Process stages on the grower and link for main grower units with required process parameters
Prepare raw material Prepare machine and hot zone Creation vacuum Melting Seeding Growth Detachment Annealing Unloading ingot
Prepare raw material Verneuil stones scrap Compacted powder (density over 3.3 g/cm^3) Purity % Check purity under UV lamp (Hg) Size: mm Layer by layer dense loading
Prepare machine and hot zone
Creation vacuum Diffusion pump Lock Vacuum gauage APG Electromagnetic valve
Vacuum parameters 1 Initial vacuum 1*10 -2 Pa 2Melting 5*10 -4 Pa 3Annealing 5*10 -5 Pa
Melting 5 cm melt Crucible material Equilibrium gas concentration in melt Mo x 10 W x 1.1 Ir No change
Reaction in Al 2 O 3 Al 2 O 3 Al 2 O+AlO Al 2 O 3 Al 2 O+2O Al 2 O 3 Al 2 O 2 +O AlO Al+O AlO 2 Al+2O Al 2 O AlO+Al Al 2 O 2Al+O Al 2 O 2 Al 2 O+O Al 2 O 2 2Al+2O Al 2 O 2 2AlO 2O O 2
Adjusting temperature field Black seed t melt ~ 100°C =2.88 g/cm 3
Control parameters Voltage on heater fluctuation 1 mV in the range 5-12 V Voltage decreasing rate 5-15 mV/hour Pulling rate mm/hour, accuracy 1% Accuracy of load measurement 1 g when load100 kg. Temperature change 1 deg/hour when water flow cubic meter/hour and water pressure 4-6 bars
Adjust melt temperature for seeding Over froozen melt Normal island seed
Seeding Seed Convection line Island Over heated Normal
Formation constrictions Heat removal from grown ingot – to provide ingot temperature lower then crucible walls Decreasing dislocations density Decrease inner stress Symmetrical growth
Shouldering Seed Crystal
Animation of the temperature along the melt free surface Before seedingSeedingShouldering
Not symmetrical field HORN
Melt temperature fluctuations «Blinds» Overheated melt- bubbles accepted by solid interface due to temperature fluctuations «Central cord» too cold melt or too fast growth speed
Ingots profile mm/hour mm/hour
After touch of ingot with crucible bottom to increase pulling up rate to mm/hour
Cycle example- capacity
Position of seed
Weight fluctuation
Weight
Annealing Voltage-hours
Unloading ingot
Prepare machine for next cycle Remove foreign material from crystallizer shields and heater and apply vacuum cleaner for crystallizer Clean elements of hot zone with rectified alcohol Remove and clean windows Clean washer with rectified alcohol
Optical properties Transmission As grown (b, d) and after X-ray 4 hours (с, e)
X-ray diffraction диафрагма: b – 5 мм, c –2мм, d-1 мм, e-0,2 мм, f-0,1 мм