1 Status of the CLIC two-beam module program A. Samochkine, G. Riddone Acknowledgements to the Module WG members 4 February 2014 CLIC Workshop 2014 (3-7.

Slides:



Advertisements
Similar presentations
COOLING TUBE ACCELERATING STRUCTURE MANIFOLD COUPLER VACUUM INTERFACE FLANGE RF INTERFACE FLANGE TUNING STUD ENGINEERING DESIGN AND FABRICATION OF X-BAND.
Advertisements

CLIC two-beam module integration issues 4 th CLIC Advisory Committee (CLIC-ACE), May 26-28, 2009 CLIC two-beam module integration issues G. Riddone on.
SLAC workshop 7-10 July 2009 WP1: microwave based accelerators Status of CLIC X-band high-power components G. Riddone, (contribution from A.
LCWS12, 25/10/ CLIC two-beam module development Status and future plans G. Riddone Outlook Short introduction CLIC Module Validation program Future.
TMM of the CLIC Two-Beam Module T0 in the LAB – Proceedings to structural FEA Riku Raatikainen
1 RF-Structures Mock-Up FEA Assembly Tooling V. Soldatov, F. Rossi, R. Raatikainen
Influence of the Gravity, Vacuum and RF on CLIC Module T0 Behavior R. Raatikainen.
Vacuum, Surfaces & Coatings Group Technology Department Vacuum tests for CLIC module prototypes 6 November 2013 C. Garion2 Outline: Reminder: specification.
K. Alam, CLIC workshop, October 16-18, CLIC workshop, October 2007 Working group “ Two beam hardware and integration” Test module in the two.
CIEMAT CONTRIBUTION TO TBL PETS (January 2009) David Carrillo on behalf of the Accelerators Team.
F. Toral CLIC Workshop CIEMAT contribution to CLIC Experimental Verification F. Toral on behalf of Accelerator Technology Group, CIEMAT.
ENGINEERING DESIGN AND FABRICATION OF PETS V. Soldatov¹, D. Gudkov¹, I. Syratchev², A. Samoshkin¹, G. Riddone², A. Olyunin¹, S. Atieh² 1 – JINR, Dubna,
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
30 GHz waveguide line modification towards 12 GHz.
International Workshop on Linear Colliders 2010 Design and fabrication update on PSI/Trieste X-band phase- space rotator structure Dmitry Gudkov 21-OCT-2010.
INTEGRATION OF RF STRUCTURES IN THE TWO-BEAM MODULE DESIGN G. Riddone, CERN, Geneva, Switzerland A. Samoshkin, D. Gudkov, JINR, Dubna, Russia Abstract.
R&D proposals for EuCard 2 EuCard2, April 21Steffen Döbert, BE-RF  SRF basic research (W. Weingarten)  CTF3 and CTF3+, possible infra - structure for.
CTC, Two-beam module program (WP CTC-004) CLIC Modules (boundary conditions, technical system design and integration) CDR modules Prototypes.
PETS EuCARD. Present status and precision assembly L. Sánchez, F. Aragón, J. Calero, J.L. Gutiérrez, E. Rodríguez, F. Toral, CIEMAT 26/10/2011.
06-November-2013 Thermo-Mechanical Tests BE-RF-PM Review of the CLIC Two-Beam Module Program Thermo-Mechanical Tests L. Kortelainen, I. Kossyvakis, R.
CLIC RF structure development meeting Structure cost study (introduction) G. Riddone,
TBL as a 12 GHz power source, overview and first results from commissioning IWLC 2010 workshopSteffen Döbert, BE-RF  Current status of TBL  Status of.
CLEX TBM T0 Cooling system Progress Report 1 V. Soldatov, A. Vamvakas, BE-RF
18/04/12 Arnaud ACKER Mechanical Analysis of RF Network 1/14 CLIC Two-Beam Module type 0.RF Network. Drive-Beam Main-Beam.
TM0 components inventory and procurement schedule In LAB testing facility A. Bartalesi.
CTC, Outcome from Two-beam Module Review on15/ G. Riddone,
CLIC08 workshop CLIC module layout and main requirements G. Riddone, on behalf of the CMWG Home page of the TBM WG:
1 Thermal tests planning for mock-up TM0 Thermal tests planning for CLIC prototype module type 0 May 30th,
«BE-RF-PM» CLIC prototype two-beam modules Thermal test planning G. Riddone, F. Rossi Introduction Thermal tests 1.Environment 2.Heating and.
CLIC two-beam modules TEST modules final schemes Dmitry Gudkov BE/RF CLIC Module Working Group.
