LHC status & 2009/2010 operations Mike Lamont. Contents Consolidation – brief recall Splices Operational energies Potential performance Present status.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

February 2009 Summary of Chamonix 09 Steve Myers.
Yasmine Amhis EPFL Yasmine Amhis EPFL Status of the LHC and LHCb Adrenaline.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
(n)QPS LHC status LHC: past, present and future Mike Lamont for the LHC team
Status of the LHC Mike Lamont for the LHC team. The LHC Very big Very cold Very high energy 2.
LHCC 3rd June 2015 Mike Lamont for the LHC team
Injection test? Mike Lamont For initial discussion.
Lot’s of time lost due to cryo problem in IR8. Major impact, therefore review of MD program… Start discussion here, please let us know your input. Will.
REVIEW OF THE CRYOGENIC BY-PASS FOR THE LHC DS COLLIMATORS ELECTRICAL CIRCUIT MODIFICATION, INCLUDING OPERATIONAL CONSIDERATIONS PRESENTED BY A. SIEMKO.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
1 Luminosity monitor and LHC operation H. Burkhardt AB/ABP, TAN integration workshop, 10/3/2006 Thanks for discussions and input from Enrico Bravin, Ralph.
A. Verweij, TE-MPE. 3 Feb 2009, LHC Performance Workshop – Chamonix 2009 Arjan Verweij TE-MPE - joint stability - what was wrong with the ‘old’ bus-bar.
A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
LHC progress Report LHCC Wednesday 23 rd March 2011.
R. Assmann - LHCCWG Two Beam Operation R.W. Aßmann LHCCWG Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P. Baudrenghien, J. Uythoven,
EPPOG - LHC Machine LHC machine (and some outreach) Mike Lamont.
Status of the LHC Mike Lamont for the LHC team. LS1 - descent into the underworld again.
Running scenario 2009/10 Run through components – and then synthesis.
T. LeCompte Argonne National Laboratory Evolution of the Run Plan.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
1 LHC Status LHCC 23 rd September 2009 Steve Myers.
LHC Machine Status Report Mike Lamont for the LHC team Acknowledgements: Mirko Pojer, Matteo Solfaroli, Katy Foraz et al.
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
LHC Machine Operational Status and Plans LHCC, 22nd September 2010 Steve Myers (On behalf of the LHC team and international collaborators)
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Thursday 27 th October 00:57 fill 2257 dumped during squeeze (RQTF.A67B1) 03:52 stable beams fill #2258 4:33 Dumped, problem of LBDS dilution kicker power.
LMC 1 (Pre Chamonix) DN200 relief valve position DN200 relief valve position On top wherever possible. Open W bellows for MLI protection. On top wherever.
LHC Commissioning Status Gianluigi Arduini CERN – AB Department For… 23/10/20081LHC Commissioning Status - G. Arduini.
The Large Hadron Collider The 19 th Sep 2008 incident [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] NIKHEF Seminar ( )
NIKHEF Annual Meeting, December 18, The LHC Project Status report to the NIKHEF annual meeting Jos Engelen Based on last week’s reports to CERN.
News from the LHC J. Wenninger CERN Beams Department Operation Group
Luminosity monitor and LHC operation
Wednesday 8.9 External crossing angles:
Minimum Hardware Commissioning – Disclaimer
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
MPI-ATL Calor Meeting 7-Sep-2009 H. Oberlack MPI für Physik, Munich
LHC schedule.
Machine Coordinators: G. Arduini, J. Wenninger
12 October 2009 RRB Plenary R.-D. Heuer
The LHC - Status Is COLD Is almost fully commissioned
Long Shutdown for the LHC: Vacuum Beam Pipes
Status of LHC Commissioning
Powering the LHC Magnets
Summary of week 7 Hardware Commissioning:
Status of the BLHC ….work in progress! Mike Lamont CERN/AB 18/01/2008
Machine plans - Alignment workshop
Status of the LHC December 2009
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Tue :25 Beams dumped due to RF vacuum interlock
LHC status & 2009/2010 operations
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
Machine Protection Xu Hongliang.
Summary of Week 16 G. Arduini, J. Wenninger
J. Uythoven, W. Venturini Delsolaro, CERN, Geneva
Summary of Week 26 Main aims: G. Arduini, B. Holzer, M. Lamont
Wire almost entirely through beam before BLM triggers dump
LHC Beam Operations Past, Present and Future
Summary Thursday h21: Stable beams fill #1303.
Machine plans - CMS startup workshop
LHC status & 2009/2010 operations
Collimators: Operations - Baseline Assumptions
Luminosity and time estimates
Summary Tuesday h23: Machine closed. Precycle started.
Another Immortal Fill….
Presentation transcript:

