Fermilab High Intensity Neutrino Source R&D Program - Mission, Status, Plans, and Support Needs - For AD Department Heads March 2007 Bob Webber.

Slides:



Advertisements
Similar presentations
Overview of SMTF RF Systems Brian Chase. Overview Scope of RF Systems RF & LLRF Collaboration LLRF Specifications for SMTF Progress So Far Status of progress.
Advertisements

ILCTA-MDB RF Power Status 9/21/06 Reid 1 ILCTA-MDB Status 1.3 GHz RF Power Meson Detector Building 3.9 GHz RF Power A0 Building September 21, 2006 [John.
Final Design of a CW Radio-Frequency Quadrupole (RFQ) for the Project X Injector Experiment (PXIE)* Abstract: The Project X Injector Experiment (PXIE)
C. Rossi – L4 Project Meeting 3 March 2011 Status and Plans of 3 MeV Test Stand.
Superconducting Spoke Resonator Cavities and Cryomodules
Roger Ruber, Volker Ziemann, Gergana Hamberg Uppsala University
 An h=4 (30 MHz) RF system will be used for electron operation. For protons, this would correspond to h=56, and the 1 kV maximum gap voltage would only.
MuCool RF Status MICE Collaboration Meeting June 7-10, 2006, Fermilab A. Moretti June 9, 2006.
RF Unit Test Facility at NML & CM1 Test Plan Bob Kephart Fermilab IWLC-10 October 20, 2010.
MEBT & RT CH Section Thomas Page Fermilab Accelerator Advisory Committee May 10 th – 12 th, 2006.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
Front End Test Stand Klystron Commissioning Alan Letchford UKNF Plenary Meeting 22 nd April 2009.
Discussion on Studies at Test Stands Roger Ruber Uppsala University.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
F HINS Schedule of Activities in Meson During FY08 Bob Webber AD Safety Meeting December 5, 2007.
Test Stands Roger Ruber Uppsala University ESS TAC4 16 Feb
High Power RF Systems, Control and Distribution in the HINS Alfred Moretti, Brian Chase, Chris Jensen and Peter Prieto Fermilab Accelerator Advisory Committee.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
ANL-FNAL Collaboration on High Intensity Neutrino Source Activities G. Apollinari Introduction Collaboration Activities ‘05-’07 Achievements ’07-’10 Plans.
HLRF DRAFT Global Design Effort 1 Defining EDR* Work Packages [Engineering Design Report] Ray Larsen SLAC ILC Division for HLRF Team DRAFT April.
F Project X Overview Dave McGinnis October 12, 2007.
Proton Improvement Plan William Pellico FRA Visiting Committee Meeting March 14-15, 2011.
Linac R&D Update May 15, L-Band Source Consists of a LLRF system (VME/Epics based), a SNS High Voltage Converter Modulator (on loan), a Thales 2104C.
RF Development for ESS Roger Ruber and Volker Ziemann Uppsala Universitet 4 Dec Dec-20091RR+VZ: ESS RF Development.
Anders Sunesson RF Group ESS Accelerator Division
High Intensity Source R&D Overview or Multi MW Proton Sources G.A. – FNAL Steering Group – April 30 th ‘07 What R&D Status PS vs. “6 GeV ILC Test Line”
HINS Front-End R&D --- Status and Plans Bob Webber Fermilab Accelerator Advisory Committee August 7, 2007 Update of May 10 th – 12 th, 2006 AAC Presentation.
Americas Region: T4CM Status and Plans H. Carter TD SRF Dev. Dept. July 14, 2006.
MCTF 8/17/06 A. Bross MTA Activities and Plans MCTF August 17, 2006 A. Bross.
Ding Sun and David Wildman Fermilab Accelerator Advisory Committee
Project X Injector Experiment (PXIE) Sergei Nagaitsev Dec 19, 2011.
Horizontal Test Stands and CC2 Results Andy Hocker Testing an alternative ILC cavity design at USPAS (Q 0 =2.23E+02)
Fermilab Proton Driver Project Weiren Chou for Bill Foster Fermilab, U.S.A. October 20, 2004 Presentation at the Proton Driver Session ICFA-HB2004, Bensheim,
