Update on the SOUTHWEST COASTAL LA Project Governor’s Advisory Commission Meeting August 7, 2013 Abbeville, LA committed to our coast.

Slides:



Advertisements
Similar presentations
Flood Risk Management Pete Rabbon Association of State
Advertisements

Restoring and protecting Louisiana’s coast January 18, 2011 CPRA Meeting David Peterson Asst. Attorney General and AG Designee to CPRA Civil Division Lands.
Status Update on Future Water Quality Strategies for the Refuge Kenneth G. Ammon, P.E., Deputy Executive Director, Everglades Restoration and Capital Projects.
Update on Southwest Louisiana Projects Office of Coastal Protection and Restoration.
Shell Island West NRDA Restoration
US Army Corps of Engineers BUILDING STRONG ® LOUISIANA COASTAL AREA (LCA) PROGRAM UPDATE June 16, 2010 Presented by: Bren Haase, OCPR Mark Wingate, USACE.
US Army Corps of Engineers BUILDING STRONG ® Louisiana Coastal Area Modification of Davis Pond Study Overview Governor’s Advisory Commission on Coastal.
1 Coastal Wetlands Planning, Protection, and Restoration Act (CWPPRA) Update Bren Haase Louisiana Office of Coastal Protection and Restoration Presentation.
Mid-Barataria Diversion - Status Update committed to our coast Andrew Beall Project Manager Governor’s Advisory Commission Meeting December 5, 2012.
Fiscal Year 2013 Annual Plan BRIEFING TO: COASTAL PROTECTION AND RESTORATION AUTHORITY Baton Rouge, LA January 18, 2012.
US Army Corps of Engineers PLANNING SMART BUILDING STRONG ® Project Planning with the U.S. Army Corps of Engineers (USACE) Presenter Name Presenter Title.
SMART Feasibility Study Process
EPA Update- Bob Judge Maine Air Quality Monitoring Committee April 18, ) NAAQS schedule 2) Budget 3) Technical Systems Audit.
Briefing to the Central Valley Flood Protection Board on Status of the FCSA July 12, 2013 Central Valley Integrated Flood Management Study.
April, 2008 Office of Coastal Restoration & Management PROJECT UPDATE Office of Coastal Restoration & Management PROJECT UPDATE.
Coastal Texas Protection and Restoration Project
US Army Corps of Engineers BUILDING STRONG ® North Atlantic Coast Comprehensive Study U.S. Army Corps of Engineers Coastal Storm Risk Management Planning.
OCPR Performance During Hurricane/Flood Fights (Disasters Averted) (Disasters Averted) October 29, 2008 Jerome “Zee” Zeringue Governor’s Office Coastal.
Regional Flood Plain Management Council April 15, 2015 H-GAC December 2nd.
1 Technological Innovations and Future Vision of Technical Support Louisiana Coastal Protection and Restoration and Mississippi Coastal Improvements Program.
Integrated Ecosystem Restoration and Hurricane Protection: Louisiana’s Comprehensive Master Plan for a Sustainable Coast.
Louisiana’s 2012 Comprehensive Master Plan for a Sustainable Coast Path Forward on Nonstructural Program Implementation CPRA Meeting - October 17, 2012.
LCA Mississippi River Hydrodynamic and Delta Management Study (MRHDMS) Carol Parsons Richards River Studies Manager Governor’s Advisory Commission on Coastal.
Sacramento Local Agency Formation Commission (LAFCo) UPDATE ON PROPOSED SMUD ANNEXATION Presented to Yolo LAFCo September 19, 2005.
Restoring and protecting Louisiana’s coast David Peterson – La. AG’s Office – Asst. Attorney General - AG Designee to CPRA Ken Ortego – Vilar and Elliott.
Defining Louisiana’s Coastal Zone: A Science-Based Evaluation of the Louisiana Coastal Zone Inland Boundary revised October 2010 A summary of the results.
Integrated Regional Watershed Management Plan Presentation – March 12, 2013 HLVRCD.
Land Building Sediment Diversion at Myrtle Grove: Evolution & Status Update Brian Vosburg Geologist Governor’s Advisory Commission Meeting August
PLANNING TEAM Mississippi Department of Environmental Quality (and Coordinating Agencies) Mississippi State Department of Health Mississippi Department.
Civil Works Transformation Foundations of SMART Planning
NOAA Restoration Center Implementing the Gulf Regional Sediment Management Master Plan …responding to an ongoing emergency, improving responses to new.
Increase Atchafalaya Flow to Terrebonne Governor’s Advisory Commission Meeting 7 August 2013 committed to our coast.
SOUTHWEST COASTAL AND SOUTH CENTRAL PROJECTS – Update and Path Forward CPRA Meeting January 22, 2013 committed to our coast.
Update On Mississippi River Delta Management Plan Presented at August 20, 2009, Meeting of Governor’s Advisory Commission on Coastal Protection, Restoration.
LCA Comprehensive Study Louisiana Coastal Area, Louisiana- Comprehensive Coastwide Ecosystem Restoration Feasibility Study.
One Team: Relevant, Ready, Responsive, Reliable US Army Corps of Engineers 1 Coastal Protection and Restoration Advisory Committee 3 April 2006 D
Mississippi River Long Distance Sediment Pipeline Project Louisiana Office of Coastal Protection and Restoration Coastal Protection and Restoration Authority.
Oil Spill Restoration Planning Part 2 (RESTORE Act, Criminal, NRDA, SEPs) Kyle Graham Deputy Director CPRA May 15, 2013 committed to our coast.
Northstar Commuter Rail Project Update Mark Fuhrmann, Project Director Rich Rovang, Deputy Project Director, Design and Construction Chris Weyer, Assistant.
Presentation to the Little Rock SAME Small Business Symposium by LTC Mark Jernigan Deputy Commander, New Orleans District April 28, 2009 Presentation to.
The Science and Policy of Louisiana Coastal Ecosystem Restoration.
STATUS UPDATE FOR CPRA January 26,  Study combines Cong. Boustany Recon with LCA Chenier Plain Effort  Cost Share Agreement signed in Jan
STATUS UPDATE FOR CPRA September 21,  We are 2.5 years into the Feasibility Study  Study is being cost shared between the State and the.
Consistency with the 2012 Coastal Master Plan: Guidelines for Restoration Projects Receiving State Funding Bren Haase CPRA Board Meeting September 18,
New Orleans Hurricane Protection System Overview by Mike Park HPS Program Manager Task Force Hope U.S. Army Corps of Engineers March 19, 2008.
Fiscal Year 2009 Annual Plan: Ecosystem Restoration and Hurricane Protection in Coastal Louisiana Draft.
Coastal Forest Conservation Initiative Update CPRA Meeting July 18, 2012.
Implementing the Master Plan Kyle Graham Deputy Executive Director CPRA June 20, 2012 committed to our coast.
Is the Mid-Atlantic Region Water Rich? Presentation to 5 th Mid-Atlantic Regional Planning Roundtable November 7, 2008 Joseph Hoffman, Executive Director.
LCA Program State Concerns Moving Forward February 25, 2010 Kyle Graham Governor’s Office Coastal Activities.
DEEPWATER HORIZON $1B EARLY RESTORATION AGREEMENT Governor’s Advisory Commission May 11, 2010.
US Army Corps of Engineers Comprehensive Everglades Restoration Plan Master Recreation Plan.
2 West Sacramento, California Project General Reevaluation Report Letter of Support for the West Sacramento General Reevaluation Report Agenda Item 4G:
PROJECT PLAN: The Nature Conservancy Corps of Engineers ICPRB Presentation Potomac Watershed Roundtable January 9, 2009.
C A L I F O R N I A E N E R G Y C O M M I S S I O N Integrated Energy Policy Report Workshop Landscape-Scale Environmental Evaluations for Energy Infrastructure.
2017 Coastal Master Plan Overview Karim Belhadjali
Middle Fork Project Relicensing Process Plan April 25, 2006.
Texas GLO & US Army Corps Join on Texas Upper Coast Storm Barrier Study.
IEEE /r5 Submission November 2008 John Notor, Cadence Design Systems, Inc.Slide 1 IEEE IMT-Advanced Review Process Date:
Project Updates Louisiana Water Synergy Project May 19, 2016.
BUILDING STRONG SM Revitalizing and Expanding Partnerships Charles E. Shadie, P.E. Senior Hydraulic Engineer Mississippi Valley Division U.S. Army Corps.
STUDY TITLE Presenter Name Presenter Title Duty Location
Louisiana’s Coastal Protection and Restoration Update
CPRA Program Update ACEC, New Orleans Chapter April 14th, 2016
Louisiana Coastal Area
RC Ohio Valley Region Strategic and Annual Planning Process January – September 2016 Notes Fr John says greeting and reflects on 75 anniversary and then.
2040 Long Range Transportation Plan Update
FY 2019 Close Schedule Bi-Weekly Payroll governs close schedule
2023 Coastal Master plan committed to our coast
White Flint North Entrance Feasibility Study
Presentation transcript:

Update on the SOUTHWEST COASTAL LA Project Governor’s Advisory Commission Meeting August 7, 2013 Abbeville, LA committed to our coast

Coastal Protection and Restoration Authority of Louisiana

The Feasibility Cost Share Agreement was signed between CPRA and the Corps in January The study is multi-purpose = coastal restoration and hurricane protection. Is cost shared between the CPRA and the Corps. The Project Delivery Team has the active participation of many stakeholder groups and agencies. Study was transitioned to the Corps new 3X3X3 planning paradigm (SMART Planning). Funds have been made available to complete the study. Southwest Coastal Overview

Coastal Protection and Restoration Authority of Louisiana Status The Study has produced a Feasibility Scoping Report and a Value Engineering Report. Full structural inventory has been completed. Hydraulic models developed: ADCIRC model (storm surge) Regional Circulation (salinity) The current schedule indicates a Draft Feasibility Report in November 2013 and and a Chief’s Report Milestone in September The Alternatives Milestone (all work to date, plus the alternatives carried forward) was approved by the Corps vertical team in June Measure types under evaluation are in concert with the 2012 State Master Plan.

Coastal Protection and Restoration Authority of Louisiana

NER Focused Array of Alternatives No Action Plan (Future without-project condition) Large Integrated Restoration Across Basins Moderate Integrated Restoration (Hydrologic Emphasis) Moderate Integrated Restoration, including Gum Cove Entry Salinity Control (Emphasis) Interior Perimeter Salinity Control (Emphasis) Marsh and Shoreline (Minimal Hydraulic & Salinity Control)

Coastal Protection and Restoration Authority of Louisiana

NED Focused Array of Alternatives No Action Plan (Future without-project condition) Lake Charles Risk Reduction Structural Feature Abbeville Risk Reduction Structural Feature Lake Charles Structural and Abbeville Non- Structural Abbeville Structural and Lake Charles Non- Structural Non-structural plan

Upcoming Milestone Schedule 29 Oct 2013Tentative Selected Plan 15 Nov 2013Public Review/ ATR/ IEPR 30 Jun 2014 Final Report Milestone/ CWRB 25 Jul 2014 State and Agency Review Complete 30 Sep 2014 Chief’s Report Milestone 9

Coastal Protection and Restoration Authority of Louisiana Discussion/Questions Norwyn Johnson Darrel Broussard Southwest Coastal