CASS, Marsfield Phil Diamond 4 October 2011 SKA Pre-Construction Phase: Where we are, and what we’re trying to achieve ?
Outcomes from recent SKA Founding Board Met at LHR on 29 September FB appointments: Michiel van Haarlem (ASTRON) Exec Officer until legal entity est. Select Interim Director by 1 November Proceed with appointment of D-G, but will not appoint until after site decision Site Selection Advisory Cmte: Evaluation plan approved Legal Entity: Incorporation by mid-November 2011 Members, at minimum: UK, NL, IT, AU, NZ, RSA, CA, China Resourcing: Committed cash for SPO < required (16.6MEuro vs. 27.5MEuro) Enough for Year 1 plan Work on basis others will join and funding will ramp up Business Plan group draft a revised plan to reflect expected growth in membership
Outcomes from recent SKA Founding Board SPO Building: To be located at Jodrell Bank Planning application to be submitted on 14 Oct Contractor appointed by 31 Jan 2012
CSIRO: PEP PEP Overview Work PackageDescription 1Management (€16.8m) 2Science (€1.3m) 3System Design (€2.3m) 4Maintenance and Support (€0.3m) 5Dish Arrays (€15.3m) 6Aperture Arrays (€22.7m) 7Signal Transport & Networks (€3.7m) 8Central Signal Processing (€11.9m) 9Software & Computing (€11.3m) 10Power (€2.8m) 11Site engineering and site office (€2.5m)
Stage 1 engineering work in the Pre- Construction Phase SPDO FB meeting, 29 September 2011
Context for Pre-Construction Phase PEP Stage 1 PEP Stage 2
Stage 1: System and Element Work in Technical Requirements Stage 2 Detailed Work Breakdown Structure Stage 1 Element Work Finish CoDRs SR R System level Stage 1 Stage 2 Work Package definition and contracting Planning Element SRR Science Requirements Planning RFP Bid Contract Element level Stage 1 Apr12 Q4/ SPDO/SPO WPCs
Conceptual Design Reviews in 2011 Feb System delta-CoDR on SKA 1 Apr Signal Processing Apr Aperture Arrays Jun Signal Transport & Networks July Dish and Dish Arrays 2-3 Feb CoDR Dish Verification Antenna #1 5-7 Oct PDR Dish Verification Antenna #1 9-11 Nov Monitor & Control Dec Software & Computing
Allocation of Requirements from System to Element level Pre-Stage 1 Apr/12 System RR Element SRR Q4/12 (resource dependent) 1st allocation is science requirements, operations requirements (Instrument Requirements Review). Later allocations are extensibility requirements and non-functional requirements. System Level (SPDO/SPO) Element Level (WPCs) 1 2
WPC Element Work in Analysis of CoDRs Element SRR Planning CoDR => SRR Work (See next slide) Allocated Requirements Stage 1 Pre-Stage 1 Verificatio n Work Element Requirements, WBS Development and Design studies
Assembling Element Level RFPs for Stage 1 Work SoWs Pre-Stage 1 Planning Element 1 CoDR-SRR Work Planning Element 2 CoDR-SRR Work Planning Element N CoDR-SRR Work RFPsBid Define Top-level WBS Develop Stage 1 Legal, Bid Policy, T&C Contract Templates Stage 1 Element Contracts Nov/11 Apr/12 Assemble Work Package Contractor Consortia
Pre-Stage 1 : Planning Element CoDR-SRR Work Purpose of Work o Planning next phase – to Element SRR What needs to be done? Which options are to be carried forward? How much effort? How much time? What is the outcome to be presented at the SRR? o Preparation of Statement of Work to reach SRR. Contract Phases and Milestones o Familiarisation with tasks and inputs o Analysis of input data, identify gaps o 1 st draft plan o Presentation and review o Decisions on how to handle gaps and missing information o Finalize plan o Final presentation, review and delivery. Deliverables o Reports Scope of requirements analysis for the element level. Consolidation and recommendation of viable technical options Architecture documents for viable options. Outline of work to be done on requirements, and other items identified in the SEMP for the SRR level. Identification of resources and time to complete actual work to SRR. Preliminary estimate of work needed to complete detailed design. Review of gaps or missing information needed to proceed. o Prepared Statement of Work for the period up to SRR.
Assembling Element Level RFPs for Stage 1 Work SoWs Pre-Stage 1 Planning Element 1 CoDR-SRR Work Planning Element 2 CoDR-SRR Work Planning Element N CoDR-SRR Work RFPsBid Define Top-level WBS Develop Stage 1 Legal, Bid Policy, T&C Contract Templates Stage 1 Element Contracts Nov/11 Apr/12 Assemble Work Package Contractor Consortia
Assembling Element Level RFPs for Stage 1 Work SoWs Pre-Stage 1 Planning Element 1 CoDR-SRR Work Planning Element 2 CoDR-SRR Work Planning Element N CoDR-SRR Work RFPsBid Define Top-level WBS Develop Stage 1 Legal, Bid Policy, T&C Contract Templates Stage 1 Element Contracts Nov/11 Apr/12 Assemble Work Package Contractor Consortia
Resources for Planning, Requirements Development, WBS, Stage 1 work Pre-Stage 1 Planning (Nov11-Apr12) Assuming 5-8 Elements 3 people/element from PrepSKA Lead Institutes => persons for 5 months ( PMs) SPDO/SPO Domain specialists at 30% (5 persons) (8 PMs) System Requirements Development (Nov11-Oct12) SPO Domain specialists at 30% (5 people) (20 PMs) Three additional System Engineers at SPO, assumed available immediately (36 PMs) SPDO/SPO will need TBD assistance with specific tasks during the SRR preparation Element level Requirements Development (Apr12-Mar13, PEP Table 2) WPC s: 15 FTE/ WP on average (total: 90 FTEs)
Where are we, and what are we trying to achieve? Still at planning stages SPDO/SPO plan for process is solidifying Method of interaction with SPDO/SPO not yet established Key triggers: Appointment of Interim Director Possibly allows formation of consortia Site decision: Releases funding D-G appointed We establish a model for Australian participation We talk to international partners about the formation of potential consortia We be ready to go as soon as possible.
Contact Us Phone: or Web: Thank you CSIRO Astronomy and Space Science Philip Diamond Chief Phone: Web: