LS1 planning meeting 15.8.2013. Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore.

Slides:



Advertisements
Similar presentations
TC meeting /11/14TC meeting2 ALICE LS1 plan from now till MarchWeeks Install TRD infrastructure46 TRD4&5 (and counterweights removal)47.
Advertisements

André Augustinus 16 June 2003 DCS Workshop Safety.
MOM Summary 19/01/10 Water Now the ice has cleared I am able to get on the roof again. Could do with getting the conductivity readings fed back similarly.
LS1 planning meeting Activities weeks 13, 14 & 15 22/3/13LS1 planning meeting - A.Tauro2.
LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation.
June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.
SR1 ongoing workH.Pernegger21/2/02 Ongoing work in SR1 and preparations for detector macro assembly Heinz Pernegger.
May Exp-Area meeting1 Safety Systems Installation status Flammable Gas Detection System Fire Detection System in SG8 ODH Detection System CO2 Detection.
ALICE planning meeting /12/10 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
TC meeting P2 planning wks 7&8 A.Tauro
Notes After TIG 17/7/08 HF+ Move out of garage: Aug 15* Platform+table+collars+racks+BP support (jack up for platform) = 3 days Controls for motors = 1.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
LS1 reference slides LS1 plans Detector’s plans Services and central systems availability 8/2/13LS1 planning meeting - A.Tauro1.
ALICE 5 o’clock meeting Wk 50. INDICO You’ll find this meeting here: – The full shutdown planning.
Claudio Bortolin. 1 st June: PT100 electrical connection failure (Temp Chiller water In&Out) 1) it required an access to the cavern to be fixed 2) access.
ISOLDE: Status report building th ISCC meeting CERN, 22 October 2013 Maria Borge, Erwin Siesling.
ALICE Collaboration Meeting Heidelberg Services Update  Progress on services Detector cabling Gas systems Cooling systems  Rack footprint  Primary electrical.
P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.
TS4 preparatory meeting TS4 – weeks Underground access possible in week 51 – as from Monday morning 9:30 –Ulli and Philippe will start.
winter shutdown preparatory meeting A.Tauro /12/11ALICE winter shutdown schedule - A.Tauro 1.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
Test beam setup: status report 31/03/2009 M. Alfonsi (CERN)
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
ALICE 5 o’clock meeting Wk 51. INDICO You’ll find this meeting here: – The full shutdown planning.
Claudio Bortolin. Drilling: – tungsten carbide tip welded on twisted ss cable – drill to operate the rotation – counter-flow at 200 mbar w/manometer to.
EN-CV interventions during YETS
ALICE TC meeting – Plans for the next technical stop A. Tauro.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.
TS planning meeting 7 to 11 Nov Technical stop Wk 45: Monday 7 th to Friday 11 th November Ramp down magnets (SL): Mon 8:00 – 8:30 (latest) RP search.
winter shutdown planning A.Tauro
winter shutdown planning A.Tauro
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
TS May 9-12 – Schedule SL instructions: Both magnets ramped down Monday May 9 th 7:00 latest Thursday: check with CCC before restarting magnets: – TE-EPC.
LS1 planning meeting /4/13 ALICE TBStatus of LS1 activities - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare.
TC meeting P2 planning wks 9&10 A.Tauro
TC meeting LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS extraction, remove RB24 beampipe and PMD10 Remove.
André Augustinus Infrastructure  Turbines  Radmon  Thermocouple readout  Netgear redundancy  Other cavern items  Cooling CRs  Other CR and surface.
ALICE 5 o’clock meeting Wk 49. INDICO You’ll find this meeting here: – The full shutdown planning.
TC meeting P2 planning wks 5&6 A.Tauro
TS2 preparatory meeting A.Tauro. General information LHC- TS2: from Monday 31st 6am, to Friday 4th 5pm LHC beam stops on Monday morning.
LS1 planning meeting /7/13LS1 planning meeting - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS.
1 Planning DCS WS L.Jirdén. 2 TPC HMPID ACORDE FE PC Console DSS Disk SRV DB-SRV App GW sensors actuators DSS sensors actuators PC room SXL2.
1 Update on Power Supplies TB L.Jirden u LV u Concerns u Orders & deliveries u Maintenance u HV u Overview u purchasing.
TS3 preparatory meeting 14/9/2012 TS3: 17-21/
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
ALICE 5 o’clock meeting Wk INDICO You’ll find this meeting here: – The full shutdown planning.
LHCb Week 27/11-01/ D.LACARRERE on behalf of Expt Area Team1 Experimental Area Latest News from IP8  Radiation Shield – Upper & Front Parts  Structures.
TS3 preparatory meeting A.Tauro. General information LHC-TS3: from Mon 9 6am, to Fri 13 5pm LHC beam stops on Mon morning at 6:00.
TC meeting P2 planning wks 3&4 A.Tauro
1. Road to the EDR 2 Requirements Safety system Transfer line concept Plant concept design Requirements Evaporator concept and performance Transfer line.
LHCb CO 2 cooling meeting Burkhard Schmidt – May 20,
ALICE planning meeting /11/10 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
DCal-ALICE integration and installation plan and status A. Tauro.
21 Mar 2007ALICE - Paul Dauncey1 ALICE CR07: Installation and Commissioning Paul Dauncey Material from: L. Leistam: “ALICE Status” W. Riegler: “Commissioning.
1 04 April 2007 L. Roy Detector Safety System for infrastructure - General fire detection (barracks, cavern) - Sniffer system (smoke detection above the.
ALICE Installation: Planning Meeting Agenda: 1- ALICE shutdown schedule 2- Miniframe removal sequence.
ALICE 5 o’clock meeting Wk 50. INDICO You’ll find this meeting here: – The full shutdown planning.
EYETS planning A.Tauro.
ALICE 5 o’clock meeting Wk 51.
TS2 preparatory meeting
LS1 planning meeting - A.Tauro
LS1 planning meeting
ALICE 5 o’clock meeting Wk
TS1 preparatory meeting
Shutdown conclusion, LS1 and LS2 planning - A.Tauro
ALICE 5 o’clock meeting Wk
Teleconference ACS – FREIA 19th June 2017
Polarized 3He target installation
Presentation transcript:

LS1 planning meeting

Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore DCal SM installation delayed by one week (Joseph informed) Issues: –DCal installation  DCal phone meeting 3 rd September (tbc) –TRD SM insertion  Bernd says realistically speaking we will have only three SMs during LS1. –TOF slot  depending on: Date completion LV modification BKF Availability all rails (Yannick) + installation (10 SM must be moved) I hope we can finalize these details by beginning September. 15/8/13LS1 planning meeting - A.Tauro2

15/8/13 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS extraction, remove RB24 beampipe and PMD10 Remove PHOS cradle and modules, transfer TOF crates on SF11-13 Modify L3 services and install YP for TRD1714 Modify L3 services, remove TRD17 and rework LV distr. TRD , DCal tests in SXL Modify L3 services, open low-beta and swap Q5L8 magnet, DCal tests in SXL2, new UPSes20-23 Swap PHOS beams with DCal beams25-26 Install DCal support structure and rails27-30 DCal and PHOS services + complete support structure and rails31-37 Open Days – / Install 2 1/3 DCal modules, new L3 ventilation ducts PX24 (Oct-Nov)42 Install 3 DCal modules (C-side) and remove infrastructure (w45)43-45 Rework LV distr. TRD TOF electronics repair49-51 Xmas pause52-1 Done Ongoing Done LS1 planning meeting - A.Tauro3 Done