Jan 12, 2005G.W.Foster - Proton Driver General Meeting Proton Driver General Meeting Kick-off Presentation G. W. Foster PD General Weekly Meeting Jan 12,
Overview and Status of the Fermilab High Intensity Neutrino Source R&D Program Giorgio Apollinari for Bob Webber.
0 Plenty Energy Clean Environment Healthy Life Commissioning and Initial Operation of the KOMAC 100-MeV Proton Linac KOMAC / KAERI Kyung-Tae Seol
MICE Coupling Coil Testing at Fermilab All Experimenters Meeting Ruben Carcagno March 19, R. Carcagno - MICE CC Testing at Fermilab3/19/2012.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
HINS R&D Giorgio Apollinari Fermilab Accelerator Advisory Committee May 6-8 th, 2008.
Copyright © 2015 SCKCEN ADS accelerator developments presently on-going for MYRRHA and possibly for the Chinese-ADS Dirk Vandeplassche 1 Eucard-2 — APAE.
Overview of HINS Operations and Radiation Shielding Considerations in the Meson Detector Building Bob Webber August 16, 2006.
Proton Driver Resources & Schedule (R&D Plan) Rich Stanek May 10, 2005.
Comparison of Fermilab Proton Driver to Suggested Energy Amplifier Linac Bob Webber April 13, 2007.
June 3, 2004G.W.Foster - Proton Driver Proton Driver Project Development, Tactics & Strategy G. W. Foster Fermilab User’s Meeting June 3, 2004.
F. f 2 Definitions Proton Driver –Generic name for past ~15 years for new, higher intensity machines and schemes to replace present Linac and Booster.
F DOE Annual Program Review High Intensity Neutrino Source R&D in the Meson Detector Building Bob Webber & Giorgio Apollinari September 26, 2007.
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
Project X RD&D Plan 325 MHz Linac including High Intensity Neutrino Source (HINS) Program Bob Webber AAC Meeting February 3, 2009.
Proton Driver Status Bob Kephart Proton Driver Physics Workshop Oct 6, 2004.
Current Proton Driver Activities in the Accelerator Division Accelerator Physics and Technology Seminar Bob Webber February 2, 2006.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
Fermilab SRF Linac Development Steve Holmes Workshop on High Intensity Proton Accelerators October 19, 2009.
Project X High Power 325 MHz RF Distribution and Control Alfred Moretti, Nov 12, 2007 Project X Workshop.
Wish list from ESS Christine Darve H-ECCTD Kick-off meeting 16 March
Introduction to the effort on C-ADS accelerator physics and review charges Jingyu Tang For the Joint IHEP-IMP group on the C-ADS Accelerator Physics International.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
PSI, Zurich February 29 – March Session classification : Accelerator Concepts Tuesday, March 1, 2016 Summary Vyacheslav Yakovlev Fermilab, USA.
ILCTA-MDB RF Power Status 4/27/06 Reid 1 ILCTA-MDB Status 1.3 GHz RF Power 3.9 GHz RF Power Meson Detector Building April 27, 2006 [John Reid]
HINS Status and Strategy/Plans with Respect to Project X Bob Webber AAC Meeting November 16-17, 2009.
Fermilab-India Agreements and Collaboration Shekhar Mishra Project-X, International Collaboration Coodinator Fermi National Accelerator Laboratory Batavia,
High Intensity Neutrino Source HINS Linac Front-End R&D --- Systems Integration, Beam Diagnostics Needs, and Meson Lab Setup Bob Webber.
Bunch Shape Monitor for HINS Wai-Ming Tam Project X Collaboration Meeting September 11, 2009.
ESS LLRF and Beam Interaction
Uppsala Commitment to ESS and FREIA Planning
Chris Adolphsen Sergei Nagaitsev
ESS RF Development at Uppsala University
CEPC RF Power Sources System
High Intensity Neutrino Source R&D Overview
Advanced Research Electron Accelerator Laboratory
RF introduction Anders Sunesson RF group leader
Presentation transcript:

