Chad Thompson, ERCOT Special ROS PGRR011 Workshop October 21 st, 2011 SCED Overview and Results.

Slides:



Advertisements
Similar presentations
Bill Blevins Management of the West-North Stability Limit Under the Nodal Market.
Advertisements

Additional CREs to address Stability Limits Beth Garza TAC June 26, 2008.
Intra Hour Tagging/Oasis During System Contingencies The transmission tagging process was initially developed to solve an after the fact accounting issue.
October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
Ancillary Services and SCED Jeff Gilbertson Market Analyst Congestion Management Working Group 9/4/2013.
Critique of Proposal to Designate SAPS-Shrew as CRE Shams Siddiqi, Ph.D. Crescent Power, Inc. (512) June 4, 2009.
Discussion: Use of RAPs in system operations Kris Dixit 1.
Real-Time Transmission Congestion Management & Market Effects
ERCOT Compliance Audits Robert Potts Sr. Reliability Analyst March 23, 2005.
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N 1 Network Operating Committee (NOC) June 12 th, 2014.
ERCOT SOL Methodology for the Planning and Operations Horizons Stephen Solis 2014 OTS 1.
JACKSBORO TO WEST DENTON 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
System Operations Staffing Request Presented to the ERCOT Board Of Directors By Sam Jones, COO November 16, 2004.
Peak RCCo Performance Metrics Draft –November 2013.
10/03/ Report on Existing and Potential Electric System Constraints and Needs Within the ERCOT Region October 3, 2002.
July 30, 2015 TAC Meeting Update to COPS Michelle Trenary August 12, 2015.
Proposed Revision to the Shadow Price Cap and Power Balance Penalties in SCED Same Transmission Element.
Reliability Requirements Bill Blevins Manager of Operations Support ERCOT.
SPS policy – Information Presentation Presentation to ROS June 16, 2004.
April, 2008 Maximum Shadow Price. April, 2008 Protocol Requirement: Transmission Constraint Management (2)ERCOT shall establish a maximum Shadow.
March 11, 2011 RPG Meeting Lower Rio Grande Valley (LRGV) Import.
Lead from the front Texas Nodal 1 Texas Nodal Energy Management System Requirement Documents December 5, 2006 Jay Dondeti EMS Project.
John Dumas Director of Wholesale Market Operations Jeff Billo Manager of Mid Term Planning Dan Jones Director with Potomac Economics, the ERCOT IMM Board.
Constraint Management Plans (CMPs) An Ops Planning Perspective Nitika Mago Operations Planning, ERCOT.
EDS 2 Early Delivery Systems Review and Request for Approval May 2007 John Webb.
1Texas Nodal Market Trials Update. 2Texas Nodal Full System Market and Reliability Test 24-Hour Test Observations Duration of Test for Week of 8/ Hour.
June 19, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
January 21, 2010 Security Constrained Economic Dispatch Resmi Surendran.
SM April Peak Week Operations Review Presentation to ISO Business Issues Committee May 22, 2002.
Presentation to House Regulated Industries Committee Chairman Phil King Trip Doggett Chief Operating Officer The Electric Reliability Council of Texas.
Responding to post contingency overloads, IROL’s and SOL’s Art Gardiner – CPS Energy Steve Rainwater - LCRA 1.
Current Export Initiatives Jerry Mossing Exports Workshop February, 16,2006, Metropolitan Center, Calgary.
CMWG Update to WMS Report of CMWG Meeting of M Wagner Edison Mission Marketing & Trading.