15/8/13 Detailed plan till end of the yearWeeks Empty SA2 (SX2) + install new CR1 racks30 Install new CR1 racks. DCal Al rails and I-side extensions 31 DCal Al rails and I-side extensions. Anti-collision system32 DCal cabling, work at DCal support structure, clear SX2 hall for OD 33 DCal cabling, clear SXL2 for DCal SM storage, install 2 T0 racks (C33-34), reinstall CR1 rack door covers34 Test anti collision system (Mon or Tue), CO2 cabling, arrival 4 DCal SMs (Tue/Wed)35 Finalize DCal support structure (Mon-Wed), installation CO2 bottles C-side, maintenance TRD rotator, +1TRD (tbc)36 Fix DCal rotator (Manoel), DCal installation platform, arrival dipole OD37 Open low-beta and install scaffolding, PHOS and DCal cooling pipes38 OD preparations - OD39 Remove scaffolding (start Tue), remove ACR tables, remove portable chiller40 Close low-beta41 Install 2 1/3 DCal modules, PX24 scaffolding (L3 ventilation)42 Modify DCal infrastructure, PX24 scaffolding (L3 ventilation)43 Install 3 DCal modules (C-side), new L3 ventilation ducts44 Remove DCal infrastructure and install TRD infrastructure45 Rework LV distr. TRD and install TOF rails46-48 TOF electronics repair49-51 September August LS1 planning meeting - A.Tauro4 October Nov-Dec

15/8/13LS1 planning meeting - A.Tauro5 LS1 plan 2014Weeks Extend SAA3 shielding2-6 Install top/bottom TRD counterweights7-8 Remove comp. magnet and Suspend Miniframe9-11 Install TRD with yellow platform (bottom)12-14 ‘Un-suspend’ Miniframe15-16 Reinstall TRD1717 Concrete walls & TRD installation frame18-19 Install TRD4-5 (top) & counterweights20-21 Remove TRD infrastructure22 Reinstall ZEM and comp. magnet23 Reinstall and bakeout RB24 beampipe24-25 … … Install 4 PHOS + 3 DCal (A-side) supermodules Reinstall PMD Close plug, L3 doors, reinstall shieldings45-48 (Nov.) latest

Status UPS upgrade CR1: done. 2 racks less than foreseen CR2: done. Y row UPS, X-Z rows normal power. Replacement 32A -> 63A CB next week CR3: 1-2 racks to be connected CR4: done CR5: CV cable to be installed Rack between EBD and EXD installed last week To be done: Interlock with SX2 ventilation On-battery signal False floor mezzanine UPS support and false floor in front of UPS500 Project should be completed by end August 9/8/13LS1 planning meeting - A.Tauro6

Renaming CRs racks We have renamed all the CR1-4 racks, in order to: – avoid non-conventional naming (e.g. X01A, X01B…) – foresee place for non-installed racks  update CR drawings (Arturo, Maridor)  update DCDB information (Andre, Mateusz)  install proper labels (Andre, Fred)  inform detectors (Andre) 15/8/13LS1 planning meeting - A.Tauro7

ACR planning Kick off meeting Wed 4 th September 14:00 Before end August: Remove personal objects (all subdetectors) w34-35: move DCS, SLIMOS, LACS consoles and visitor token distributor to WR3 (upstairs) + key PAD/MAD Remove screens and PCs (and WR1&2 tables) Remove fire detection system (incl. piping) September: w36 (Mon-Tue): remove Ethernet cables (MTE) w37-38 (tbc): remove 220V cables (SPIE) + lights October-December: w40 (starting Tue 1/10): move ACR tables and chairs to SX2 (right after OD) Remove ventilation outlets Remove false ceiling, walls and doors. Install new windows Install isolation panels and electrical ducts concealed in the plasterboard walls Install false floor and cable trays January-February: Install 220V and Ethernet cables Modify ventilation ducts (and unit) Install new false ceiling and lights Install fire detection system March: Install tables, WiFi, move consoles back in ACR, telephones Finalize cabling April-May: TVs, screens and PCs Contingency 15/8/13LS1 planning meeting - A.Tauro8

Opening low-beta (w38) 15/8/13LS1 planning meeting - A.Tauro9 ALTEAD: remove blocks 9 to 24

15/8/13LS1 planning meeting - A.Tauro10 Scaffolding 35 persons max.

