Public Utilities in County Rights-of-Way CHRIS MUDGETT, P.E. County Road Administration Board MARYA SILVERNALE, J.D. Municipal Research & Services Center The 1997 Washington Public Works Design Conference October 16, 1997
Introduction Overview of issues Group discussion
Topics of Discussion Maps of Definite Locations Utility Accommodation Policy Franchises on County Rights-of-Way Utility Relocations to Accommodate Road Construction and Improvements Factors in Cost Responsibility Avoiding Utility Relocation Delays in County Public Works Contracts
Maps of Definite Locations Who is responsible for locating utilities? Where is the information?
Utility Accommodation Policy Does your agency have one? –Status of county compliance with WAC
Utility Accommodation Policy Issues to consider addressing in the policy –No release of hazardous substances –No abandonment in place –Maintenance of clear zone –County not responsible for damage of obscured structures –Notification policies and practices
Utility Accommodation Policy Sample Utility Accommodation Policy Other joint use agreements
Franchises on County Rights-of-Way Authority per RCW Sample Utility Franchise Agreement –Including terms and conditions for use of the public right-of-way Watch for new federal and state laws –Especially related to new technologies
Utility Relocations to Accommodate Road Construction and Improvements Responsibility for cost of relocations –Generally, the utility is responsible for the costs of relocation (RCW )
Utility Relocations to Accommodate Road Construction and Improvements Case law and recent legal developments –Sundquist Homes v. PUD No. 1 of Snohomish County –Clark County v. PUD of Clark County –Pierce County, et al, v. U.S. West Communications –GTE v. City of Bothell
Factors in Cost Responsibility Easement rights Franchise language Local ordinances regulating public right-of-way Local utility accommodation policy Utility tariffs filed with WUTC State and federal law
Avoiding Utility Relocation Delays in County Public Works Projects Early notice programs Design solutions Jointly bid projects with interlocal agreements for inclusion of utility relocation work –Sample interlocal agreement for utility relocation (at utility expense) in connection with county road project
Avoiding Utility Relocation Delays in County Public Works Projects Contractual allocation of responsibility -- special provisions Limitations of ability to contractually allocate liability for damages (RCW )
Avoiding Utility Relocation Delays in County Public Works Projects Limitations of ability to contractually allocate liability for damages (RCW ) –Sample bid specifications language to supplement WSDOT/APWA standard Specification
What If There Are Problems? Practical advice on dealing with your attorney
Questions - Comments - Discussion
Summary Careful planning and attention to details can avoid or minimize utility conflicts and/or delays in county public works projects On-going communication with utility purveyors can strengthen relationships necessary to deal with construction project issues
Summary Draft contract language to anticipate potential problems and clearly assign responsibility Provide all available information to contractors