Maciej Ostręga Michal Zimny IBL CO 2 cooling progress meeting 14.01.2014.

Slides:



Advertisements
Similar presentations
IBL CO 2 cooling control system development status Lukasz Zwalinski – PH/DT/DI Maciej Ostrega – PH/DT/DI.
Advertisements

Daikin Altherma™ Troubling Shooting
UNICOS Objects (CPC) 11/02/14 UNICOS, CERN1 CERN, EN/ICE, UNICOS Team.
Lukasz ZwalinskiLHCb CO 2 cooling; 1 IBL CO 2 cooling control system Bart Verlaat, Lukasz Zwalinski, Maciej Ostrega, Michal Zimny,
Module 2: Hardware and Terminology
PLC: Programmable Logical Controller
-P&ID- Piping & Instrument Diagram
SPD Cooling workshop: PLC item details. ups upgrade: 10-12' after trigger 24V - what to do in 10 minutes Present situation: In case of “normal power”
Engineer Training UV Electrical Cabinet (16 and above) TJ8300 / TJ8500 UV Electrical Cabinet (Machines 16 and above)
IBL CO 2 cooling control system development status Lukasz Zwalinski – PH/DT/DI Maciej Ostrega – PH/DT/DI Florian Corbaz – EN/CV/DC.
Lukasz ZwalinskiATLAS IBL CO 2 cooling 1 CO 2 cooling system for Insertable B Layer detector into the ATLAS experiment L. Zwalinski, C. Bortolin,
SCADA and Telemetry Presented By:.
MICE Hydrogen Control System MICE H2 Review Meeting RAL 15 th Jan 2015 PJ Warburton – STFC Daresbury Lab.
I Pag 1 Microchiller 2. I Pag 2 I Pag 3 Information on the display.
Industrial Process Control System Simon Hui Engineer Control and Informatics, Industrial Centre.
LHC ARC Commissioning report during LS1 Agenda: VRGPE documentation (former VRJGE) Active Penning modification By-Pass Valves modification LHC ARC commissioning.
CO2 progress and issues on the control system Lukasz Zwalinski – PH/DT
MICE Hydrogen Control System MICE Collaboration Meeting CM33 27 th July 2012 PJ Warburton – STFC Daresbury Lab.
IBL cooling status Pixel week 15 October 2014 Bart Verlaat, Lukasz Zwalinski, Maciej Ostrega, Claudio Bortolin, Piotr Gach, Artur Szlachcic, Olivier Crespo.
DCP 12 May 2010 Jan Godlewski PH-DT-PO 1 DETECTOR COOLING PROJECT WP2 CO2 activities status report Jan Godlewski PH-DT-PO
Vacuum Controls Status MACS week December 2010 PP a-JWA-VacControlStatus.ppt Joachim Wallner 1.
Claudio Bortolin. 1 st June: PT100 electrical connection failure (Temp Chiller water In&Out) 1) it required an access to the cavern to be fixed 2) access.
LHC Cryogenics Control: INTEGRATION OF THE INDUSTRIAL CONTROLS (UNICOS) AND FRONT-END SOFTWARE ARCHITECTURE (FESA) APPLICATIONS Enrique BLANCO Controls.
19 May 09P. Tropea1 Fluorocarbon systems –SS1 hydraulics completed, now under commissioning –SS2 connections and sensors installation done –Pixels ready.
European Organization for Nuclear Research - Organisation européenne pour la recherche nucléaire SSD/SDD Proposal Upgrade 30/08/2012
MICE Hydrogen Control System MICE Safety Review Meeting 4 th Oct 2011 PJ Warburton - Daresbury Lab.
Michal Zimny Cracow University of Technology Seminar - Internship programmes at CERN PH-DT-DI.
IBL cooling thermal chock incident 15 October The IBL cooling team.
Chiller control system Lukasz Zwalinski – PH/DT.
Chiller control system Specification meeting Lukasz Zwalinski – PH/DT.
Alice DCS workshop S.Popescu 1 1. News from TPC DCS cooling prototype Project overview: Aim of the prototype: investigating and developing standard.
Why HIPPS ?? We have 600# (high pressure bearing) pipeline from well pads till production header. After that, we have 150# (low pressure bearing) pipeline.
CUE – Make Any Pump an E-Pump
AIDA Traci commissioning LHCb – CO 2 cooling meeting 18 March 2015 Kamil Wojdyla, Lukasz Banasik, Nicola Spadavecchia, Tomasz Kucharski, Piotr Dziurdzia,
The (prototype) C&V Framework component used for the SPD Cooling Control A.Tauro, G.De Cataldo.
IBL cooling operation at bake-out IBL CO2 meeting 10 April 2014 Bart Verlaat, Lukasz Zwalinski, Maciej Ostrega, Olivier Crespo Lopez 1.
CO2 progress and issues on the control system Lukasz Zwalinski – PH/DT
CISSP Common Body of Knowledge Review by Alfred Ouyang is licensed under the Creative Commons Attribution-NonCommercial-ShareAlike 3.0 Unported License.
60kW Thermosiphon control system
IBL CO 2 cooling planning 03 July 2013 Jan Godlewski, Bart Verlaat, Lukasz Zwalinski 1
Chiller + Brine + Water control system UNICOS CPC Lukasz Zwalinski – PH/DT.
Overview of recent CO 2 cooling developments As an example for LHCb-Velo and UT cooling? Kick-off meeting 28 may 14 Bart Verlaat 1.
Krzysztof Śliwa 26 August, Krzysztof Śliwa 26 August, 2015  Tests done between 7th to 25th of August 2015  Circulation in by-pass over the manifold.
Created by Daniel Gargas Student from Cracow University of Technology.
DCS meeting - CERN June 17, 2002V.Kouchpil SDD DCS status Low Voltage system End-ladder ASIC High Voltage system Cooling system Schedule.
The (prototype) C&V Framework component used for the SPD Cooling Control A.Tauro, G.De Cataldo.
GTK GAS COOLING SYSTEM Marco Statera, Vittore Carassiti, Ferruccio Petrucci, Luca Landi, Stefano Chiozzi, Manuel Bolognesi NA62 - GTK working group meeting.
MARCO control system Munich Lukasz Zwalinski – PH/DT Maciej Ostrega – PH/DT.
2015 Operations Stay Treat CHL2 4K Cold Box Modifications SC1 2K Cold Box CC4 Failure Helium and LN2 Losses Contamination Operations Stay Treat.
1 04 April 2007 L. Roy Detector Safety System for infrastructure - General fire detection (barracks, cavern) - Sniffer system (smoke detection above the.
MARCO control system Munich Lukasz Zwalinski – PH/DT Maciej Ostrega – PH/DT.
Detector Safety System overview DSS is a PLC based system designed to protect ATLAS detector from damages. Front end (hardware) 2 redundant PLC ~700 input.
S A Griffiths CM42 June 2015 Electrical & Control.
Internship final report Joanna Staniszewska Cracow University of Technology –
European Organization for Nuclear Research - Organisation européenne pour la recherche nucléaire CO 2 IBL plant failures 16/06/ /06/2016 O.Crespo-Lopez.
Electrical and Controls
Control Logic for ATLAS Thermosiphon chiller brine and water circuit
LCLS-II 2K Cold Box Controls Design Review
Forum on Tracking Detector Mechanics - Bonn, May 2016
352MHz Klystron Control for the 3MeV Linac test stand
MAUVE CO2 cooling review
Status of the cryogenic system for B180
Insertable B Layer Cooling System
Instrumentation and Controls
SC1R Cold Box PDR Controls
MicroLogix Packaged Controllers
CERN with UNICOS M. Pezzetti AT_ECR_CE 27 June 2005.
Charge 2. Equipment Protection 3. Definition and Documentation
Presentation transcript:

Maciej Ostręga Michal Zimny IBL CO 2 cooling progress meeting

Pressure supply pipes already connected to all valves Power supply for plants connected to power distribution box Electrical connection for communication between plants – will have been tested when plant B commissioning will be finished Plant A I/O commissioning  Digital input  Feedback from PV108 liquid line bypass valve (valve is still not connected)  MV106 filling valve open status (cable not connected to valve – no feedback in PVSS)  MV110 liquid line bypass valve ( valve has to be changed – existing valve has only one feedback status)  MV054,MV056,MV058 service line valves close status ( end-switch was broken ! No feedback to PLC)  Digital output  Communication with DSS

IBL CO 2 cooling progress meeting Plant A I/O commissioning  Analog input  Pump head membrane pressure PT101, PT102, PT103 sensors still not connected  Accumulator level transmitter LT142  J.box and vacuum system inputs will have been tested after installation  Analog input real  Bug in PTsat and TTsat table found by Maciek  Alarms  Manual valves end-switchs and position verification alarms  J.box and vacuum system alarms will have been tested after installation  Communication with DSS  All alarm groups  Pump LP101 alarms  Alarms for some of the heaters has to be finished

IBL CO 2 cooling progress meeting General comments  Circuit breaker (8Q3) in plant B control cabinet has to be changed  Missing protection for high voltage on terminal in Accumulator  Pneumatic valve PV108 save mode should be open  Time delay for all alarms changed to 0.0 s  Valve EV208 is Normally Open!  Added function in PLC program for PHOENIX TC card (wire break detection)  Compressor GP250 ramping time speed was increased (during stop) All necessarily modification are immediately updated in PLC program and SCADA application You can find more detailed report on DFS: \\cern.ch\dfs\Departments\PH\Groups\DT\PO\Cooling activities\PROJECTS\ATLAS_IBL\COMMISSIONING Current file version: IOCommissioning_IBL_A.v3.xlsx

IBL CO 2 cooling progress meeting We have 2 weeks of delay, because of communication problems which was related to bug in Schneider firmware !!!

IBL CO 2 cooling progress meeting