Fermilab High Intensity Neutrino Source R&D Program - Mission, Status, Plans, and Support Needs - For AD Department Heads March 2007 Bob Webber

Fermilab High Intensity Neutrino Source R&D The Mission –We have been tasked by the Directorate, since nearly two years ago, to assemble and operate with beam the front-end of the Proton Driver linac in Meson Detector Building by the end of 2010.

Fermilab β=1 Modulator β=1 Modulator 36 Cavites / Klystron TESLA LINAC 8 Klystrons 288 Cavities in 36 Cryomodules 1300 MHz β=1 β<1 TESLA LINAC 2 Klystrons 96 Elliptical Cavities 12 Cryomodules 1300 MHz GeV β=1 Modulator β=1 Modulator β=1 Modulator β=1 Modulator β=1 Modulator β=1 Modulator 10 MW TESLA Multi-Beam Klystrons 48 Cavites / Klystron β=.81 Modulator β=.81 8 Cavites / Cryomodule 0.5 MW Initial 8 GeV Linac 11 Klystrons (2 types) 449 Cavities 51 Cryomodules “PULSED RIA” Front End Linac 325 MHz MeV H-RFQMEBTRTSRSSRDSR Single 3 MW JPARC Klystron Multi-Cavity Fanout at kW/cavity Phase and Amplitude Control w/ Ferrite Tuners DSR β=.47 Modulator β=.47β=.61 or… 325 MHz Spoke Resonators Elliptical Option Modulator 10 MW TESLA Klystrons 80 % of the Cost ~80 % of the Engineering & Technical System Complexity

Fermilab Following Orbach’s ILC Timeline Comments Re-invigorated interest in the Director’s Office in Proton Driver ‘synergies’ with ILC and other ideas Director’s statement that he would seek to build 6 GeV section of ILC Establishment of steering group under Young-Kee Kim “to generate strategic plan for accelerator effort” Immediate impact on HINS/PD effort –None on HINS Meson R&D mission –Start (actually revival of) discussions on possibility of using 6 GeV section of ILC as the high energy end of an 8 GeV Proton Driver Don’t you simply add on the front 2 GeV? Are we expected to fit three times the RF power into the ILC physical geometry?

Fermilab From Director’s 3/9/07 ILC Fest Talk

Fermilab A Possible Outcome From Director’s 3/9/07 ILC Fest Talk Here we are, although the mission is actually 60 MeV and FY07/FY08 funding is actually $2.2/2.8M M&S

Fermilab HINS R&D Facilities Plan To address accelerator physics questions for a new concept, low-energy superconducting Linac we will construct key components of this Linac and integrate them into a demonstration accelerator in Meson Detector Building Pulsed 2.5 MW, 325 MHz klystron RF power source 325 MHz high power RF component test facility for studying RF power control devices Test stand for 325 MHz RT cavities and a test cryostat for 325 MHz SC spoke cavities Ion source and RFQ as a 2.5 MeV beam source 10 MeV Room Temperature Linac Three 325 MHz SC spoke cavity cryomodules All accelerator sections to be operated with beam up to 60 MeV to verify and quantify performance This all adds up to building and operating a first-of-its-kind superconducting 60 MeV H- linac

Fermilab 325 MHz Front-End Linac 325 MHz Klystron – Toshiba E3740A (JPARC) 115kV Pulse Transformer Modulator Capacitor / Switch / Bouncer Charging Supply RFQ MEBT SCRF Spoke Resonator Cryomodules RF Distribution Waveguide Ferrite Tuners Single Klystron Feeds SCRF Linac to E > 100 MeV

Fermilab Layout Through Second β=.4 Cryostat Ion SourceRFQMEBTRoom Temperature 16-Cavity, 16 SC Solenoid Section One Β=0.4 SSR 11-Cavity, 6-Solenoid Cryostat Two Β=0.2 SSR 9-Cavity, 9-Solenoid Cryostats 2.5 MeV50 KeV 10 MeV 20 MeV 60 MeV 30 MeV

Fermilab HINS Floor Plan in Meson Detector Building RF Component Test Facility Ion Source and RFQ Area 150 ft. Cavity Test Cave 60 MeV Linac Cave Klystron and Modulator Area Existing CC2 Cave ILC HTC Cave

Fermilab Klystron and Waveguide Installation

Fermilab Modulator Pulse Transformer Klystron Modulator and Pulse Transformer Modulator Signals at 5.6 KV into Resistive Load February 2, 2007 Modulator Output Current 200A/div Bouncer Voltage Capacitor Bank Voltage at 5.6 KV Pulse Transformer Output Current 2A/div at 36A

Fermilab RF Component Test Area Cage

Fermilab Electronics Installed Klystron solenoid power supplies Klystron and modulator interlocks Control system timing crate Personnel safety interlocks

Fermilab HINS Room Temp Cavity in Production Brazed cavity before welding end walls Body wall roughed in and annealed. Cavity in concept Copper spokes rough machined and annealed

Fermilab Bead Pull thru Completed RT CH-01 Relative field amplitudes Blue – measured Red - predicted View thru RF drive port during bead pull