Transmission Outage Process April Purpose In compliance with the Protocols and the Electric Reliability Council of Texas (ERCOT) Operating Guides,
Nodal ATF 1 Nodal Advisory Task Force Update for TAC September 2 nd, 2010.
WEST LEVEE TO NORWOOD 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
© Property of ERCOT /17/20041 RTCA, CAM, and SFT Presented by: John Adams November 17, 2004.
ERCOT Operational Audit 2005 August 1 - August 19, 2005.
January 21, 2008 TPTF 168 Hour Test Initial Approach Discussion.
July 30, 2015 Technical Advisory Committee (TAC) Update to RMS Kathy Scott August 4, 2015 TAC Update to RMS 1.
Appeal of PRS Action NPRR 351, Calculate and Post Projected Non-Binding LMPs for the Next 15 Minutes Floyd Trefny Texas Steel Companies.
Lance Cunningham, Ph.D., PE November Frisco, TX 2.
Texas Nodal © Electric Reliability Council of Texas, Inc. All rights reserved. 1 Nodal Verifiable Costs Process WMS Meeting May 15, 2007 Ino.
Managing of Limits during Loss of Analysis Tools/ EMS April 23, 2014.
1. Non-Dispatchable Resources and EIS Market Carrie Simpson May 30,
Operating Guide and Planning Guide Revision Requests Blake Williams, ROS Chair September 13, 2012.
1 State Estimator performance. 2 State of Technology Many metrics have been proposed for measuring State Estimator performance.. PI = min Σ( Z – h i (x))^
Grid Operations Report To ERCOT Board Of Directors December 16, 2003 Sam Jones, COO.
October 16, 2009 RPG Meeting ERCOT Independent Review of the Corpus Christi Improvements Project Jeff Billo.
Current Operational Challenges Computing the West – North Limits Potential IROLs Local Voltage & Thermal issue (OOME) High Voltage Outages.
Scheduling and Operating Transmission Devices in the Nodal Environment.
1 Nodal Stabilization Market Call December 27, 2010.
POWER SYSTEM PLANNING CHARTER AND PROCESSES Presentation to TAC May 6, 2004 Transmission Services Ken Donohoo, Manager of System Planning Dan Woodfin,
Joint PLWG/CMWG Assignment Update to ROS September 15, 2011.
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
RCWG Update to WMS March 7, Draft NPRR, Caps and Floors for Energy Storage Resources Chair of ETWG gave high level overview ERCOT had questions.
Response to TAC Questions on PGRR031 TAC– January 28, 2014 Jeff Billo, ERCOT 1.
Proposal for Consideration Regarding Holistic Solution to Congestion Irresolvable in SCED Issue:How do you identify when constraint is irresolvable Proposal:Adopt.
TPTF Update Trip Doggett TAC March 9, TPTF Update Meetings February 6 & 7, February 20 Attendance approximately 40 Completed review of ERCOT’s clarification.
Congestion Management Work Group 2008 Overview CMWG Marguerite Wagner, Reliant Energy Inc.
Texas Congestion Management Work Group Update For WMS Marguerite Wagner, PSEG Texas.
February 26, 2015 Technical Advisory Committee (TAC) Update to RMS Kathy Scott March 3, 2015 TAC Update to RMS 1.
RELIABILITY AND OPERATIONS SUBCOMMITTEE Report to TAC Austin, TX December 1, 2011 Kenneth A. Donohoo, P.E. Chairperson Oncor Electric Delivery Company.
Reliability Must Run Workshop RMR Study Process May 24, 2016.
Transmission Planning in ERCOT- Overview
Barrilla Junction Area Transmission Improvements Project
NPRR833 Workshop: Contingency Processing in CRR, DAM and SCED
Phase Angle Limitations
Modifications to Planning Charter
ISO New England System R&D Needs
Presentation transcript:

