Changes in QPS R. Denz, TE-MPE-EP MPP workshop 12.03.2013 Acknowledgements: K. Dahlerup-Petersen, V. Froidbise, S. Georgakakis, B. Magnin, C. Martin, J.

Slides:



Advertisements
Similar presentations
LHC UPS Systems and Configurations: Changes during the LS1 V. Chareyre / EN-EL LHC Beam Operation Committee 11 February 2014 EDMS No /02/2014.
Advertisements

TE-MPE-CP, RD, 03-Dec Quench Detection and Energy Extraction Systems R. Denz (Quench Detection), K. Dahlerup-Petersen (Energy Extraction Systems),
TE-MPE –TM, 16/05/2013, Mateusz Bednarek, TE/MPE-EE ELQA testing during and beyond LS1.
REVIEW OF THE CRYOGENIC BY-PASS FOR THE LHC DS COLLIMATORS ELECTRICAL CIRCUIT MODIFICATION, INCLUDING OPERATIONAL CONSIDERATIONS PRESENTED BY A. SIEMKO.
LHC Beam Screen Heaters: System overview, consolidation needs and project planning 4 February TE-CRG/JCC (Beam Screen Heater Review) 1.
TE-MPE-EP, RD, 26-Jul Quench Heater Supervision for MB Status of System Integration R. Denz TE-MPE Technical Meeting July 26 th Acknowledgements:
Session th January 2010 R.Schmidt TE/MPE Hardware Commissioning 2010 and beyond R.Schmidt.
TE-MPE-EP, VF, 11-Oct-2012 Update on the DQLPU type A design and general progress. TE-MPE Technical Meeting.
ITER – Interlocks Luis Fernandez December 2014 Central Interlock System CIS v0.
Operational tools Laurette Ponce BE-OP 1. 2 Powering tests and Safety 23 July 2009  After the 19 th September, a re-enforcement of access control during.
How to achieve higher redundancy of the UPS for QPS ? -The lack of redundancy concerns the supply lines from UPS to consumer but equally parts of the UPS.
TE-MPE-EP, RD, 06-Dec QPS Data Transmission after LS1 R. Denz, TE-MPE-EP TIMBER PM WinCC OA Tsunami warning:
Chamonix Risks due to UPS malfunctioning Impact on the Superconducting Circuit Protection System Hugues Thiesen Acknowledgments:K. Dahlerup-Petersen,
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
How can we reduce the “no beam„ time? Walter Venturini Delsolaro D. Arnoult, S. Claudet, G. Cumer, K. Dahlerup Petersen, R. Denz, F. Duval, V. Montabonnet,
TE-MPE-CP, RD, 23-Nov Summary of Radiation Induced QPS Events in LHC 2010 R. Denz TE-MPE-CP.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
B. Todd et al. 25 th August 2009 Observations Since v1.
TE/MPE/EE J. Mourao T/MPE/EE 1 November 2012 LHC Machine Local protection Redundant Power supply (DQLPUR) & interface Module (DQLIM) progress status.
Update and status for the Work Unit ‘Energy Extraction’ - equipping the three test benches for series testing of Super-FRS Dipoles D2, D3, D4 and Quadrupoles.
FGC Upgrades in the SPS V. Kain, S. Cettour Cave, S. Page, J.C. Bau, OP/SPS April
Training LHC Powering R. Denz Quench Protection System R. Denz AT-MEL.
TE-MPE-CP, RD, 09-June Enhanced Diagnostics & Supervision for Quench Heater Circuits R. Denz TE-MPE-CP.
AT-MEL-PM, R. Denz, CERN, CH-1211 Geneva 23 1 QPS system and its risks  Principal risks  General remarks  Quench heater circuits  Quench detection.
AT-MEI-PE, RD, LIUWG 31-JUL R. Denz AT-MEI-PE LHC Luminosity Upgrade Protection of the Inner Triplet, D1, Correctors and Superconducting Links/Leads.
TE-MPE-EP, RD, 26-Aug Workshop on QPS Software Layer Hardware / Agents R. Denz, TE-MPE-EP.
MPE Review – June 2, 2015 A. Erokhin, TE-MPE-EE Upgrade, IST and Powering tests of the Upgrade, IST and Powering tests of the 600A Energy Extraction Systems.
QPS R2E Status R2E Internal Meeting, October 24 th 2013Discussion 1 LS1 developments Digital Quench Protection insertion region magnets Delivery/installation.
TE-MPE-CP, RD, 06-Oct Radiation Induced Faults in QPS Systems during LHC run 2011 R. Denz TE-MPE Technical Meeting October 6 th.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