cern.ch 1 A. Samoshkin 28-Feb-2011 Progress on CDR module design.
cern.ch International Workshop on Linear Colliders 2010 CLIC TWO-BEAM MODULE DESIGN & INTEGRATION 21-Oct-2010 WG 8 «TECHNICAL SYSTEMS»
Updated Thermo-Mechanical Model of the CLIC Two-Beam Module Riku Raatikainen
ENGINEERING DESIGN AND FABRICATION OF X-BAND ACCELERATING STRUCTURE TD24 WITH WFM Abstract To achieve high luminosity in CLIC, the accelerating structures.
1 Thermal tests planning for mock-up TM0 Thermal tests planning for CLIC prototype module type 0 July 17,
1 Assembly and installation of TM0 in the Lab Assembly and installation of TM0 in the Lab F. Rossi September.
5 th CLIC-ACE Structure production in laboratories and industries G. Riddone, 02/02/2010 (contribution from KEK/SLAC colleagues) 1.
CLIC module Experimental program for module array Module review, June 22 nd 2015Elena Daskalaki, BE-RF-MK.
TBTS Test Program & Schedule G. Riddone
cern.ch CLIC MEETING (17-Dec-2010) CLIC TWO-BEAM MODULE LAYOUT (short introduction) BE / RF 1.
CLIC requirements on Warm Magnets (for CLIC Modules mainly) 1 M. Modena, CERN TE-MSC 13 April 2011 CERN-UK Collaboration Kick-off Meeting.
TD26CC PLANS FROM CIEMAT Laura Sánchez on behalf Electrical Engineering Group of CIEMAT.
7-Sep-2011 CLIC RF Structure Development Meeting «BE/RF» TD26 WITH COMPACT COUPLER FOR CLEX (TD26 CC SiC) ENGINEERING DESIGN this structure will be used.
CLIC meeting CLIC module status G. Riddone on behalf of the CLIC Module WG,
CLIC workshop ”Two beam hardware and integration” working group Module layout and main requirement G. Riddone, A. Samoshkin
1 CTF3 CLEX day July 2006 CLEX day 2006 Introduction G.Geschonke CERN.
CLEX TBM T0 Cooling system Design strategy 1 V. Soldatov, A. Vamvakas, BE-RF
Alignment system and impact on CLIC two-beam module design H. Mainaud-Durand, G. Riddone CTC meeting –
1 [24-July-2013] [CMWG] «BE-RF-PM» CLIC TBM Prototypes Status EDMS №[Number] Dmitry Gudkov 1.
TBL experimental program Status and Results  Introduction  Status  Experimental program for 2010 and beyond  Outlook ACE, Steffen Döbert.
1 12-February-2014 BE-RF-PM CLIC MODULE Preparation for the duty cycles Written by: Elena Daskalaki Checked by: Alexander Samochkine Approved by: Germana.
CLIC Workshop 2008 TBTS status. PETS testing program and installation status. Igor Syratchev & Germana Riddone for the CLIC team.
DTL prototype summary and production sequence F.Grespan LNL _06_22 CDR.
02-Dec XB Dec-2010 XB-10 Engineering design, production and follow-up of X-band RF components G. Riddone in collaboration.
GOLD- ELECTROPLATING COOLING FITTING ADAPTER ACCELERATING STRUCTURE CONCEPTUAL DESIGN OF X-BAND ACCELERATING STRUCTURE TD26 CC SIC Abstract Many accelerating.
Module layout and types Two-beam module review, September 2009 Module layout and types G. Riddone for the CMWG,
Status of the CLIC module R&D G. Riddone on behalf of the CLIC module WG (special contributions from A. Samoshkin, D. Gudkov, A. Solodko, N. Gazis)
Two-beam module layout
Status of CIEMAT work on PETS
LCWS11 WG4 Fully featured accelerating structure engineering design
Update on the DB Girders FE Analyses
Alignment methods developed for the validation of the thermal and mechanical behavior of the Two Beam Test Modules for the CLIC project Hélène MAINAUD.
Thermal-Structural Finite Element Analysis of CLIC module T0#2
Complementary ISTC Projects #3888, 3889p
Module roadmap to end of 2017
TBL, Status, Plans, Experiments
List of changes and improvements for the next generation CLIC module
Installation plan for LAB modules
TM0s and TM1 components inventory and procurement schedule
Thermal test (lab modules)
Presentation transcript:

1 Status of the CLIC two-beam module program A. Samochkine, G. Riddone Acknowledgements to the Module WG members 4 February 2014 CLIC Workshop 2014 (3-7 February 2014)