LHC status & 2009/2010 operations Mike Lamont

Contents Consolidation – brief recall Splices Operational energies Potential performance Present status Plans for LHC status - CMS week

Consolidation 1/2 Besides the major effort required to repair sector 34… Major upgrade of the quench protection system  Protection of all main quadrupole and dipole joints (0.3 mV threshold).  High statistics measurement accuracy to < 1 nΩ.  Installation of > 200 km of cables, production of thousands of electronic boards. >> protection against similar issues in the future. Massive measurement campaign to identify bad splices  Calorimetric methods (~ 40 nΩ) to identify possible bad cells  High precision voltage meas. (~ 1 nΩ) to identify problematic splices LHC status - CMS week Improved active protection Diagnostics

Consolidation 2/2 Mitigation of collateral effects in case of problems: Additional release valves (“DN200”)  Improvement of the pressure relief system to eventually cope with maximum He flow of 40 kg/s in the arcs (maximum conceivable flow)  Installation completed in 4 sectors (1-2, 3-4, 5-6, 6-7)  Also done for Inner triplets, Standalone Magnets and DFBs: Reinforcement of the quadrupole supports  Arc quadrupoles (total 104 with vacuum barrier)  Semi-stand alone magnets  Inner triplet and DFBAs Energy extraction times lowered  Faster discharge of the energy from circuits  Possible because of lower energy running LHC status - CMS week Mitigation of damage 4

Additional splice problem The enhanced quality assurance introduced during sector 3-4 repair has revealed new facts concerning the copper bus bar in which the superconductor is embedded. The process of soldering the superconductor in the interconnecting high-current splices can cause discontinuity of the copper part of the bus-bars and voids which prevent contact between the super-conducting cable and the copper Danger occurs only in case of a quench The challenge: to find a safe limit for the measured joint resistance as a function of the current in magnet circuits (max energy in the machine) LHC status - CMS week

Additional splice problem The enhanced quality assurance introduced during sector 3-4 repair has revealed new facts concerning the copper bus bar in which the superconductor is embedded. The process of soldering the superconductor in the interconnecting high-current splices can cause discontinuity of the copper part of the bus-bars and voids which prevent contact between the super-conducting cable and the copper. Danger occurs only in case of a quench LHC status - CMS week

Stablizer problem LHC status - CMS week Bad electrical contact between wedge and U-profile with the bus on at least 1 side of the joint Bad contact at joint with the U- profile and the wedge

Splices - summary Bad splices  Resolution: calorimetry → 40 nΩ; electric → 1 nΩ  Two bad cases found in 6 sectors: 50 nΩ (1-2) and 100 nΩ (6-7); repaired.  Two sectors still to be measured cold (4-5, 3-4) Copper stabilizer problem  Measurements done in 6 sectors, missing 7-8 and 8-1  10 dipole (> 35 µΩ) and 10 quadrupole (> 80 µΩ) joints repaired  Lot of effort has gone into modeling the problem… LHC status - CMS week

LHC status - CMS week 9 25/8/2009

LHC status - CMS week 10 25/8/2009

Initial operating energy of the LHC Operating at 3.5 TeV with a dipole energy extraction time of 50 s.  Simulations show that resistances of 120 micro-ohm are safe from thermal runaway under conservative assumed conditions of worst case conditions for the copper quality (RRR) and no cooling to the copper stabilizer from the gaseous helium Decision:  Operation initially at 3.5 TeV (energy extraction time of 50 s) with a safety factor or more than 2 for the worst stabilizers. Then operate at 4 – 5 TeV LHC status - CMS week

