Failure of Original TF Inner Leg Assembly C Neumeyer 4/10/3.

Slides:



Advertisements
Similar presentations
(Adapted from:D.T. Hall:Practical Marine Electrical Knowledge)
Advertisements

1S25 Arc Fault Monitor. 1S25 Arc Fault Monitor 1S25 Arc Fault Monitor Electrical arc short circuits in metal clad switchgear may occur for many different.
1. Four LLs were published in February Transmission Relaying – Undesired Blocking 2.Lack of Separation for Critical Control Power Supply Leads.
Inspection & Preventive maintenance of breakers
We thought it was a GOOD IDEA, so we did it! We were the first to have quick make-quick break operators on bolted pressure contact switches.
IEC IEC Standard defines:
Testing Test Setup TapLok Insert Shear Key Copper Threads Friction Tests Collar Shear Tests NSTX TF FLAG JOINT REVIEW 8/7/03 Michael Kalish.
Fasteners / Joint Design Michael Kalish NSTX TF FLAG JOINT REVIEW 8/7/03.
Summary of Twisted Racetrack / Clamp Analysis K. D. Freudenberg.
© Unitec New Zealand 1 Faulty Starting System Symptoms No Cranking Slow Cranking Abnormal Noise Overheating of Cables.
Graphic Symbol Location 1. DIN Terminal X52 The machine is powered by electricity using copper cable with 5 wires (3 phase wires + neutral wire +
Inspection & Test Overview suite412.
Inductors. Stored energy. LR circuit.
Section 4: Electric Motors
Partial discharge analysis of defective three-phase cables An overview of an ongoing project involving the generation and analysis of PD within distribution.
J. H. ChrzanowskiNSTX TF Flag Joint Design Review1 NSTX TF Flag Joint Design Review Fabrication and Assembly April 10, 2003 By: James H. Chrzanowski.
NSTX TF Flag Joint Review ANALYSIS & DESIGN C Neumeyer 9/3/3.
NSTX Center Stack Upgrade Workshop Brainstorming on Design Solutions for TF Joint C Neumeyer Jan 22, 2009.
Fasteners / Joint Design Michael Kalish NSTX TF FLAG JOINT REVIEW 4/10/03.
Fasteners / Joint Design Michael Kalish NSTX TF FLAG JOINT REVIEW 8/7/03.
DAY 17 CHAPTER 28 OVERCURRENT PROTECTION FUSES AND CIRCUIT BREAKERS
Component Testing Test Setup TapLok Insert Shear Key Copper Threads
Chapter 1 Quick review over Electronics and Electric Components Prepared By : Elec Solv.
NBI March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration.
STARTING SYSTEM.
TF Joint Voltage Drop Instrumentation Robert Marsala (609) Hans Schneider (609) Engineering Operations August 7, 2003 TF_JOINT_Final_Design_Review.ppt.
NCSX NCSX PWR.System PROTECTION REVIEW 02/22/08 S. Ramakrishnan Slide 1 Electrical Power Systems (WBS 4) NCSX PWR System PROTECTION – REVIEW February 22.
Automotive Fuel and Emissions Control Systems 3/e By James D. Halderman Copyright © 2012, 2009, 2006 Pearson Education, Inc., Upper Saddle River, NJ
TF FLAG JOINT HIGH CURRENT TEST FIXTURE INSTALLATION TO BE IN THE NSTX TRANSITION AREA Features Assembled Components: Flag and Mating Section of TF Center.
NCSX Vacuum Vessel Joint Design Mike Viola PPPL July 1 st, 2003.
Types of Threaded Fasteners.  Used to hold parts together  Clearance holes in parts  Nut on other end  Can also be used with a threaded hole.
Proposed TF Joint Design C Neumeyer 2/26/9 Notes: 1)Several concepts included are based on ideas developed by R Woolley 2)No analysis has yet been performed.
Analyses of Bolted Joint for Shear Load with Stainless Steel Bushing and Frictionless Shim-Flange Interface Two cases of shim plates were investigated.
NSTX TF Flag Joint Design Review INTRODUCTION C Neumeyer 8/7/3.
NSTX TF Flag Joint Design Review OVERVIEW C Neumeyer 8/7/3.
NSTX Center Stack Upgrade Workshop Requirements & Design Point C Neumeyer Jan 22, 2009.
Mechanical Testing of Flag Joint Assembly. TF Flag Assembly to be Tested.
Modular Coil Electrical Joint1 NCSX Peer Review Modular Coil Electrical Joint James Chrzanowski April 24, 2006.
Signals from ISTP-001 April 11-13, 2005 Preliminary Assessment C Neumeyer.
Welcome to Electric Dept. Rajkot Division. How MCB works.
TF Joint Operations Review Introduction C Neumeyer 2/10/05 Scope and Outline of Review Summary of Findings from 2004 Run Review of Joint Force, Pressure.
Precept Marine Conventional Control Panels
Will This Work?. Electric circuit Your challenge: Given a lightbulb holder, a battery holder, a lightbulb, a switch, and connecting wires, make the.
NSTX Response to the Lessons Learned Report NSTX TF Coil Repair Review September 3-4, 2003 Al von Halle.
Analyses of Bolted Joint for Bolt Preload and Shear Load
Design Point Studies for next step device National High-heat-flux Advanced Torus Experiment NHTX C Neumeyer 6/8/6.
NCSX Operation of the C1 Modular Coil in the Coil Test Facility Peer Review June1, 2006 NCSX.
Announcements Read Chapters 10 and 11
F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 PF, TF, & Trim Coil Supports (WBS-15) Core Base Support Structure (WBS-17) F. Dahlgren NCSX Coil.
NSTX TF Flag Joint Torque Collar Chit Review C Neumeyer 9/11/3.
NSTX Supported by NSTX Centerstack Upgrade Project Meeting P. Titus April 14, 2010 PF4/5 Terminal Stress Existing PF4/5 Support Weld Algorythm Moment Influence.
NERC Lessons Learned Summary LLs Published in September 2015.
TF Joint Operations Review Commissioning Plan C Neumeyer 2/10/05 Test Shots Instrumentation Benchmarking.
Helene Felice HQ Test Results Review Thursday December 16 th Overview of HQ coils and Magnet.
NSTX TF Flag Joint Design Review SUMMARY C Neumeyer 8/7/3.
TF Joint Operations Review Simplified Modeling & Protection C Neumeyer 2/10/05 IP and OOP Load Modeling Linear Model of IP and OOP pressure at Joint FEMLAB.
Proposed TF Joint Design Concept #1 C Neumeyer 3/23/9 Notes: 1)Several concepts included are based on ideas developed by R Woolley 2)No analysis has yet.
AWB NSTX TF Flag Joint Design Review April 10, 2003 Art Brooks.
Design Point Studies for Next Step Device National High-power Advanced Torus Experiment NHTX C Neumeyer 7/25/06.
REQUIREMENTS & ASSUMPTIONS C Neumeyer 4/10/3. FIELD AND CURRENT Base GRD requirement: 3kG at R 0 =0.854m with 4.5 sec flat top, once every 300s
A PROPOSED TF JOINT DESIGN FOR THE NSTX CENTERSTACK UPGRADE Robert D Woolley 25 February 2009.
Engineering Operations Outage Schedule The vessel & beamline are under vacuum. 1st Bake-out complete. Air leaks found and fixed. The OH coil will be installed.
Engineering Operations TF Commissioning Mechanical testing of TF flag/box assemblies complete, inner bundle installed, and all joints made up. Joint resistance.
AUTOMATIC CIRCUIT RECLOSER
NSTX TF Flag Joint Design Review OVERVIEW C Neumeyer 8/7/3.
En. No. : En. No. : Div. : 3 rd EC Sub. : EM topic : Starter.
Hipot Testing 101.
FIGURE 35-1 If the vacuum hose is removed from the fuel-pressure regulator when the engine is running, the fuel pressure should increase. If it does not.
Presentation transcript:

