SBS Management John J. LeRose Project Manager. Good News/ Bad News We are an official DOE program (project(s), whatever…) – Good because we are more likely.

Slides:



Advertisements
Similar presentations
EMODNet Lot 4 - Chemistry Overview, management and administrative issues Alessandra Giorgetti (OGS) with the contribution of Altenburger Alessandro, Brosich.
Advertisements

The CRM Textbook: customer relationship training Terry James © 2006 Chapter 11: Management.
Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports.
paul drumm; 3rd December 2004; AFC MM 1 Cost & Schedule Review I Terms of reference: –To review the Cost and schedule of the MICE Muon beam –To review.
An updated Baseline Design for MICE From proposal to technical reference Paul Drumm, Dec 2003.
© 2008 Prentice Hall11-1 Introduction to Project Management Chapter 11 Managing Project Execution Information Systems Project Management: A Process and.
Project Execution.
SHMS Detector Commissioning and Installation Howard Fenker Hall-C Users Meeting Jan-2015.
We are Here! Gluex Collaboration Meeting May Engineering Status - Presented by Tim Whitlatch1.
SBS Program Management John J. LeRose SBS Collaboration Meeting October 18,
Project Managers Report Video Conference 172 Roy Preece 11 th December 2014.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
Dialog Practices Connections Roundtable September 2014.
The Learning Agreement, Intellectual Property Rights and Project Approval Professor Dianne Ford Director of PhD Studies, Faculty of Medical Sciences.
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
Component 10 – Fundamentals of Workflow Process Analysis and Redesign Unit 10 – Process Change Implementation and Evaluation This material was developed.
Purpose A crisis communication plan coordinates the communication within the organization, as well as between the organization and the media and the public.
BIT 286: Web Applications Work Breakdown Structure (WBS); Scheduling.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
1 The Initial Report Preparation Guidelines. 2 The Initial Report u Definition of project scope u Project aims and objectives u Initial project plan.
John J. LeRose 1.  Roles/Responsibilities/Organization  Approach  Goals and Objectives  Scope  Schedule  Funding profile  Risk management  EH&S.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
Summary DCS Workshop - L.Jirdén1 Summary of DCS Workshop 28/29 May 01 u Aim of workshop u Program u Summary of presentations u Conclusion.
Member Mail Order Helpful Hints, Reminders and Tools.
In-Kind Contribution Management Update Allen Weeks March 20, Lund.
Thomas Jefferson National Accelerator Facility Page 1 IPR October 18-20, 2011 John J. LeRose Independent Project Review of 12 GeV Upgrade Jefferson Lab.
Key Project Management Ideas A well defined project scope is best. Triple constraint thinking. Use of documents. Stage-gate process. Stakeholder communication.
Lecture 11 Managing Project Execution. Project Execution The phase of a project in which work towards direct achievement of the project’s objectives and.
Recommendation JAINA Committee Structural Proposal.
Monthly Special Education Coordinator Meeting November 18, 2013.
Project Overview How to get here…. Half Way to the Test Run October 18, 2012HPS Project Overview2 …starting from here? John Jaros HPS Collaboration Meeting.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
SBS PMP STATUS JOHN J. LEROSE 4/25/2012 received from Bob McKeown 4/12/2012.
WP2 Superbeam Work Breakdown Structure Version 2 Chris Densham (after Marco Zito version 1 )
John LeRose March 12, A Program of three “projects” to assemble the Super BigBite Spectrometer for a series of experiments in Hall A There is a.
October 4-5, Status of ARRA funded AIPs Electron Lens Scope, Cost, and Schedule Wolfram Fischer October 4, 2010 Electron Lens.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
The Bigbite second GEM tracker. SBS GEM Trackers Front Tracker Geometry x6 18 modules In Italy  50 cm x 40 cm Modules are assembled to form larger chambers.
Comments from Physics Division Rolf Ent Associate Director for Experimental Nuclear Physics SOLID collaboration meeting, February 03, 2012 Thomas Jefferson.
GEM chambers for SoLID Nilanga Liyanage University of Virginia.
End Station A Test Beam (ESTB) Carsten Hast and Mauro Pivi August 23 th 2012 Proposals, Procedures, Schedule.
Fermilab Presentation Greg Bock, Pepin Carolan, Mike Lindgren, Elaine McCluskey 2014 SC PM Workshop July 2014.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Thia Keppel 6/4/13 Hall A Update. Near term accelerator schedule – same as last meeting Accelerator Run II: Beam in hall 3/2014, or maybe as early as.
Mu2e WGM 11/16/2011 R. Ray Mu2e Project manager. Review of the past few months In September it became apparent that the cost of Mu2e was well in excess.
12/15/2015LCBE/gcm Department of Exceptional Children Mid Year Update Leslie County Schools.
SOLUTION What kind of plan do we need? How will we know if the work is on track to be done? How quickly can we get this done? How long will this work take.
MOLLER Collaboration Meeting May 2014 Hall A Update Thia Keppel 1.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
PRad Recent Achievements 1)PRad Implementation (“Position”) document developed and submitted to Jlab. 2)Jlab’s Director Office scheduling review passed.
Fundamentals of Workflow Analysis and Process Redesign Unit Process Change Implementation and Evaluation.
John J. LeRose 1.  Roles/Responsibilities/Organization  Approach  Goals and Objectives  Scope  WBS’s  WBS 1  Funding profile  Schedule  Critical.
John J. LeRose 1.  Roles/Responsibilities/Organization  Approach  Goals and Objectives  Scope  Schedule  Funding profile  Risk management  EH&S.
Modifying the PMP (remove some GEM’s add a scintillator coordinate detector) -JJL (8/29/2012)
The 12 GeV equipment Hall D – Hall D – GLUEx detector for photoproduction experiments Hall B – Large acceptance detector CLAS12 for high luminosity measurements.
Welcome to the DET INSPIRE Lunch N Learn Lunch Learn Do.
News and Misc Didier Contardo, Jeff Spalding UPO 3/2/12 1 UPO 2/2/12 o The MM, cost estimates and reporting o Milestones and scheduling o Chamonix Meeting.
SBS Budget Situation John J. LeRose 6/27/2012. What I’ve asked for in 2013 SBS Basic: $600k (direct cost) – $355k from original + $245k (power supply.
Budget Status and FY04 Requests Elton Smith Hall D Collaboration Meeting Dec 11-13, 2003.
CERN GS Department CH-1211 Genève 23 Switzerland cern.ch/gs-dep Internet Services GS AIS General Services Department GS Advanced Information Services EVM.
Cost and Schedule Breakout Session Paul Weinman Pacific Northwest National Laboratory.
Maintenance Metrics & Executive Dashboard Angelica Williamson & Michael Knight Valdosta State University.
FISCO2 – Financial and Scientific Coordination Work Package dedicated to ENSAR2 management WP leader: Ketel Turzó WP deputy: Sandrine Dubromel ENSAR2 Management.
1 Getting Value out of Earned Value (EV) Presented by Tom Arnez, PMP.
ANNUAL PERFORMANCE REPORTS
NSS Instrument Project Tollgate Coordinator
A High Intensity Neutrino Oscillation Facility in Europe
TDIS mTPC update Nilanga Liyanage and Kondo Gnanvo UVa
Presentation transcript:

SBS Management John J. LeRose Project Manager

Good News/ Bad News We are an official DOE program (project(s), whatever…) – Good because we are more likely to get the money we need. – Bad because now we’re on the radar and have all kinds of constraints and requirements imposed on us. PMP:

Start with two projects here are the “deliverables” WBS 1 (SBS basic) 48D48 Magnet transportation and modifications 48D48 Magnet assembly and support platform Magnet power supply and its associated infrastructure Beam-line vacuum and shielding components Beam-line steering magnets WBS 2 (Neutron Form Factor) Gas Electron Multiplier (GEM) tracking detectors (UVa), 29 modules Front-end and data-acquisition electronics (UVa) to accompany these modules Electronics Hut, Detector Frames, and Materials needed to construct the Lead Tube Shielding, and the Lead Tube Platform for the beamline Coordinate Detector 3 rd project, WBS 3 (Proton Form Factor) starts next year

WBS 1 Milestones ID #LevelMilestoneMilestoneDate M1Project startProject start10/1/ M2Magnet delivered to JLab4/30/ M2Platform parts received6/27/ M2Magnet assembled on platform3/19/ M2Beam-line parts received9/24/ M1Project completion1/29/2016

WBS 2 Milestones ID #LevelMilestoneMilestoneDate M1Project startProject start10/1/ M2UVa receives GEM parts7/22/ M2UVa receives electronics parts8/20/ M 2 UVa GEM modules assembled and tested 10/17/ M2Coordinate Detector Assembled11/17/ M 2 UVa front-end electronics assembled and tested 2/2/ M10 2 WBS 2.3 completed (Electronics Hut Assembled etc.) 10/5/ M1Project completion1/29/2016

Communications with DOE! The JLab SBS management team will provide a monthly status update to the DOE SC Office of Nuclear Physics via . Written status reports will be developed by the JLab Program Manager on a quarterly basis and submitted to JLab senior management as well as the DOE-NP Instrumentation Program Manager. JLab, in coordination with the DOE SC Office of Nuclear Physics, will convene external review panels annually to evaluate progress. In the event of any serious problems in the interim, e.g., a detector performance issue, additional appropriate reviews would be convened by JLab. SBS Program Team meetings will be held regularly to keep collaborators informed of progress and problems.

The Monthly Report A work in progress Executive summary of the “projects” (BP) Management Highlights WBS 1 – Work breakdown structure (BP) – Milestones (scheduled, expected, achieved) – Project oversight – WBS 1.1, 1.2, 1.3 progress problems – Costs WBS 2 (ditto) WBS 3 (ditto) This year no progress, problems, or costs October 15 report is already 7 pages (nothing really to report except that we started)

Reporting is Everyone’s Responsibility The best thing in the long run is to always tell the truth. Please, help me to know the truth. I don’t want to have to hound you about what’s going on. If you are working on something in one of the WBS’s, report on it, at least every two weeks. – Just a quick helps a lot. …

Changing the plan Easy in principle, but not in practice “They” don’t like changes – …

Expected Changes Personnel changes Funding driven delays …

BTW Hall A Collaboration meeting: – We have an hour – Who’s talking? Hall A Annual Report – ?