Higher than 3.5 TeV? Operating at 5 TeV com with a dipole energy extraction time of 68s  Simulations show that resistances of 67 µΩ are safe from thermal runaway under conservative assumed conditions of worst case conditions for the copper quality (RRR), and with estimated cooling to the stabilizer from the gaseous helium  Warm local measurements of the joint resistances in sector 45 (so- called local R16 measurement) revealed record surplus joint resistance of about 60 µΩ, caused by double joint fault on both sides of the SC splice  Conservative estimates based on statistical analysis and the worse joints estimate a conservative maximum of ~ 90 µΩ LHC status - CMS week We have 2 sectors which have not been measured warm. The essential question is “what is the maximum resistance we can “reasonably” expect in the unmeasured sectors?”

Higher than 3.5 TeV? FRESCA  Validation of splice model in the lab  Testing fully instrumented bad splice in 1.9 K Helium Full re-analysis of previous measurements  Analysis of warm non-invasive dipole measurements  Statistical analysis of invasive warm “R16” measurements  Analysis of failure modes and of worse joints found in the six sectors measured Monitor carefully all quenches to gain additional information.  Behaviour (nQPS) – propagation times, current levels…  Likelihood with beam, confirmation of simulations LHC status - CMS week Experiments’ interest in increasing the energy is noted. The jury is definitely out on this one - but we have some time.

3.5 TeV running - recall Emittance goes down with increasing  : And so beam size: And thus luminosity increases with increasing  IF we can hold other parameters constant: However, because beam size goes as:  Lower energy:  increased beam size – less aperture  higher  *  separation of beams in interaction regions drops – long range beam-beam LHC status - CMS week

3.5 TeV limits LHC status - CMS week ParameterLimitReason(s) Beam Intensity ~6 e13 collimation cleaning efficiency  * - crossing angle off 1 m aperture  * - with crossing angle 2 – 3 m aperture, long range beam-beam Crossing angle [50 ns] ~300 µrad  *, aperture, long range beam-beam Peak luminosity ~1 e32 15 Ralph Assmann Werner Herr 6 e13

Operation - assumptions Fill length: 8 hours Turnaround time: 5 hours 20 hours luminosity lifetime 30 day months. 40% machine availability Nominal crossing angle assumed for 50 ns. Nominal transverse emittance Total intensity limited to around 12% of nominal No squeeze beyond 2 m. with 156 bunches, crossing angle off - conservative LHC status - CMS week Given these constraints what can we do?

Plugging in the numbers – 3.5 TeV LHC status - CMS week Month OP scenario Max number bunch Protons per bunch Min beta* Peak Lumi Integrated % nominal events/X 1 Beam commissioning 2 Pilot physics combined with commissioning 433 x x ~200 nb x x ~1 pb x x ~9 pb a No crossing angle 1567 x x ~18 pb b No crossing angle – pushing bunch intensity 1561 x x ~36 pb partial 50 ns – nominal crossing angle 1447 x x ~16 pb x x ~32 pb x x ~48 pb x x ~80 pb x x ~80 pb x x ~80 pb

Possible evolution LHC status - CMS week Ramp, squeeze at 4-5 TeV beta* = 2 m crossing angle, 50 ns Ramp, squeeze, ramp to 4-5 TeV beta* = 2 m no crossing angle, 156 bunches Step up in energy Physics at 3.5 TeV beta* = 2 m no crossing angle, 156 bunches 18

Step up in energy LHC status - CMS week TaskComment Time Hardware commissioning of main circuits Modification and testing of dump resistors Installation of snubbing circuits Calorimetry and QPS measurements ~ 2 weeks Qualification of machine protection without beam FMCMs, PIC, Collimators, TCDQ, BLMs, BPM interlocks, SMPs, RF, LBDS In parallel with HWC Operation dry runs of re- qualified sectors After hand over from HWC Re-commissioning of ramp and associated machine protection Safe beam: LBDS, BLMs, RF ~ 1 week Re-commissioning of squeeze Could possibly ramp-squeeze-ramp (avoiding the need to re-com the 3.5 TeV squeeze) Optics and operations’ checks at high energy ~ 2 days Collimator re-optimization~4 days Estimate: 4 weeks to re-establish physics