TENT LHC DIPOLELHC DIPOLE Kids corner DAQ TOF TRD ? Cosmo phone ITS Exhibition Control Room Annex 4 – P2 surface entertainment area (SX2) Restaurant DCal ? Shop 9/8/13LS1 planning meeting - A.Tauro11 DCS

Cooling All CP in stby (except SSD-SDD) 1 chiller put in operation already this week. Primary cooling stably back in w40 D.Piednoir absent till 9/9  contact Jani Lehtinen or Denis Dumas if needed Portable chiller needed by LHCb w40 Power cut (18kV) foreseen on 2-3/9 in order to make electrical connections in SU2  Lonjon still to confirm 9/8/13LS1 planning meeting - A.Tauro12

Cabling DCal: – LV, Ethernet, HV ongoing. – Should be completed by next week  however LV cable too short, CH has ordered more. LV consolidation: – Restart next Monday, once Samuel is back – Charles-Henri to review schedule with Samuel CO2: – Started, will be finished by end August

PHOS cabling & DCal 15/8/13LS1 planning meeting - A.Tauro14 PHOS cables and fibers below space-frame re-arranged such to be able to install DCal SMs.

Status CO2 project Cables bundle and minimax boxes done and at Cern Cabling in progress from Cr5 to Ux25 Installation in October Thermo cables ordered Pyrotechnic valves at P2 Bottles refilled  installation in September System installed before end of year

Status N2 project 15/8/13LS1 planning meeting - A.Tauro16

SM to be moved by 1m – 1.3m in A-side directionSM to be moved by 15cm in C-side direction TOF interventions Yannick informed. All rails should be ready before TOF intervention (November)

Rain - actions Coming two weeks: GS to contact TSO in order to establish action plan in case of rain SXS2: roof inspected and cleaned last week (GS) >>> ACR: GS will move pipe outside SX2 building <<< P2: Vallier has intervened this week to clean both foul and rain water networks  now regular cleaning Long term: modify and repair the P2 drainage network – See R.Morton’s presentation at July LSC meeting: confId= /8/13LS1 planning meeting - A.Tauro18

Gas Still in the process of searching and fixing leaks on SF6 and C2H2F4 lines (DT and MEF). SG2: scales (C2H2F4 and i-buthane) will be installed next Monday. Ar dewar re-connected, will be put in service in the coming weeks. Then the N2 dewar will be removed (September). SF6: heater will be installed around SF6 bottles (already done in CMS) this winter. 9/8/13LS1 planning meeting - A.Tauro19

Access and perturbations The UMTS equipment covering ALICE lift and cavern will be replaced and upgraded to HSPA+ the 15th August. –The UMTS900 services in the cavern could be disrupted during 30 minutes. –The work will be performed at the surface in the SD. –The GSM and TETRA services wont be affected. Test 18kV 2-3/9  will stop UX racks (tbc) Les tests secours CERN seraient maintenus au 3 septembre 2013 de 7h00 à 7h10. Les tests auto-transfert seront probablement planifiés mi-septembre après la remise en service de la liaison MP2 (de nouveau en panne depuis vendredi dernier 9 aout 2013…) 15/8/13LS1 planning meeting - A.Tauro20

AOB Leak rack A21  water stopped. Issue: relief valve hidden below cables. Action: Philippe to check with Andre next Monday CV promised to fix leaks along ITS ventilation duct CR5->UX. Nothing done yet. Fan replacement for Wiener and CAEN (April)  Andre to contact concerned detectors. ADAM: signal ON/OFF. Request sent to Jacopo/Donatella 15/8/13LS1 planning meeting - A.Tauro21