Chad Thompson, ERCOT Special ROS PGRR011 Workshop October 21 st, 2011 SCED Overview and Results

2 Presentation Outline Real-Time Congestion Management –Overview –What Contingencies/Constraints are Considered? Constraints Irresolvable by SCED –Actions Used to Maintain System Security –Constraints Consistently Irresolvable by SCED –Irresolvable by SCED vs. N-1 Insecure –Settlements Responses to ROS Comments Additional Questions

3 Real-Time Congestion Management Overview The Security Constrained Economic Dispatch (SCED) is simply one component of the process through which Generation Resources are dispatched based on current system conditions Other components of the process include: –SCADA Telemetry –State Estimator –Network Security Analysis (NSA) –Transmission Constraint Manager (TCM) –Resource Limit Calculator (RLC)

4 Real-Time Congestion Management Overview The NSA and the TCM both play a major role in real-time congestion management The NSA analyzes contingencies to monitor for potential system element exceedances The NSA then passes information to the TCM for constraints that may need some action by the Operator –For example, if a constraint is resolved by a RAP or SPS, that constraint will not be passed to the TCM Using the TCM interface, the Operator is able to select the constraints that will be sent to SCED for consideration during the next SCED execution –A constraint is defined by a contingency and an overloaded element

5 What Contingencies/Constraints are Considered? The following guidelines are used in determining which contingencies are considered in the real-time process: –ERCOT models all single transmission line, autotransformer, and generation unit contingencies This is performed using an automatic contingency generator application developed by the ERCOT Network Modeling Department and has been discussed with the Network Data Support Working Group (NDSWG) –Certain additional contingencies are defined manually in the CIM where the automatic contingency generator cannot be used Double-Circuits –Modeled based on information received by Transmission Owners (discussed in previous NDSWG meetings) Multi-unit contingencies such as whole combined-cycle trains Additional multi-unit contingencies are modeled pursuant to ERCOT and NERC requirements (e.g. double STP or Comanche Peak)

6 What Contingencies/Constraints are Considered? The SCED process is then executed to produce Resource-specific base point instruction and LMPs Only the transmission constraints that were activated in the TCM will considered by SCED There are three potential states for transmission constraints following a SCED execution The constraint can be: –Not binding –Binding –Violated For a violated constraint, the shadow price will be equal to the shadow price cap

7 Actions Used to Maintain System Security There may be cases in which the SCED process is not able to resolve a constraint Nodal Protocol (3) describes actions that ERCOT may take in real-time to relieve any issues Additional tools available to the ERCOT Operator include Mitigation Plans (MPs) and Temporary Outage Action Plans (TOAPs), in the event a contingency occurs in real-time –These can be implemented in concert with utilizing SCED to manage congestion –Constraints with generator shift factors greater than 2 % will still be activated in SCED ERCOT has been able to manage congestion, ensure grid reliability, and maintain compliance with applicable NERC Reliability Standards

8 Constraints Consistently Irresolvable by SCED The ERCOT Business Practices Document “Setting the Shadow Price Caps and Power Balance Penalties in Security Constrained Economic Dispatch” was presented to the Technical Advisory Committee (TAC) at its October 11 Special Meeting, and was recommended for approval by the Board of Directors Under Section 3.6.1, the shadow price cap for a non- competitive constraint will be modified once one of the following conditions is met: A.A non-competitive constraint violation is not resolved by the SCED dispatch or overridden for more than two consecutive hours on more than four consecutive Operating Days; or B.A non-competitive constraint violation is not resolved by the SCED dispatch for more than a total of 20 hours within a rolling thirty day period

9 Constraints Consistently Irresolvable by SCED After one of the trigger conditions is met, the shadow price cap for the constraint is calculated based on the Business Practices Document Based on the analysis provided at the October 11 TAC meeting, a list of seven potential constraints for which the shadow price cap may be modified was identified Unless modified per the Business Practices Document, the shadow price cap for a transmission constraint is set using one of the following generic values: –345 kV -- $4,500 –138 kV -- $3,500 –69 kV -- $2,800 –Base Case / Generic Constraints -- $5,000

10 Irresolvable by SCED vs. N-1 Insecure SCED Irresolvable refers to congestion which cannot be alleviated due to inability of SCED to dispatch Resources past a certain threshold (max shadow price) –Could be due to factors such as ramp rate limitations or economics of the capable resources N-1 Secure refers to the ability of the ERCOT ISO to withstand the loss of a credible single contingency without exceeding or violating System Operating Limits or Interconnection Reliability Operating Limits SCED Irresolvable is not typically the result of an N-1 insecure state –When ERCOT is N-1 insecure, it will issue a transmission watch

11 Settlements ERCOT is drafting material regarding settlements and will post an updated presentation when completed

12 Responses to ROS Comments Would changing SCED so that it only changes generator outputs after a contingency actually occurs rather than before a contingency occurs address most of the gaps between planning and operating processes? –This implies SCED only dispatches generation for power balance and base case (N-0) constraints, and might require additional Protocol changes to implement Economically, that would set the default max shadow price for all constraints to $5,000 since every constraint would be base case –Due to ramp rate limitations, SCED might not be able to redispatch generation post-contingency to resolve an overload As indicated earlier (slide 10), ramp rate restrictions could cause equipment damage as a result of SCED being unable to resolve an overload in time.

