Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay.

Slides:



Advertisements
Similar presentations
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Advertisements

4m Undulator Design Concepts Amanda J Brummitt CCLRC RAL On behalf of the HeLiCal Collaboration.
Status of the SPL cavities at CERN I.Aviles & N. Valverde on behalf of SPL team 1I. Aviles & N. ValverdeLund, 11 December 2013.
CEA DSM Irfu - Bernard GASTINEAU - R3B Technical Board Meeting -April 4, Reactions with Relativistic Radioactive ions Beams GSI Large Acceptance.
Design pressure issues of Super-FRS dipole CrYogenic Department in Common System (CSCY), GSI, Darmstadt Yu Xiang, Hans Mueller* * Primay Beam Magnet Technology.
TOTEM Collaboration Meeting, Feb. 2005, F. Haug, CERN Cooling System for TOTEM Friedrich Haug and Jihao Wu Cryogenics for Experiments CERN TOTEM Collaboration.
SPL cryo-module conceptual design review Cavity, helium vessel and tuner assembly N. Valverde, G. Arnau, S. Atieh, I. Aviles, O. Capatina, M. Esposito,
2 Technical seminar - 5 th June 2014 Vincent Roger - TE-MSC-TF.
HQ TEST CERN by Marta Bajko CERN TE-MSC TF For Hi Lumi and LARP the 16 th of November 2011 CERN.
Status and Integration of the Spectrometer Solenoid Magnets Steve Virostek Lawrence Berkeley National Lab MICE RAL June 15, 2007.
LARP LQX and MQX Magnets Cryogenic Testing at Fermilab’s Industrial Building 1 Roger Rabehl Technical Division/Test & Instrumentation Department.
R&D Status and Plan on The Cryostat N. Ohuchi, K. Tsuchiya, A. Terashima, H. Hisamatsu, M. Masuzawa, T. Okamura, H. Hayano 1.STF-Cryostat Design 2.Construction.
V.Parma, CERN, TE-MSC On bahalf of the Cryomodule development team
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
ESS Cryogenic Distribution System for the Elliptical Linac MBL/HBL - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden.
24 January 2014 LARP VTF Follow-up Meeting P. Kovach VTF 1 LARP Vertical Test Facility Vertical Dewar Design, Magnet Prep And Installation Paul Kovach.
IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009.
Spectrometer Solenoids MICO 214 Steve Virostek LBNL February 6, 2013.
Agenda – Basics of cavity integration into CAST Introduction (M Davenport) Information exchange 2016 – Vacuum in cold bore – 2 cavities Cooling RF Cavities.
EuCARD WP 7 – High Field Magnets Task – Radiation certification Status report EuCARD WP 7 – High Field Magnets Task 2 – Support studies Task
L. Serio COPING WITH TRANSIENTS L. SERIO CERN, Geneva (Switzerland)
Shrikant_Pattalwar TTC 2015 Dec 1, 2015 SLAC 1 Horizontal Tests in a Vertical Cryostat Shrikant Pattalwar STFC Daresbury Laboratory UK.
9/17/07IRENG071 Cryogenic System for the ILC IR Magnets QD0 and QF1 K. C. Wu - BNL.
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
The integration of 420 m detectors into the LHC
Mike Struik / LHC-CRI INSTRUMENTATION FEEDTHROUGH SYSTEM FOR LHC MACHINE ARC QUADRUPOLE MAGNETS. 123rd LHC Vacuum Design Meeting 19 April 1999.
Cryogenic scheme, pipes and valves dimensions U.Wagner CERN TE-CRG.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
SPL cryomodule specification meeting, CERN 19th October 2010 SPL cryomodule specification: Goals of the meeting SPL cryomodule specification: Goals of.
The SPL Short Cryo-module: Status Report V.Parma, CERN, TE-MSC On bahalf of the Cryomodule development team SPL seminar December 2012, 6-7 December 2012,
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
8/29/07K. C. Wu - Brookhaven National Lab1 Major Components in ILC IR Hall Interchangeable Detectors.
Shrikant_Pattalwar ICEC 26, March 7-11, 2016, Delhi 1 Horizontal Tests in a Vertical Cryostat Shrikant Pattalwar STFC Daresbury Laboratory UK.
Spoke section of the ESS linac: - the Spoke cryomodules - the cryogenic distribution system P. DUTHIL (CNRS-IN2P3 IPN Orsay / Division Accélérateurs) on.
3 rd ESAC Review, 27 th February to 1 st March 2013, CEA Saclay Fresca2 Dipole Structure Assembly J.C Perez on behalf of Fresca2 collaboration team.
1 IPN Orsay / Division Accélérateurs The Spoke cryomodule Vacuum aspects P. DUTHIL on behalf of the IPNO team ESS Lund February 19 th 2013.
ILC : Type IV Cryomodule Design Meeting Main cryogenic issues, L. Tavian, AT-ACR C ryostat issues, V.Parma, AT-CRI CERN, January 2006.
Final Design Cryogenic and mechanical configurations
Teleconf ACS – FREIA 28th March 2017
Teleconference ACS – FREIA 31th May 2017
Teleconf ACS – FREIA 13th March 2017
Mechanical and cryogenic configurations
Uppsala University Contract UH2015/09 - UA2016/05 Job nr. 5973
CERN – Zanon discussions
MQXC Nb-Ti 120mm 120T/m 2m models
Roadmap for triplet cryostats
Ti/SS transitions A.Basti INFN-PISA*
HFM Test Station Main Cryostat
LEP cryostat Procurement strategy and plans
Proximity Cryogenics P&IDs meeting
Status of design and production of LEP connection cryostat
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
Teleconference ACS – FREIA 18th April 2017
Status of cryostat integration and conceptual design
Leak Detection Tutorial Work
Teleconference ACS – FREIA 10th May 2017
Cryostat design Mechanical design: Thermal screens: Specifications:
LARP Vertical Test Facility
(vertical cryostat, Gersemi)
Design of Distribution Feedbox at LHC P7
Cryostat design Mechanical design: Thermal screens: Specifications:
The Quench Detection-Wire-Feedthrough Plug-In of W7-X
FRESCA Cryostats Outer cryostat during pressure test at the manufacturer Top plate and lambda plate for the outer cryostat Inner cryostat during reception.
Teleconference ACS – FREIA 20th February 2018
Schematic diagram of the cryogenic system
Teleconference ACS – FREIA 19th June 2017
UPPSALA UNIVERSITY_GERSEMI PROJECT
Review Bloc 4 and SM18 facilities and upgrade
J. Fleiter, S. C. Hopkins, A. Ballarino
Presentation transcript:

Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay

Summary Introduction Design Status Conclusion 27/02/20132

3

Introduction Vertical cryostat “Claudet bath” principle Few cryogenic connections Installed in a pit Support structure in the pit 4 parts Vacuum vessel Helium vessel Thermal shield Insert Magnet hanging from lambda plate 27/02/20134

Integration on ground level Jumper to valve box Exhaust line DN 300 In a trench Release outside of SM18 Current leads 20 kA for main magnet 10 kA for insert Instrumentation Magnet Helium vessel Level gauge Heaters Temperature sensor 27/02/20135

Magnet cooling 3 Phases 300 K – 80 K 8 hours Cold gaseous helium 80 K – 4.2 K 8 hours Liquid helium (1 bar) 4.2 K – 1.8 K 36 hours (1.5 days) Heat exchanger in cryostat 627/02/2013

Cooling from 300 K to 80 K 727/02/2013 Pre cooling valve box Courtesy M. Bajko

Magnet cooling 3 Phases 300 K – 80 K 8 hours Cold gaseous helium 80 K – 4.2 K 8 hours Liquid helium (1 bar) 4.2 K – 1.8 K 36 hours (1.5 days) Heat exchanger in cryostat 827/02/2013

Cooling from 80 K to 4.2 K 927/02/2013 Courtesy M. Bajko

Magnet cooling 3 Phases 300 K – 80 K 8 hours Cold gaseous helium 80 K – 4.2 K 8 hours Liquid helium (1 bar) 4.2 K – 1.8 K 36 hours (1.5 days) Heat exchanger in cryostat 1027/02/2013

Cooling from 4.2 K to 1.8 K 1127/02/2013 Heat in-leak estimation at 1.9K Qnom=25W, Qdyn=40W, Qc-d=100W LHe/LHe heat exchanger, 1.9K Cooling power 100W, dT ≈30mK during cool down and nominal condition Pumping Filling LHe/GHe heat exchanger 1.9K Cooling power up to 150W at 2K Courtesy M. Bajko

27/02/201312

Vacuum vessel Dimensions 4.6 m height 2.3 m diameter 4.8 tons Stainless steel (304L) Conical cover Limit deformations due to magnet weight 3 supports  Isostatic Static vacuum Protection using burst disk 27/02/201313

Helium vessel Max pressure : 5 bar Stainless steel (316 L, 316 LN) Welded to conical cover Neck thermalisation to limit heat in-leak Magnet support by lambda plate seat Heat exchanger for magnet cooling to 1.8 K 27/02/ K 4.2K 300K

Helium vessel Jumper Regroup all cryogenic lines Connection to valve box Fixed point Cryogenic lines Block lines movement G10 plate + Collars 1527/02/2013

Helium vessel Neck thermalisation Copper profile Brazed to neck (stainless steel) Part of thermal shield cryogenic line 1627/02/2013 Neck Brazing Copper profile

Helium vessel Heat exchanger Copper tube brazed to stainless steel tube U shaped and welded to flange (30 x) Saturated helium (18 mbar – 1.8 K) in the tubes Cool-down pressurized helium (magnet) by conduction through copper Cooling power ≈ K (1.5 day Cool-Down) 1727/02/2013

Helium vessel Heat exchanger prototype 1827/02/2013

Thermal shield Actively cooled Supported from top cover Stainless steel structure Support shield Rigidity of the assembly Copper Sheet to form shield Pipe brazed on sheets for cooling 27/02/201319

Insert (concept) Top plate Current leads Instrumentation Radiative screens Lambda plate Quench valve (DN150) Splices Instrumentation Mechanical support Lambda plate to top plate Magnet (15 tons) to lambda plate 27/02/201320

27/02/201321

Vacuum vessel Design : Finished Construction : In progress First production meeting : 14 th February 2013 Delivery : June /02/201322

Helium vessel Design : Almost finished Call for tender : March 2013 Order : Summer 2013 Delivery : 6-7 months after order (Early 2014) 27/02/201323

Thermal shield and Insert Thermal Shield Design in progress Construction in the shadow of helium vessel Order expected for summer 2013 Insert Design in progress Construction at CERN 27/02/201324

27/02/201325

Conclusion Design almost finished Construction in progress All components at CERN early 2014 Assembly phase to be planned Assembly of the cryostat Connection to other components 27/02/201326

Acknowledgment M. Bajko (TE-TF) V. Benda (TE-CRG) G. De Rijk (TE) C. Giloux (TE-TF) P. Minginette (EN-MME) V. Parma (TE-MSC) P. Perret (EN-MME) P. Viret (TE-TF) CERN TE-MSC-CMI Section 27/02/201327

27/02/201328