APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More Cindy Bogorad SPIEGEL & MCDIARMID 1333 New Hampshire Ave., NW Washington,

Slides:



Advertisements
Similar presentations
Federal & State Regulatory Issues Elizabeth W. Whittle Nixon Peabody LLP 401 9th Street, N.W. Washington, D.C (202)
Advertisements

Reliability in British Columbia
Reliability Provisions of EPAct of 2005 & FERC’s Final Rule
Wholesale Restructuring 1.PURPA 2.Market based wholesale rates 3.Incentive rates 4.Energy Policy Act of 1992 Clarified power to order third party wheeling.
EMIG Electricity Market Investment Group Presentation to the Ontario Energy Board February 17, 2004.
Federal Energy Regulatory Commission Update Janice Garrison Nicholas Chief Accountant and Director, Division of Financial Regulation Federal Energy Regulatory.
Transmission Independence and Investment Pricing Policy for Efficient Operation and Expansion of the Transmission Grid FERC Docket Nos. AD and.
Energy Storage Definitions/Definitions ETWG 18 Feb 2013.
FERC-Lite: Implementation Issues For Public Power Susan N. Kelly VP of Policy Analysis and General Counsel American Public Power Association APPA November.
TARIFF REGULATION IN THE NIGERIAN ELECTRICITY SUPPLY INDUSTRY
Transmission Joint Action in the Upper Midwest a presentation to the APPA Joint Action Workshop by David A. Berg, P.E. Principal December 7, 2004.
Regional Transmission Organizations: The Future of Transmission? Dave Edwards 4/17/2004.
1 Utility Oversight: Recent Changes in Law Call for Improved Vigilance by FERC NARUC Staff Subcommittee on Accounting and Finance 2008 Spring Meeting New.
Alternative Models of Electric Industry Restructuring
The Continuing Evolution of U.S. Electricity Markets
Overview of LMP Markets Features of ISOs / RTOs David Withrow Senior Market Economist Fall 2007 Meeting of the NARUC Staff Subcommittee on Accounting and.
Federal Energy Regulatory Commission Large Generator Interconnection Final Rule RM July 23, 2003.
AMERICAN PUBLIC POWER ASSOCIATION NATIONAL MEETING Salt Lake City June 15, 2009 Panel: “WHAT DOES IT TAKE TO GET TRANSMISSION BUILT?” Remarks of James.
RenewElec October 21, 2010 Robert Nordhaus, David Yaffe Van Ness Feldman 1050 Thomas Jefferson Street, NW Washington, DC (202) FERC’s.
Transmission Incentives P. Kumar Agarwal Acting Director, Division of Reliability & Engineering Services Federal Energy Regulatory Commission U.S. DOE,
Introduction to Bonneville Power Administration
By: Ed Flippen, Partner, McGuireWoods LLP, and Lecturer at the University of Virginia School of Law and Duke University School of Law US Electric Deregulation.
Utility Finance: A View from the Trenches Brad Jackson Foley & Lardner, LLP.
Vanus J. Priestley Philip R. O’Connor. Ph.D.
Entity Registration Under EPAct 2005 Public Power Council April 6, 2006 Louise McCarren Chief Executive Officer WECC.
“Transmission Siting and The Federal Landscape” Remarks of James J. Hoecker Husch Blackwell Sanders Former Chairman of the FERC Public Participation In.
ThinkEquity Summer Call Series “CAN WE DEAL WITH THE CHALLENGES TO GETTING TRANSMISSION BUILT?” Remarks of James J. Hoecker Husch Blackwell Sanders LLP.
1 View of Federal Energy Legislation Sonny Popowsky Pennsylvania Consumer Advocate September 16, 2004 Indiana Energy Conference PA Office of Consumer Advocate.
OATT Policy Overview 3/11/11 Ren Orans. Agenda History of the FERC pro forma Open Access Transmission Tariff (OATT) and its use in British Columbia Evolving.
NERC Data Collection & Coordination. Rules of Procedure: Section 1600 Overview  NERC’s authority to issue a mandatory data request in the U.S. is contained.
POWER SYSTEM PLANNING CHARTER AND PROCESSES Presentation to TAC 10/09/2003 KENNETH A. DONOHOO, P.E. Manager of System Planning Transmission Services
WINDPOWER 2003 Austin, TX May 18-21, 2003 Session 4A: Regulatory Issues Monday May 19, :40-5:00 pm Wind Generation Interconnection to Transmission.
FERC’s Role in Demand Response David Kathan ABA Teleconference December 14, 2005.
Title VII of the Dodd-Frank Act Regulation of Over-the-Counter Derivatives.
1 New Mexico State University Santa Fe Conference 2005 Steve Rodgers Office of Markets, Tariffs & Rates—South Federal Energy Regulatory Commission March.
