 S17646 coldest Sr1 default warmest Bad but only two modules enabled at all temperatures

The strange case of L2_B99_S2_C6_M6C I/O Scan/Analysis RX Current (mA)3D_BOC Scan / commentT Opto S17686/ S ok13.3 S17687/ S not working15.2 S17691/ S ok17.4 S17695/ S Not working19.2 S17699/ S Not working20.6 S17703/ S Not working22.7 S17707/ S Not working24.9 S17711/ S ok28.3 S17715/ S ok for the uppermost two Viset steps30.7

Conclusions Optoboards behaviour vs temperature has been studied in SR1: Automatic analysis tools are in preparation to systematically analyze data. Inlink/oulink scan analysis is producing a first feedback of power vs temperature (Ron, Shih- Chieh, David) Maybe interesting to repeat the scans vs Viset (multiple scans varying Viset setting or a 2D in/outlink scan with outer loop on Viset), at constant temperature. 2D scan EFR analysis on-going (Su Yung, Tobias) It might be worth to further extend the temperature range at lower temperatures to check when the ‘good’ optoboards start misbehaving. Switch off part of the optoboards when at the lowest chiller temperature? L2_B99_S2_C6_M6C: power is not always null. To be checked with the powermeter on the BOC side: -> it is worth to measure the behaviour of the bad opto channels in the pit vs optoboard temperature to know more! (Bad opto channels: 2 no opto pin current, 1 no command received, 4 dark channels) It will be interesting to repeat the test on the full detector when the cooling will be back and then a full characterization of our detector optoboards will be available on a wider temperature range. Anyway this test is interesting to have some partial results for the opto note and to prepare tools for the full scale test.

Spares Cold, default, warm scans for all PP0s…

L0_B12_S1_A6_Link0 S17684 S17638 S17646 coldest Sr1 default warmest

L0_B12_S1_C7_Link0 S17684 S17638 S17646 coldest Sr1 default warmest

L0_B12_S1_C7_Link1 S17684 S17638 S17646 coldest Sr1 default warmest

L0_B12_S2_A7_Link0 S17684 S17638 S17646 coldest Sr1 default warmest

L0_B12_S2_A7_Link1 S17684 S17638 S17646 coldest Sr1 default warmest

L0_B12_S2_C6_Link0 S17684 S17638 S17646 coldest Sr1 default warmest

L0_B12_S2_C6_Link1 S17684 S17638 S17646 coldest Sr1 default warmest

L2_B27_S1_A6 S17684 S17638 S17646 coldest Sr1 default warmest

L2_B27_S2_A7 S17684 S17638 S17646 coldest Sr1 default warmest

L2_B99_S1_A6 S17684 S17638 S17646 coldest Sr1 default warmest

L2_B99_S1_C7 S17684 S17638 S17646 coldest Sr1 default warmest

D1A_B05_S1 S17684 S17638 S17646 coldest Sr1 default warmest

D1A_B05_S2 S17684 S17638 S17646 coldest Sr1 default warmest