13 Responses to ROS Comments Would changing SCED so that it only changes generator outputs after a contingency actually occurs rather than before a contingency occurs address most of the gaps between planning and operating processes? –This change may impact compliance with NERC Reliability Standards ERCOT is required to respect System Operating Limits and Interconnection Reliability Operating Limits both pre- and post-contingency

14 Responses to ROS Comments How does ERCOT Operations respond to irresolvable SCED solutions? –The details of the actions taken by ERCOT grid operators to manage potential SCED irresolvable constraints can be found in Section 4.1 of the ERCOT Transmission and Security Desk Procedure –The Operations Support Staff may also work with affected Transmission Owners to develop a RAP, MP, PCAP, or TOAP to maintain grid reliability in the event the contingency occurs

15 Responses to ROS Comments Questions were also generally raised about the 1200 irresolvable SCED intervals that were presented –Proper context is needed –The data presented was approximately 1184 settlement intervals where the max shadow price was experienced –Multiple constraints at the max shadow price for the same settlement interval were counted twice –Comparing the number of settlement intervals where the max shadow price was experienced to the total number of binding settlement intervals: 1184 settlement intervals at max shadow price total binding intervals 1184 / = ~4.65 %

16 Responses to ROS Comments Questions were also generally raised about the 1200 irresolvable SCED intervals that were presented –ERCOT analyzed congestion Nodal-to-Date (10/5/11) pursuant to Section of the ERCOT Business Practices Document (Slide 8), and identified only 7 constraints meeting the criteria Constraint NameDescription SKEYWLV8_6611__CLoss of Willow Valley – Lamesa 138 kV overloads Ackerly Lyntegar – Sparenburg 69 kV SNCWHLT9_6915__AHolt Switch – Odessa North 69 kV overloads Odessa North – Odessa Basin Switch 69 kV DW_DDEN8_AIR_W_DE_1Denton Steam – Argyle / West Denton 138 kV overloads West Denton – Jim Christal 138 kV DODEQAL5_6611__AOdessa Switch – Quail Switch / Longshore Switch 345 kV overloads Ackerly Vealmoor Switch – Ackerly 69 kV SCABWES8_NAVAL__N_PADR1_1AEP Airline – AEP West Side 138 kV overloads Naval Base – North Padre 69 kV SNCWMOS8_ODNTH_FMR1Holt Switch – Moss Switch 138 kV overloads the Odessa North 138/69 kV Auto # 1 BASE CASE_VALIMPValley Import Voltage Stability Generic Transmission Limit

17 Responses to ROS Comments Details on the 7 Potential SCED Irresolvable Constraints –The Valley Import constraint is the only qualifying SCED Irresolvable constraint attributed to a base case System Operating Limit exceedance –Two constraints are based on double-circuit contingencies DW_DDEN8_AIR_W_DE_1 DODEQAL5_6611__A –Preliminary assessment of the constraints: Four are due to local congestion in West Texas for which there are few generators with significant shift factors to resolve the congestion One is due to local congestion in the DFW area around the time of the Cold Weather Event in February. One is due to a small load pocket near Corpus Christi One is the Valley Import Voltage Stability Limit

18 Responses to ROS Comments Details on the 7 Potential SCED Irresolvable Constraints –An MP was developed for the Valley Import –TOAPs were developed for the Odessa North Auto, West Denton – Jim Christal, and Ackerly Lyntegar – Sparenburg constraints Ackerly Lyntegar – Sparenburg TOAP would work for the Ackerly Vealmoor – Ackerly line, but a TOAP was never implemented for the constraint

19 Responses to ROS Comments Any additional information to support a gap? –The ERCOT Interconnection has not exhibited any grid-wide cascading outages as a result of a forced outage –ERCOT has experienced several operational events, but no grid damage has been observed outside the local areas affected by them The February 2, 2011 extreme weather event The contamination issues as a result from the recent draught and wildfires

20 Responses to ROS Comments Do NERC requirements prevent operating the transmission system such that generation adjustments are made after a contingency occurs rather than before? –The NERC Reliability Standards do not necessarily prevent operating the grid to move generation post-contingency, however ERCOT is required to respect its System Operating Limits and Interconnection Reliability Operating Limits both pre- and post-contingency –ERCOT is working on implementing a Dynamic Remedial Action Plan program within the Network Security Analysis which may allow for dispatching generation post-contingency through SCED

21 Additional Questions?