OSC Meeting April 27, Transmission Cost Allocation Overview.
Overview of WECC and Regulatory Structure
Sec. 5 RE-REGULATION- EPAct 1992 FERC Orders 888 and 889 (1996) EPAct 2005 In short these three laws move the power industry towards an increase in competition.
Review of EPAct05 and Other Significant Legislative Developments Joe Nipper APPA Senior Vice President, Government Relations APPA Legal Seminar San Antonio,
1 The Costs of Participating in Restructured Wholesale Markets American Public Power Association February 5, 2007 William M. Bateman Robert C. Smith.
“FERC-LITE,” WHOLESALE REFUND AUTHORITY, AND RELATED PROVISIONS NOVEMBER 10, 2005 ROBERT R. NORDHAUS VAN NESS FELDMAN WASHINGTON, DC (202)
STREAM 1B: SECTOR STRUCTURAL AND RESTRUCTURING ISSUES CLLR C JOHNSON, SALGA NEC ELECTRICITY DISTRIBUTION MAINTENANCE SUMMIT 9 JUNE 2008.
Regulatory Institutions in Turkey. Regulatory Institutions Central Bank of Turkey Banking Supervision and Regulatory Institutions Capital Markets Board.
Impact of 2005 Energy Policy Act An Independent Power Provider View Louisiana State University Energy Summit 2005 October 20, 2005 Jeanne Connelly Senior.
Successful Restructuring: The Way Forward Mark Bennett Senior Manager of Policy Electric Power Supply Association Restructuring and the Wholesale Market.
S PIEGEL & M C D IARMID APPA EEI Contract Project Update APPA Legal Seminar Cambridge, Massachusetts October 10, 2006 Robert C. McDiarmid.
The Energy Policy Act of 2005 and Its Revisions to PURPA November 11, 2005 Grace D. Soderberg Assistant General Counsel National Association of Regulatory.
1 Market Evolution Program Long-Term Resource Adequacy Regulatory Affairs Standing Committee Meeting May 14, 2003.
Energy Policy Act of FERC gets more power -- The Federal Energy Regulatory Commission (FERC) will exercise jurisdiction over generation mergers,
Update on APPA’s FERC Advocacy Activities Susan N. Kelly Vice President, Policy Analysis and General Counsel 2006 APPA Legal Seminar October 2006.
Demand Response in Energy and Capacity Markets David Kathan FERC IRPS Conference May 12, 2006.
1 Benefits of Transmission Ownership Bob Johnston CEO of MEAG Power.
Designing Energy Solutions without Borders National Association of Regulatory Utility Commissioners National Association of Regulatory Utility Commissioners.
Federal Energy Regulatory Commission MISO/Alliance Companies’ RTO Status Reports Presented by: Joseph Power Tony Ingram Rahim Amerkhail Patrick Clarey.
Market Monitoring: The Role of OMOI and MMUs Presented to: Energy Markets at the Crossroads Springfield, Illinois December 12, 2002 By: Lisa L. Carter.
Office of Market Oversight & Investigations Comments by the speaker do not necessarily reflect those of the Commission Data Collection And Access At FERC.
Federal Energy Regulatory Commission Participation In Interstate Legal Processes Federal vs. State Authority August 10, 2005 Brazilia, Brazil.
THE FEDERAL ENERGY REGULATORY COMMISSION 2 AUTHORITY... the transmission of electric energy in interstate commerce and the sale of such energy at wholesale.
Presented to: “Ethics and Changing Energy Markets: Issues for Engineers, Managers and Regulators” University of Notre Dame October 28, 2004 “Energy Market.
Overview of Energy Policy Act of 2005 A Review of Implementation issues in New Hampshire.
Utility owned generator Federal Power Project Distribution System Residential users Commercial users Industrial users Municipal Utility Residential users.
DATA COLLECTION William McCarty Chairman Indiana Utility Regulatory Commission September 9-10 Riga, Latvia.
Enron Government Affairs Status Report to EWS 1 September 2001.
Electric Industry Overview: Municipal Electric Utilities Municipal Utilities are not-for-profit electric systems owned and operated by the people and.
UTC STUDY OF DISTRIBUTED GENERATION AND RECOMMENDATIONS Presentation for the Washington Future Energy Conference October 19, 2011.
European Union Law Week 10.
Regional Transmission Organizations
Transmission: the Critical Link
Wholesale Electricity Marketing & Trading Fundamentals
Developing the power sector in Federal Nepal Main lessons from international experience Kathmandu, November 06, 2018.
Presentation transcript:

APPA OVERVIEW OF EPACT 2005 Transmission Provisions, Merger Review, and More Cindy Bogorad SPIEGEL & MCDIARMID 1333 New Hampshire Ave., NW Washington, DC (202) November 10, 2005

S PIEGEL & M C D IARMD 2 Electricity Title  Most major overhaul of Federal Power Act and PUHCA since 1935  React to various problems— reliability, inadequate transmission, Enron scandals, regulatory gaps, QF machines

S PIEGEL & M C D IARMD 3 Recurring Themes  Transmission infrastructure  Tradeoffs for PUHCA repeal-enhanced merger review authority

S PIEGEL & M C D IARMD 4 Reliability (EPAct05 § 1211; FPA § 215)  Electric Reliability Organization to establish and enforce reliability standards with FERC oversight  Reliability standard “does not include any requirement to enlarge [bulk-power system] facilities or to construct new transmission capacity….”

S PIEGEL & M C D IARMD 5 Reliability (cont’d)  Compliance with standards should prod transmission construction  Recovery of prudently-incurred costs to comply covered in incentive rulemaking  Periodic reports on bulk-power system reliability and adequacy

S PIEGEL & M C D IARMD 6 Backstop Siting Authority (EPAct05 § 1221; FPA § 216)  DOE to designate National Interest Electric Transmission Corridors- constraints or congestion adversely affects consumers  FERC (or where regional siting compact, DOE) may issue permit with federal eminent domain where state delays/conditions/lacks authority

S PIEGEL & M C D IARMD 7 Backstop Siting Authority (cont’d)  Includes state inability to consider interstate benefits or failure to qualify requestor that does not serve end users  DOE lead agency for federal authorizations/environmental review  Expedition/reporting required

S PIEGEL & M C D IARMD 8 Third-Party Finance (EPAct05 § 1222)  WAPA/SWPA participation in National Interest Electric Transmission Corridor facilities under certain circumstances  Third party funding, capped at $100 million through 2015

S PIEGEL & M C D IARMD 9 Federal Utility RTO Participation (EPAct05 § 1232)  Permits TVA and PMAs to participate in RTOs  Through contracts with protections  Includes ensuring consistency with existing contracts, third- party financing arrangements, and statutory obligations

S PIEGEL & M C D IARMD 10 Transmission Infrastructure Rule (EPAct05 § 1241; FPA § 219)  Incentive/performance-based rates to benefit consumers by ensuring reliability/reducing delivered power cost by reducing congestion  Promote transmission investment “regardless of the ownership”  Technologies to increase capacity/efficiency  Return that attracts new investment