Fermilab Superconducting Cavity Fabrication

Fermilab Quick Status 2.5 MW, 325 MHz modulator/klystron system is installed –Modulator is commissioned –Klystron commissioning planned to commence on April 2 Fast ferrite vector modulators await RF power testing Ion source work is proceeding on 50 KeV sources, both H+ and H- sources 2.5 MeV RFQ is in fabrication, delivery expected end of summer First Room Temperature spoke cavity will be ready for power testing in a few weeks Two superconducting spoke cavities are now in fabrication, delivery of first expected in April Prototype superconducting solenoid is built and final design is progressing Cryostat for SC cavity testing is in design review

Fermilab Recent AD HINS Effort

Fermilab Recent AD HINS Effort

Fermilab HINS Near-Term Schedule Goals in MDB 325 MHz RF power system commissioning –Commence in two weeks Component testing in RF test area –Awaiting RF power system commissioning First room-temp cavity full power tests –Late April / Early May Design and construct fenced ion source / RFQ area and move 50 KeV proton source from MS-6 to MDB –By mid-summer, i.e. before end of summer accelerator shutdown Procure and install RF power distribution system to RFQ area –By mid-summer, i.e. before end of summer accelerator shutdown Install RFQ and commission –Operate RFQ at full RF power by mid-September 2007 –2.5 MeV beam before end of calendar year 2007

Fermilab Tasks Required for Near-Term Objectives Water –Install new pump on existing skid –Install water to ion source/RFQ –Develop design specs for new skid with higher flow capacity Mechanical –Install coax transmission lines to cavity test cave –Construct ion source/RFQ area fencing –Support ion source installation in MDB –Design/Install RF distribution components to RFQ Vacuum –Establish vacuum system for room temp cavity testing in cave –Design/install vacuum system (with Piekarz et al.) for ion source/RFQ EE –Deliver ~ 6 regulated power supplies for ferrite vector modulators (testing and RFQ) –Engineering for global solenoid, steering, and FVM power system design –Charging supply

Fermilab Tasks Required for Near-Term Objectives Controls –Provide interface with” ILC Controls” so we aim for common methods –Continued/enhanced daily controls support –EPICs database management and entry –EPICS applications –New timing system rate generator hardware RF –Provide/commission initial LLRF system Cryo –Support TD with test cryostat cryogenics system issues –Install cryo transfer lines into cavity test cave –Support TD with accelerator spoke cavity cryostat and interface design to understand Linac enclosure cryo physical requirements/features Instrumentation –Supply Semenov digitizer boards

Fermilab HINS R&D Objectives Superconducting cavity test cryostat installation and operation Linac cave design, construction, and utilities Demonstration of independent RF amplitude & phase control of multiple Room Temperature cavities on single klystron Room temperature Linac installation 10 MeV operation Ready to install SC cavity cryostat(s) and high energy beam transport in Linac cave in 2010

Fermilab Tasks Required for Objectives Water –Install new skid –Install water to Linac cave Mechanical –Install coax transmission lines to room temp section of Linac cave –Install room temp Linac beam line and components Vacuum –Install vacuum system for room temp Linac EE –Complete engineering design for global solenoid, steering, and FVM power system –Deliver ~ 40 power supplies for ferrite vector modulators –Install/commission power system for room temperature Linac components –Deliver final klystron charging supply –Vacuum controls

Fermilab Tasks Required for Objectives Controls –Provide interface with” ILC Controls” so we aim for common methods –Continued/enhanced daily controls support –EPICs database management and entry –EPICS applications –Hardware support RF –Provide/commission multi-cavity LLRF system Cryo –Support TD with test cryostat cryogenics system issues –Install cryo transfer lines into cavity test cave –Support TD with accelerator spoke cavity cryostat and interface design to understand Linac enclosure cryo physical requirements/features –Completer Linac cave cryo system design Instrumentation –Specification/design/engineering/procurement of room temp Linac beam instrumentation –Suppy/install room temp Linac beam instrumentation

Fermilab Conclusion A program to address key accelerator physics and technology questions of a new concept, low-energy superconducting Linac is actively being pursued The present mission is to assemble a ~60 MeV front- end demonstration including three superconducting cavity cryomodules by 2010 Facilities are being out-fitted now 325 MHz RF power will soon be available Copper and Superconducting cavity design and first article fabrication is well underway Plan to have 2.5 MeV beam from RFQ by end of 2007 Increased AD support is needed to stay on track for coming year objectives