2 04-February-2014 CLIC Workshop 2014 «BE-RF-PM» Content Introduction to module –TBM LAB –TBM CLEX Test program Module design, component fabrication and assembly –TBM LAB –TBM CLEX Conclusions

3 04-February-2014 CLIC Workshop 2014 «BE-RF-PM» TBM LAB. Overview Systems to test: Supporting & pre-alignment RF structures Vacuum Cooling MBQ stabilization No beam, thermo-mechanical tests 3 modules in series (final configuration “0 - 1 – 0”) Real mechanical interfaces, quasi-nominal assembly procedure Functional RF mock-ups

4 04-February-2014 CLIC Workshop 2014 «BE-RF-PM» TBM CLEX. Overview TBM CLEX One TBMPriming RF Network Integration in CLEX TBM RF and beam 1 module + existing PETS Real RF structures

5 04-February-2014 CLIC Workshop 2014 «BE-RF-PM» TBM Test Program CLEX Demonstration of the two-beam acceleration with fully fledged two- beam module Address feasibility issues in an integrated approach (detailed program under finalization) Demonstration of the two-beam acceleration with fully fledged two- beam module Address feasibility issues in an integrated approach (detailed program under finalization) LAB Validation of different types of girders and movers Pre-alignment of girders/quadrupoles in the module environment Validation of interconnections and vacuum system under different thermal loads Measurement of resonant frequencies Simulation of several thermal cycles and alignment verification Transport of the module and alignment verification Validation of different types of girders and movers Pre-alignment of girders/quadrupoles in the module environment Validation of interconnections and vacuum system under different thermal loads Measurement of resonant frequencies Simulation of several thermal cycles and alignment verification Transport of the module and alignment verification

6 04-February-2014 CLIC Workshop 2014 «BE-RF-PM» Supporting/ pre-alignment RF Components Vacuum system Cooling system TBM LAB T0#1. Overview Considering the module consisting of several “layers”:

7 04-February-2014 CLIC Workshop 2014 «BE-RF-PM» TBM LAB Main Beam. Accelerating Structures  Overall length  2010 mm  Simplified parts = reduced cost  Mechanical interfaces are equal to real AS  Internal surface area is equal to real AS  Cooling system is equal to real AS VACUUM MANIFOLD ( x 32 ) DISK STACK ( x 8 ) COOLING SYSTEM CONNECTOR ( x 64 ) COMPACT LOAD INTERFACE ( x 16 ) INTERMODULE INTERCONNECTION ( x 2 ) AS – VAC. TANK INTERCONNECTION ( x 8 ) WAKE FIELD MONITOR ( x 32 ) RF NETWORK INTERFACE ( x 16 ) See talk “Experience assembling structures with damping manifolds” on Wed ’14

8 04-February-2014 CLIC Workshop 2014 «BE-RF-PM» TBM LAB Main Beam. Accelerating Structures

9 04-February-2014 CLIC Workshop 2014 «BE-RF-PM» TBM LAB Main Beam. Accelerating Structures Standard fittings: Cu tubes Brazing of 2 stacks 1005 mm + Interconnections MB-MB; Welding (EBW) of two stacks together x 2 x 1 EBW

10 04-February-2014 CLIC Workshop 2014 «BE-RF-PM» TBM LAB Drive Beam. PETS mock-up Octants replaced by simplified single body bar Simplified damping inserts On-Off actuator is replaced by the plug The inner geometry is simplified Using of interconnection flanges Using of screw cooling fittings PETS MOCK-UP INTERCONNECTION PETS MINITANK PETS ON-OFF (COUPLERS) DAMPING INSERT

11 04-February-2014 CLIC Workshop 2014 «BE-RF-PM» TBM LAB Drive Beam. PETS mock-up General assembly. EB welding. CC subassemblies. Brazing. Compact Coupler subassemblies. Brazing. Minitank. Brazing & Welding. Mock-up Compact Coupler. Brazing. EBW

12 04-February-2014 CLIC Workshop 2014 «BE-RF-PM» TBM LAB PETS mock-up, EBW Final assembly step. Electron beam welding accomplished by CERN main workshop.