S PIEGEL & M C D IARMD 11 Transmission Infrastructure Rulemaking – RTO Participation  To the extent within jurisdiction, FERC to provide incentives to each transmitting utility and electric utility that joins an RTO/ISO  Ensure any costs recoverable under this subsection may be recovered through utility’s transmission rates or RTO/ISO rates

S PIEGEL & M C D IARMD 12 Transmission Infrastructure Rulemaking  Little in the way of specifics  All subject to just, reasonable and not unduly discriminatory standard  Flexibility to design rates that get needed transmission built at reasonable cost, e.g., by reducing risks and/or accessing new sources of capital

S PIEGEL & M C D IARMD 13 Participant Funding (EPAct05 § 1242)  Far less prescriptive than last bill  Permissive to FERC-may approve if just and reasonable, not unduly discriminatory and otherwise consistent with §§ 205/206  Consistent with existing law

S PIEGEL & M C D IARMD 14 Native Load Service Obligation (EPAct05 § 1233; FPA § 217)  Facilitate planning and expansion of transmission to meet reasonable needs of LSEs  Enable LSEs to secure firm transmission rights (or equivalent financial rights) on a long-term basis for long-term power supply arrangements

S PIEGEL & M C D IARMD 15 Native Load Service Obligation (planning/long-term rights)  Applies in RTO and non-RTO markets (except ERCOT)  Required rulemaking to implement within organized markets

S PIEGEL & M C D IARMD 16 Native Load Service Obligation (existing rights)  LSE is entitled to use existing firm rights or equivalent financial rights to meet service obligation  Preserves resource-to-load rights existing as of date of enactment  Whether through ownership, GFA, or OATT service agreement  Consistent with OATT

S PIEGEL & M C D IARMD 17 Native Load Service Obligation (existing rights)  Not just TO native load  LSEs include everyone in this room; not just those serving enduse load  Include joint action agencies— obligation under long term contracts to municipal utilities that serve endusers

S PIEGEL & M C D IARMD 18 Native Load Service Obligation (existing rights)  N/A to PJM, NYISO, ISO-NE, and CAISO (except certain CA rights protected against conversion)  Not directly applicable to MISO, but FERC must take policies into account when MISO changes FTR allocation methodology  Applies to SPP and other new RTOs  Separate added protections for PNW

S PIEGEL & M C D IARMD 19 PUHCA Repeal Tradeoffs  PUHCA, by active and passive restraints, largely restricted utilities to compact vertically integrated entities  PUHCA’s repeal will open up industry to consolidation and fragmentation in ways we can’t imagine

S PIEGEL & M C D IARMD 20 Tradeoffs - Mergers (EPAct05 § 1289; amending FPA § 203)  Expanded/clarified authority to review generation acquisitions and holding company mergers  But FERC must act within 180 days, plus 180-day extension period

S PIEGEL & M C D IARMD 21 Merger Review (cont’d)  Maintains traditional “consistent with the public interest” test  Added test: not result in cross- subsidization of non-utility or pledge/encumbrance of utility assets unless consistent with the public interest

S PIEGEL & M C D IARMD 22 Qualifying Facilities (EPAct05 § 1253; amending PURPA § 210)  Eliminate restrictions on QF ownership  No obligation to purchase from new QF unless meets new requirements  No mandatory purchase obligation for new contracts if QF has non-discriminatory access to RTO/ISO with competitive wholesale market, or comparable markets  Preservation of existing QF contracts

S PIEGEL & M C D IARMD 23 Odds and Ends  Eliminate 60-day wait for Section 206 refunds  Non-RUS-financed coops with less than 4 million MWh sales removed from FERC jurisdiction  Sense of Congress that FERC should consider state objections to LICAP

S PIEGEL & M C D IARMD 24 Bottom line  Many, many rulemakings  Expanded FERC regulatory and enforcement tools  Costs won’t go down  Life won’t get less complicated