1 Capital Improvements Committee 2011 Capital Request April 14, 2010 Chief Edward A. Flynn Milwaukee Police Department
2 Capital Strategic Objective Maintain and initiate improvements to existing facilities to ensure the safety and security of MPD employees Fund technology and capital equipment projects that allows MPD to provide neighborhood police presence, prevent crime, apprehend criminals, and investigate criminal activity in the City of Milwaukee
3 Capital Funding 2009 Budget $6.7 million $1.1 million expended $4.8 million encumbered $800,000 available for evidence storage and PAB electrical substation 2010 budget $4.2 million 2011 REQUEST $7.3 million
4 2009/10 Accomplishments 5 th District Station HVAC upgrade NTF renovation, parking lot expansion Evidence Storage Warehouse upgrade 4 th floor HVAC, fire alarms, chiller 911 System Replacement 911 System, Call Recording System, telephones, voice mail all integrated
5 2009/10 Accomplishments PAB cooling tower replaced PAB electrical substation upgraded PAB COMP STAT Room completed PAB Space Utilization Study/Master Building Plan completed
Capital Projects:Early Stages PAB Jail Cell Door Replacement Automated Fingerprint Identification System 4 th District Station HVAC replacement PAB Mechanical Shafts Liners failing and nearing capacity PAB Domestic Water Pump Replacement 40 y/o – obsolete equipment; repair and parts difficult At capacity limits PAB Lower Garage Floor Restoration
Capital Budget Request Evidence Warehouse $593,000 Movable shelving – Homicide floor Security system – proximity readers Automated elevator controls Fire suppression system
Capital Budget Request PAB fire pump replacement $85,000
Capital Budget Request D #2 Replace Emergency Generator $100,000
Capital Budget Request Radio Shop HVAC Replacement $200,000
Capital Budget Request Tiburon RMS VMP Upgrade $354,000 Major Capital Equipment Front-end Loader (for snow removal) $70,000
12 PAB Rehab/Code Compliance Project Be A ForceMilwaukee Police Department
13 PAB Rehab/Code Compliance Project Building’s HVAC infrastructure is obsolete and parts are hard to find/replace Piping/plumbing system is failing PAB does not meet hi-rise code compliance No fire sprinklers or code-compliant alarm system Stairwells too close together; code compliance requires pressurization Replacement of fire pump recommended Code compliant generator required for life-safety systems Electrical systems need upgrading Hazardous materials (asbestos) exists in ceilings and walls Building “envelope” deteriorating – thermal value is poor (wasted energy-steam and electricity), windows are inefficient
14 PAB Rehab/Code Compliance Project Any renovations to PAB require asbestos abatement and fire code compliance for high-rises Abatement alone: $2.9M in 2012 $3.1M in 2013 $3.3M in 2014 Window replacement approx. $150,000/floor Fire sprinklers ONLY approx. $92,000/floor Average per floor rehab cost is $4.5M Approximately $240/sq foot
Capital Budget Request PAB Renovation $5.9 million Mechanical/HVAC shaft replacement net of $2.3M in 2010 budget And significant hi-rise upgrades to bring PAB up to code compliance Architectural and engineering fees to begin the re-hab work starting at Level 5
16 PAB Rehab/Code Compliance Project Estimates YearExpenditure 2010$0.4M (approved) 2011$5.9M 2012$14.7M 2013$12.9M 2014$10.4M 2015$2.5M TOTAL$46.7M