13 04-February-2014 CLIC Workshop 2014 «BE-RF-PM» TBM LAB RF network The RF network (incl. hybrid, splitter and CMF) is meant to transfer the RF power from PETS (Drive Beam) to accelerating structures (Main Beam). SPLITTER HYBRID FROM PETS TO AS CHOKE MODE FLANGE COOLING PIPE REINFORCEMENT TO LOAD standard WR90 profiles the inner geometry of machined parts is simplified using of interconnection RF flanges The assembly procedure is similar to one for real component

14 04-February-2014 CLIC Workshop 2014 «BE-RF-PM» TBM LAB RF network Hybrid (also splitters and elbows). Brazing. Splitter sub-assy. Brazing. CMF sub-assy. Brazing. General assembly. Brazing. Cooling pipe. Brazing. Reinforcement. Low temp. brazing.

15 04-February-2014 CLIC Workshop 2014 «BE-RF-PM» TBM LAB Vacuum Network Network connected rigidly to the vacuum tank Bellows used between compact loads and vacuum network PETS and AS connected to vacuum tank COLLECTOR TUBE Ø64 TUBES Ø28 BELLOWS COMPACT LOAD MOCK-UP TO VAC. TANK FROM AS MAIN BEAM

16 04-February-2014 CLIC Workshop 2014 «BE-RF-PM» TBM LAB Cooling System Nominal cooling system simulated to cool about 7.5 kW dissipated power 1.Insert tube 2.Tighten the nut Standard fitting are used to avoid brazing or welding operations:

17 04-February-2014 CLIC Workshop 2014 «BE-RF-PM» TBM LAB Experimental results SAS, example T AMB = 20 °C, V AIR = 0.4 m/s, V SAS = m 3 /h Heat power: 50% Heat power: 100% Surface temperature :  Average: 31.4 °C  Max: 32.1 °C Average water temperature increase per SAS: +6.3 °C Transient time from 50% to 100%: ~20 min. Measurements in agreement with expectation Surface temperature:  average: 28.0 °C  Max: 28.6 °C Average water temperature increase per SAS: +3 °C

18 04-February-2014 CLIC Workshop 2014 «BE-RF-PM» TBM CLEX. Integration Priming RF network specially developed for providing the RF power Fully equipped module (with supports) integrated in the CLEX line PB DB 2320 TWO-BEAM MODULE

19 04-February-2014 CLIC Workshop 2014 «BE-RF-PM» TBM CLEX Supporting System Validation of the positioning system before starting the assembly of the module (by SU colleagues) Installation of the motorized stations of the 1 st batch supporting systems at the supplier facility 1 st batch supporting systems (SiC) at the supplier facility Alignment measurements Delivered at CERN: currently under CMM, first measurements within the specification

20 04-February-2014 CLIC Workshop 2014 «BE-RF-PM» TBM CLEX DB BPM. Assembly Fabrication of all pieces under completion Feedthroughs under testing Installation of SiC rings (assembled with copper interface parts) inside the body; Welding of the drift tube; Welding of the bellows; Screwing of RF-fingers. CF FLANGE & BELLOWS ASSEMBLY RF-FINGER & SiC RING ASSEMBLY MAIN BODY ASSEMBLY DRIFT TUBE SIC RING & CU-INTERFACE ASSEMBLY RF-FINGER QCF FLANGE & BELLOWS ASSEMBLY FEEDTHROUGH

21 04-February-2014 CLIC Workshop 2014 «BE-RF-PM» TBM CLEX. PETS The production of the 2 nd PETS has been launched by CIEMAT: 8 x Octants production is finished; Assembly of 8 x Octants ready; Production of mini tank and couplers finished Electron beam welding is expected in the coming weeks (CERN); PETS RF check PETS before EBW PETS#1 finalized and successfully checked PETS#2 RF check before final welding OK

22 04-February-2014 CLIC Workshop 2014 «BE-RF-PM» TBM CLEX. Several other components Few hundreds pieces needed for one module

23 04-February-2014 CLIC Workshop 2014 «BE-RF-PM» Schedule

24 04-February-2014 CLIC Workshop 2014 «BE-RF-PM» Summary  Module program very important to understand technical issue on integrated approach  All the components of the TM0 #1 have been successfully manufactured and module assembled in the LAB 169. Module currently under test.  The important lessons learnt during the fabrication of the components and module assembly are taken into account for the next TBM prototypes, especially the experience on SAS mock fabrication was indispensable for the production of real structures for CLEX  Alignment system fully validated  Heating/cooling systems operating as expected  Final duty cycles and failure scenarios under completion (thermal behaviour and alignment of components)  TM0 #2 under fabrication and assembly  Module review on roadmap for TBM LAB in Nov 2013: TBM LAB: final configuration ‘0-1-0’ TBM CLEX: final configuration ‘0’  TBM CLEX under fabrication and assembly (installation from June 2014)