TE-MPE-EP New DQLPU type A Production of 1300 new protection units TE-MPE-EP, VF, 23-Nov-2012.
TE/MPE activities currently planed for YETS Reiner Denz, Knud Dalherup-Petersen, Markus Zerlauth & Bruno Puccio YETS coordination meeting.
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
NQPS commissioning …a long way to go. Topics nQPS component overview Enhancements in Firmware Commissioning diagram Detailed task list Summary.
SAFETY DURING HARDWARE COMMISSIONING, 18 October 2007, D. Bozzini, AT/MEL-EM 1 Safety during Hardware Commissioning Davide Bozzini on behalf of the ELQA.
TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb R. Denz TE-MPE-CP on behalf of the QPS team QPS Upgrade and Re-commissioning.
Quench Detection System R. Denz TE-MPE-EP on behalf of the QPS team.
[R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] HWC Workshop ( ) Consolidation and major changes that have impact on the powering circuits.
1 J. Mourao (TE/MPE/CP) Enhanced DQHDS functionality  Status for 2011  Increase Magnet diagnostic capabilities  Our proposals.
HWC with nQPS Splice Monitoring Zinur Charifoulline & Bob Flora Real Time (~10 sec) BUS Voltage Energy Extraction Trip 300 µV threshold on Un-bypassed.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
18, 19, 20 February 2002 Power Converters for magnets (PBS 1.2.3) R. GENAND SL/PO 1 Power Converters for Magnets –Introduction –Specification Magnet characteristics.
Training LHC Powering - Markus Zerlauth Powering Interlocks Markus Zerlauth AB/CO/MI.
MPP Workshop Status of Powering Interlocks I. Romera on behalf of MPE-MS MPP Workshop, 12 June 2015, I. Romera (TE-MPE)1.
MPP Meeting 07/03/2007 MPP Main Ring Magnet Performance Panel Meeting Wednesday 7th March 2007 Agenda: 1)Matters arising 2)Recommendations for the case.
TE-MPE-CP, RD, 12-Dec QPS - analysis of main problems, areas to target, possible improvements R. Denz, TE-MPE-CP Evian 2011.
MPE Workshop 14/12/2010 Analysis of the RB and RQF/D splice data recorded with nQPS - status and plans towards full automation Analysis of the RB and RQF/D.
CERN TE-MPE-EP, RD, 09-April Quench Protection Systems (QPS) for the LHC R. Denz, TE-MPE-EP Acknowledgements: K. Dahlerup-Petersen, A. Siemko, J.
TE-MPE-CP, RD, 28-Sep Problems with QPS DAQ Systems During LHC Operation, 1 st Results from 2010 CNRAD Tests R. Denz TE-MPE-CP.
 TE-MPE-PE Clean code workshop – R.Heil, M.Koza, K.Krol Introduction to the MPE software process Raphaela Heil TE-MPE-PE Clean code workshop - 9 th July.
Machine Protection Review, Markus Zerlauth, 12 th April Magnet powering system and beam dump requests Markus Zerlauth, AB-CO-IN.
MPE LS1 workshop Summary Session 4 – Quench Detection R. Denz, D. E. Rasmussen.
Inner Triplet Protection Strategy LHC & HL-LHC Daniel Wollmann with Inputs from B. Auchmann, G. Ambrosio, R. Denz, P. Fessia, E. Ravaioli, F. Rodrigues.
Hardware Commissioning Review, R. Denz, 12-May Superconducting circuits: what remains to be done during hardware commissioning R. Denz AT-MEL-PM.
Main MPE Activities during YETS/EYETS/LS2 and the Provision of Resources Andrzej Siemko Andrzej Siemko TE-MPE1.
R. Denz, A. Gomez Alonso, AT-MEL-PM
Injectors BLM system: PS Ring installation at EYETS
Ideas and design concepts, and challenges
Powering the LHC Magnets
J. Uythoven for the MPE-MI & MS Teams
MPE main activities planned for LS2
the CERN Electrical network protection system
Re-Commissioning (IST) of Electrical Systems: QPS, EE & PIC
Detailed global view on protection and detection of the circuits
Quench detection electronics for the HL-LHC magnet circuits of the LHC
Machine Protection Xu Hongliang.
Review of hardware commissioning
R. Denz, TE-MPE-EP Acknowledgements: J. Steckert
Close-out.
Presentation transcript:

Changes in QPS R. Denz, TE-MPE-EP MPP workshop Acknowledgements: K. Dahlerup-Petersen, V. Froidbise, S. Georgakakis, B. Magnin, C. Martin, J. Mourao, B. Puccio, A. Siemko, J. Steckert 1 st change – trying to use new CERN corporate identity

Introduction Major upgrades can only be smoothly implemented during long shutdowns Re-furbished / upgraded systems should be able to run without major overhaul at least for 3 to 4 years No principal change of the protection functionality required for the LHC after LS1 Some protection settings to be adapted to higher energy Several requests for enhanced supervision & diagnostic capabilities by equipment owners, experts and users Requested for LHC operation as for hardware commissioning Enhanced remote control options, less accesses, more automatic analysis and maintenance tools, configuration databases R2E consolidation to be completed General system overhaul

R2E consolidation Relocation of QPS equipment Concerns the inner triplet protection systems installed in UJ14, UJ16 and UJ56 (12/35 dumps in 2012) Deployment of radiation tolerant hardware IPQ & IPD protection (RR13,17, 53, 57) One system successfully tested in 2012/2013 (Q6.L5) 600 A protection (RR13,17, 53, 57, 73, 77) Development to be completed  upgrade is mandatory Enhanced power-cycle options for DAQ systems including automatic re-start of stalled field-bus couplers Intermediate solution until NanoFip based DAQ systems are available

Enhanced quench heater supervision I The upgrade is driven by the intention to reduce the risk of damage to the quench heater circuits The present system monitoring only the discharge voltage is not sensitive enough to detect all fault states of the quench heater circuits especially failures of the heater strips. All of the few quench heater faults observed so far during LHC operation could be mitigated by disabling the respective heater circuit and switching to a low field heater. There is however a risk of a quench heater fault requiring at least an exchange of the magnet (short to coil, compromised electrical integrity of the magnet)

Enhanced quench heater supervision II The enhanced quench heater supervision is supposed to reveal precursor states of a potential failure The newly developed system records simultaneously the discharge voltage and current Sampling rates up to 192 kHz, 16 Bit resolution Special mode to detect blown internal fuse of the quench heater power supply  potential heater isolation fault Requires development of sophisticated high level software to analyze post mortem data

Enhanced quench heater supervision III The present protection crates cannot be extended to house additional measurement systems The existing quench detection electronics, DAQ systems can be re-used Protection racks type DYPB need as well to be refurbished completely  decision to perform the work outside LHC Complete series of new devices to be designed, validated, produced and tested in relatively short time New crates will be adapted to the redundant UPS powering scheme implemented in 2009 Fed by two external radiation tolerant AC/DC LDO converters Major upgrade requiring significant effort Still on track but it may become necessary to postpone some other less important activities

Earth voltage feelers for LHC main circuits The earth voltage feelers will monitor the electrical insulation strength of the LHC main circuits especially during fast discharges The system will as well measure the electrical insulation strength between adjacent bus-bars As all data will be stored in the LHC logging database also the evolution in time can be studied. In case of an eventual earth fault the system will allow to identify the location of the fault position on the half-cell level. Per sector a maximum of 54 devices for the main dipole circuit and 55 for each of the main quad circuits can be installed (1308 units in total).

General system revision I - hardware QPS systems have been exploited since 2007 Designs and firmware dating back to 2002 No major hardware change a part the nQPS extension Replacement of obsolete systems, upgrades with improved or enhanced functionality IPQ and IPD protection (mandatory) Upgrade of warm instrumentation cables for Q9 & Q10 to achieve better immunity against electrical perturbations Fix non-conformity in QPS / DFB instrumentation interface Unique interface required Detection hardware to be updated and unified nDQQDI board, so far SEU and near miss free

General system revision I – hardware continued 600 A protection (partly mandatory) Deployment of radiation tolerant detection systems in RR Implementation of a hardware multi-trigger option for the DAQ systems Eases hardware commissioning, assures that all post mortem data are sent Quench loop controller upgrade (optional) Redundancy of loop current sources Enhanced diagnostics especially with respect to false triggers including the interface to the powering interlock controller Noteworthy; new DQLPU type A is capable of localizing faults inside the current loop Note on QPS quench loops for LHC main circuits: Proposed upgrade is for enhanced diagnostics and easier maintenance only. During LHC run 1 the quench loops were extremely reliable; there is no evidence at all for a malfunction or spurious trigger caused by the loop itself.

