Qualification Test of UFE Board  Schematic diagram of UFE  Board types and current status  Qualification test procedures  VA & UFE test setup 

Slides:



Advertisements
Similar presentations
The group is developing readout electronics for initial use with the prototype test-stand at Fermilab. This work will contribute towards the design and.
Advertisements

MPPC readout electoronics
Test Setup for PHOBOS Hybrid/Module Testing at MIT Pradeep Sarin 31 July 98.
Specific requirements for analog electronics of a high counting rate TRD Vasile Catanescu NIHAM - Bucharest CBM 10th Collaboration Meeting Sept 25 – 28,
Adding electronic noise and pedestals to the CALICE simulation LCWS 19 – 23 rd April Catherine Fry (working with D Bowerman) Imperial College London.
A scalable DAQ system using the DRS4 sampling chip H.Friederich 1, G.Davatz 1, U.Hartmann 2, A.Howard 1, H.Meyer 1, D.Murer 1, S.Ritt 2, N.Schlumpf 2 1.
Built-In Self-Test for Radio Frequency System-On-Chip Bruce Kim The University of Alabama.
Calibration of the VA2 B Pal, R Mountain, M Artuso 6/29/2010 Goal: get an absolute calibration of a VA2 channel to measure diamond charge collection.
MDT-ASD PRR C. Posch30-Aug-02 1 Specifications, Design and Performance   Specifications Functional Analog   Architecture Analog channel Programmable.
The first testing of the CERC and PCB Version II with cosmic rays Catherine Fry Imperial College London CALICE Meeting, CERN 28 th – 29 th June 2004 Prototype.
Anthony AffolderUS CMS Meeting 12/3/2002Proposal of UCSB Short-term Testing Program Assumptions Electrical and optical hybrids not burnt-in prior to arrival.
Development of novel R/O electronics for LAr detectors Max Hess Controller ADC Data Reduction Ethernet 10/100Mbit Host Detector typical block.
EE 198 B Senior Design Project. Spectrum Analyzer.
ECAL electronics Guido Haefeli, Lausanne PEBS meeting 10.Jan
Mass production testing of the front-end ASICs for the ALICE SDD system L. Toscano a, R. Arteche Diaz b,d, S. Di Liberto b, M.I. Martínez a,c, S.Martoiu.
Preliminary Design of Calorimeter Electronics Shudi Gu June 2002.
Oct, 2000CMS Tracker Electronics1 APV25s1 STATUS Testing started beginning September 1 wafer cut, others left for probing 10 chips mounted on test boards.
Performance of SPIROC chips in SKIROC mode
Mark Raymond /10/051 Trip-t testing brief status report test setup description - hardware and software some very early results.
CERN Beam Test of Silicon-Tungsten Calorimeter Test Module Shinwoo Nam (Ewha Womans University) On behalf of Ewha Womans University: S.J. Baek, H.J. Hyun,
System Test Status Report R. D’Alessandro 1 TIB System Test Report Where were we ….., Mechanics (layer 3 prototype) Mother Cable & Interconnect Board System.
Jean-Marie Bussat – January 31, FPPA2000 characterization history Sumary of tests done at LBNL.
FCAL R&D in Minsk Group: Sensors and Electronics FCAL Collaboration MPI Munich October 17, 2006, Munich, Germany Presented by Igor Emeliantchik.
AIDA FEE64 development report August 2010 Progress after Texas CAD work Manufacturing 25th August
Preliminary measurements for the 8 channel prototype of SPD discriminator ASIC I.The 8 channel prototype. II.Status of the test. III.Noise. IV.Gain. V.Test.
Montpellier, November 15, 2003 J. Cvach, TileHCAL and APD readout1 TileHCAL- fibre readout by APD APDs and preamplifiers Energy scan with DESY beam –Energy.
SiTRA test beams at CERN: infrastructure developments and results Annual EUDET meeting NIKHEF Alexandre CHARPY.
25th June, 2003CMS Ecal MGPA first results1 MGPA first results testing begun 29 th May on bare die (packaging still underway) two chips looked at so far.
Hold signal Variable Gain Preamp. Variable Slow Shaper S&H Bipolar Fast Shaper 64Trigger outputs Gain correction (6 bits/channel) discriminator threshold.