Plugging in the numbers with a step in energy LHC status - CMS week Month OP scenario Max number bunch Protons per bunch Min beta* Peak Lumi Integrated % nominal 1 Beam commissioning 2 Pilot physics combined with commissioning 433 x x ~200 nb x x ~1 pb x x ~9 pb a No crossing angle 1567 x x ~18 pb b No crossing angle – pushing bunch intensity 1561 x x ~36 pb Shift to higher energy: approx 4 weeks Would aim for physics without crossing angle in the first instance with a gentle ramp back up in intensity 7 4 – 5 TeV (5 TeV luminosity numbers quoted) 1567 x x ~26 pb ns – nominal Xing angle 1447 x x ~23 pb ns 2887 x x ~46 pb ns 4327 x x ~69 pb ns 4329 x x ~110 pb

Caveats Big error bars on these numbers Bunch intensity/ Beam intensity  quench limit, beam lifetimes, parameter tolerances & control, emittance conservation through the cycle… Cleaning efficiency of collimation versus quench limits  Note: we have already proved that we can quench a dipole with only ~2-3 e9 at 450 GeV Operability:  reproducibility, ramp, squeeze, beam lifetime, background, critical feedback systems Machine availability:  just about everything… include the injectors Machine Protection  has to work perfectly LHC status - CMS week

LHC status - today LHC status - CMS week SectorStatusTemp 12PO PHASE 11.9 K Phase 2 powering starts this week, following installation of new QPS. 23COOLDOWN~4 K 34COOLDOWN~175 K 45COOLDOWN~13 K 56COOLDOWN~2 K1 w delay due to cryo-preparation; 67COOLDOWN~250 K Cool-down of 6-7 started few days earlier than foreseen 78COOLDOWN1.9 K1 w delay due to cryo-preparation; 81COOLDOWN~75 K 22 A lot still going on out there: ELQA, access doors, QPS…

General Schedule 24 th, August 09 no shifts 2 shifts, 5 days 2 shifts, 7 days 3 shifts, starting from Friday 18/9

Hardware commissioning - NB HWC phase 1  Limited current – no powering of main circuits – restricted access HWC phase 2  Individual system tests of new QPS  Power main circuits to 6000 A (just over 3.5 TeV)  No access during powering in sector concerned and adjacent access zones New Quench Protection System still to be installed and tested just about everywhere  First 54 crates finished testing last Saturday LHC status - CMS week

injectors LHC status - CMS week ± first LHC beam Injection test Sector 23 as first priority Sector 78 if part of 81 required is ready Ions in the lines 25

Beam commissioning Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning TeV beam & first collisions 450 GeV collisions Ramp commissioning to 1 TeV Full machine protection qualification Pilot physics System/beam commissioning LHC status - CMS week Machine protection commissioning 1 EnergySafeVery Safe 4501 e121 e11 1 TeV2.5 e112.5 e TeV2.4 e10probe One month to first collisions 26

450 GeV collisions Time limited: 3-4 shifts No squeeze Low intensity – machine protection commissioning unlikely to be very advanced. ~1 week after first beam LHC status - CMS week Number of bunches 1412 Particles per bunch 444 Beam intensity 4 x x x beta* [m] 11 Luminosity [cm -2 s -1 ] 1.7 x x x Integrated lumi/24 hours [nb -1 ]

LHC 2009 LHC status - CMS week All dates approximate… Reasonable machine availability assumed Stop LHC with beam ~19 th December 2009, restart ~ 4 th January

LHC 2010 – very draft 2009: 1 month commissioning 2010: 1 month pilot & commissioning 3 month 3.5 TeV 1 month step-up 5 month TeV 1 month ions LHC status - CMS week

Conclusions Splices remain an issue Constraints of 3.5 TeV enumerated Potential performance shown  200 – 300 pb -1 seem reasonable Step up in energy would take ~4 weeks – increase to be decided Would start with a flat machine at the higher energy… before bringing on crossing angle and exploiting 50 ns. LHC well into cool-down and on schedule for mid- November start with beam With a bit of luck, first high energy collisions before Christmas LHC status - CMS week