General system revision II – Energy Extraction Arc chamber installation for RQD/RQF extraction switches to be completed in order to increase the maximum operational voltage of these circuits Will allow to keep the discharge time constant of the RQD/RQF circuits short (t < 20 s) At the same time the installation of the snubber capacitor banks in the RQF/RQD Circuits (16 installations) will be executed 600 A energy extraction systems Implementation of a general upgrade campaign, including an improved fixation of the holding coils and supervision of the internal current distribution Firmware update of interface board to fix vulnerability to non-conform user manipulations

General system revision III – firmware General revision of detection system firmware Fixing of some vulnerabilities revealed during the last years Compatibility with remote access to device parameters (read and write) Adapt supervision resolution and sampling rates to actual hardware capabilities Upgrade of QPS low level supervision Full visibility of redundant circuit boards including post mortem buffers Some bug fixes (e.g. timing problems) and code optimization Update is tedious as many circuit boards need to be re- programmed

General system revision IV – QPS supervision Major change in the physical layer of the QPS field-bus by doubling the number of segments Allows to increase data transmission rate by almost a factor two by reducing the macro-cycle length to 100 ms Transmission of QPS data to logging database to be improved On change recording or filtering of analog signals no longer permitted States must be interpolated for retrieval Allows much easier analysis and detection of eventual hidden fault states Firmware download and update via the QPS supervision under investigation Not straightforward; requires quite a number of changes

General system revision V – QPS supervision high level tools The full exploitation of all QPS upgrades presented so far requires a series of new high level supervision tools (MS section) Enhanced quench heater supervision data analysis Fully automatic signal integrity checks  of particular importance during LHC re-commissioning QPS configuration database to be commissioned as well during LS1 Automatic check of all device parameters Automatic download of some parameters, e.g. download of nQPS compensation coefficients after a hardware change Critical parameters can only manually set by experts Dependency of QPS systems on human interaction to be further reduced as principal cause for near misses during LHC run 1.

General system revision VI – quench detection settings revisited THE THRESHOLD of 100 mV Revision of THE THRESHOLD of 100 mV is long overdue Increases system dependability significantly, reduces machine downtime, spares the superconducting circuit … Especially necessary for “tricky” circuits like the 600 A and some IPQ Simulations & analysis almost completed by Arjan, Bernhard etc. ECR to be issued soon Even with the revised settings none of the 600 A circuits can be protected without inductive compensation Longer evaluation and higher threshold voltage are however especially beneficial for the development of radiation tolerant systems. By the way (just a coincidence?) … from Wikipedia: “Endo cochlear presentation is the positive voltage of mV seen in the cochlear endolymphatic spaces.”

Re-commissioning and operation after LS1 All the work performed during LS1 by will require a full re- commissioning of all protection systems prior to the powering tests Complete electrical quality assurance for all superconducting circuits Test of all QPS instrumentation cables (very critical activity) Complete individual system tests: interlock tests (all 13722, quench heater discharge tests etc., verification of data transmission The re-commissioning will profit from the experience gained so far but will remain challenging (as usual) Additional tests will be required during the powering tests in order to qualify some newly installed items

Re-commissioning and operation after LS1 System exploitation will change significantly after LS1 Teething problems during initial exploitation phase to be expected (otherwise something is really wrong …) Longer turn around time after trips; more real triggers Almost all circuits will operate outside self-protecting regime Efficient training of service teams (MPE stand-by, MP3..) is essential and has to start soon Integration of new members, get people familiar with upgraded systems After initial phase less but more complex interventions of the stand-by service expected  will require a substantial training effort

Summary The upgrade of the QPS systems during LS1aims to increase the system dependability and to enhance the diagnostic capabilities Successful upgrade will reduce machine time significantly, especially radiation induced trips and allow much more preemptive fault diagnostics Substantial effort to improve maintainability (more remote control etc.) Major upgrade of the QPS only possible during LS1 So far on track but not much room to manoeuvre Upgrades and projects not yet defined will cause delays Sufficient time for testing and re-commissioning including some contingency required Eventual savings in time during commissioning will need to be repaid during operation with interest and compound interest …