Alexei SemenovGeneric Digitizer Generic Digitizer 10MHZ 16 bit 6U VME Board.
USB Project Ian Coulter. USB Interface USB Menu -Download HEX File -Send Trigger -Start DAQ.
October, 2001CMS Tracker Electronics1 Module studies at IC OUTLINE laboratory setup description, APV I2C settings pulse shape studies (dependence on ISHA,
9th July, 2003CMS Ecal MGPA test results1 MGPA test results first results presented 25 th June – repeat here + some new results testing begun 29 th May.
1 VFE/MGPA considerations for EE/VPT EB/EE electrical spec. differences: full-scale signal noise input capacitance dominated by: APD capacitance (x2) for.
Trip-t testing progress report
L.Royer– Calice LLR – Feb Laurent Royer, J. Bonnard, S. Manen, P. Gay LPC Clermont-Ferrand R&D pole MicRhAu dedicated to High.
AHCAL Electronics. SPIROC2 and HBU measurement results Mathias Reinecke CALICE main meeting Univ. HASSAN II, Casablanca, Morocco Sept. 23rd, 2010.
Calibration of the gain and measurement of the noise for the apv25 electronics K. Gnanvo, N. Liyanage, C.Gu, K. Saenboonruang From INFN Italy: E. Cisbani,
1 Status Report on ADC LPC Clermont-Ferrand Laurent ROYER, Samuel MANEN.
ASIC Activities for the PANDA GSI Peter Wieczorek.
1 MGPA Linearity Mark Raymond (Dec.2004) Non-linearity measurements in the lab hardware description method results.
SKIROC ADC measurements and cyclic ADC LPC Clermont-Ferrand Laurent ROYER, Samuel MANEN Calice/Eudet electronic meeting Orsay June.
SRS Calibration Michael Phipps, Bob Azmoun, Craig Woody 1.
Saverio MINUTOLITOTEM Electronics W.G., 9 December T1 electronics status.
MuTr Chamber properties K.Shoji Kyoto Univ.. Measurement of MuTr raw signal Use oscilloscope & LabView Read 1 strip HV 1850V Gas mixture Ar:CO 2 :CF 4.
Aurore Savoy-Navarro 1), Albert Comerma 2), E. Deumens 3), Thanh Hung Pham 1), Rachid Sefri 1) 1) LPNHE-Université Pierre et Marie Curie/IN2P3-CNRS, Fr.
CALICE, CERN June 29, 2004J. Zálešák, APDs for tileHCAL1 APDs for tileHCAL MiniCal studies with APDs in e-test beam J. Zálešák, Prague with different preamplifiers.
CBM 12 th Meeting, October 14-18, 2008, Dubna Present status of the first version of NIHAM TRD-FEE analogic CHIP Vasile Catanescu and Mihai Petrovici NIHAM.
1 Front-end electronic for Si-W calorimeter Sylvie Bondil Julien Fleury Christophe de La Taille Gisèle Martin Ludovic Raux.
Mai 31th 2011 Christophe Beigbeder PID meeting1 ETD meeting Test setup : Activities in Bari, Univ of Maryland and at Orsay Test setup : Activities in Bari,
Front-end Electronic for the CALICE ECAL Physic Prototype Christophe de La Taille Julien Fleury Gisèle Martin-Chassard Front-end Electronic for the CALICE.
PHOTOTUBE SCANNING SETUP AT THE UNIVERSITY OF MARYLAND Doug Roberts U of Maryland, College Park.
VFE & PCB Status & schedule of production Presented by Julien Fleury Christophe de La Taille, Julien Fleury, Gisèle Martin-Chassard.
Setup for automated measurements (parametrization) of ASD2 chip
A General Purpose Charge Readout Chip for TPC Applications
ECAL front-end electronic status
96-channel, 10-bit, 20 MSPS ADC board with Gb Ethernet optical output
R&D activity dedicated to the VFE of the Si-W Ecal
A Readout Electronics System for GEM Detectors
Setup for measurements with SCT128 in Ljubljana: SCTA128VG chip
Electronics for the E-CAL physics prototype
A Low Power Readout ASIC for Time Projection Chambers in 65nm CMOS
Christophe de La Taille, Julien Fleury, Gisèle Martin-Chassard
UCSB Short-term Testing Plan
Christophe de La Taille, Julien Fleury, Gisèle Martin-Chassard
STATUS OF SKIROC and ECAL FE PCB
Time calibration Dmitry Chirkin, LBNL UC Berkeley, November 2004.
BESIII EMC electronics
SKIROC status CERN – CALICE/EUDET electronic & DAQ meeting – 22/03/2007 Presented by Julien Fleury.
The Ohio State University USCMS EMU Meeting, FNAL, Oct. 29, 2004
Presentation transcript:

Qualification Test of UFE Board  Schematic diagram of UFE  Board types and current status  Qualification test procedures  VA & UFE test setup  Test results  Conclusion C. H. Chung AMS TRD eeting, July 16 ~17.

Schematic Diagram of UFE VA32 HDR12 Preamp. Shaping Multiplexing Peak. T = 2.4  s Power:55mW Applied Power HCC Chip 12 bit ADC AD7476

UFE Board Types UFE45M21UFE45S17 UFE90S96 UFE90M18 UFE development made up to the present ADC Op. Amp VA

Test Procedures Measurements : Gain, Pedestals, Noise, Linearity, Connectivity VA Hybrid UFE w.o VA  Peaking Time = 2.4  s  Gain = 2.0 [ADC counts / fC]  Pedestals and Noise  All channels within  1% of the mean gain  All channels within 3% non-linearity  Connection test with external CAL Production More Qualification Tests  Mechanical Vibration  Thermo Vacuum  EMI

VA Hybrid Test Setup VA-DAQ setup * IDE Co. * Type of VA-chip: VA32HDR12 * Number of channels/chip: 32 * Number of chips/board: 1 * Value (pF) of calibration capacitor:10.00E+0 Labview w. ROOT VA DAQ PCB and Adapter board

VA Test Results(1) Peaking time & Linearity / channel Signal waveform of channel Oscilloscope Gain fitting vs. input charge

VA Test Results (2)

VA Test Results (3) Click to add text Typically all channels within 1% of the mean gain Mean = [mV/fC], Sigma =

UFE Board Test Setup Board Box Block diagram of DAQ system Control signal WIN NT CVI, ROOT Real mode : Pedestal and Noise CAL mode : Gain and Nonlinearity 4m

UFE Test Results (1) One Channel Pedestals and Gain linearity Noise = ADC counts Gain = 2.01 [ADC counts/fC] MIP signal in TRD = 55 Xe + 20%CO 2, gain = 3000(3.5  10 5 e-) S/N = 55/0.86 = 64

UFE Test Results (2) Pedestals and Noise

UFE Test Results (3) Non-Linearity = [Fit-Measured]/Fit upto 1.5[pC] Linear range : 0~1.5pC within 2% nonlinearity

UFE Test Results (4) External Connection Test

Conclusion Qualification test setup for VA and UFE board is ready and working successfully. 40 VA Hybrid were tested and two chips were malfunctioning. 12 UFE boards were produced and tested. Pedestal, Noise, Gain, Linearity, Nonlinearity, Peaking Time, Connectivity /Channel/ VA chip/ UFE-Board Some problems are under investigation. Defect on VAs after soldering with UFE, connectivity improvement. Calibration const. DB : data sheet in ASCII format on the WWW.