Failure of Original TF Inner Leg Assembly C Neumeyer 4/10/3

February 14, 2003: Following our morning “test shots”, the first plasma attempt of the day resulted in a loud bang (heard on the control room audio monitors) accompanied by a plume of smoke (visible on the control room video monitors). Test Shot Failed Shot

Target level was 53.4kA which produces Bt=4.5kG Fault occurred just prior to flat top as the current passed 50kA Several protective devices tripped within milliseconds TF power supply fault detector section overcurrent, - TF Analog Coil Protection (ACP) overcurrent, - TF Rochester Instrument System (RIS) overcurrent, - TF ground fault current relay.

Initial inspection revealed that one of the TF “flags” on the bottom end of the machine was displaced radially by about 1 inch TF Flags

Subsequent inspection revealed the extent of the damage Peak Damage RegionMating Flags

PEAK DAMAGE AREA Peak Damage Area Start & Finish Leads (  V = 1kV)

Fault Scenario An open circuit fault (the flag joint opening up) led to multiple turn-to-turn and turn-to-ground faults (to the hub and umbrella assemblies) at or near the high- voltage terminals of the TF circuit. Spike of fault current from the power supply shunted the coil inner/outer leg assembly. Once the power supply tripped, the current spike decayed. This was followed by an L/R decay of the coil current as the coil released its stored energy. The L/R decay can be modeled by fault with V=125V and R=500 . The energy dissipated in the arc was of order 1.4MJ. Spike Current Coil Current

Current Decay Waveshapes V arc =125V R fault =500  Normal vs. Fault L/R DecayCurve Fit to Fault Model Other “glitches” in current decay are explainableby mutual coupling to OH power supply circuit along power cable run

MECHANICAL/ELECTRICAL FAILURE OF JOINT TF Flag Hub Assembly TF Bundle “Keensert[tm]” Shim Preload (bolts) EM Load

HISTORY OF TF OPERATIONS Approx Shots mainly at 3kG, 4.5kG Limited number at 6kG 3kG 4.5kG 6.0kG FAULT

TF Pulse Spectrum Max I 2 T = 5.46x10 9 A 2 -sec,  T = 65 o C Rated I 2 T = 6.5 x10 9 A 2 -sec,  T = 80 o C 3kG 4.5kG 6.0kG

PRECURSORS Evidence of a problem surfaced after ‘02 run period Also, loose bolts and broken inserts were discovered

RESPONSE TO PRECURSORS Corrected Various Defects –Resurfaced non-planar flag faces and chamfered bolt holes (bottom) –Improved bolt washers and bolt retention (top and bottom), –Retorqued bolts (top and bottom) and replaced 4 “keenserts” with “tap-lok” inserts (bottom), –Replaced G-10 flag shims with inflatable epoxy shim design (top and bottom) Initiated more detailed FEA Returned to 4.5kG limit Initiated more regular inspections Too Little, Too Late Shim

FACTORS LEADING TO FAILURE Design Factors –hub stiffness not adequate to react moment –communication of load from flag to hub uncertain with G10 shims –bolt thread and shoulder engagement too small –bolts necked down too far at threads, not enough on shaft –dual shear/preload function of bolts –lack of feature to facilitate joint resistance measurement w/o disassembly Quality Factors –frequent manual reworking of contact surfaces –non-planar flag surfaces –shoulder bolt concentricity Operational Factors –monitoring of joint integrity too infrequent, too imprecise ALL OF THESE FACTORS HAVE BEEN ADDRESSED IN THE NEW DESIGN