PMG, June 15, 2000 Slide 1 Schedule Started ! Done Late Done Done(today)
PMG, June 15, 2000 Slide 2 Sensor Delivery p Axial detectors (3-chip): All sensors in hand p 90 o detectors, DSDM (6-chip): ~60 sensors to be delivered; current delivery 5/wk production paced by sensor delivery Micron delivery just in time, and remains worrisome »Fallback: Accept sensors which have one p-stop fault (noise region channels). 15 such sensors have been identified »Need to act soon on lower grade devices p 2 o detectors (9-chip) Still to deliver (lyr2), (lyr4) sensors, which includes sensor to be returned after cleaning 226 sensors being processed at Micron (with yield of 53%), of which 94 have 4 month processing remaining Taking processing into account, will need to purchase ~10 lower grade devices »Fallback: Accept sensors which have higher R bias, ~50 sensors have been identified p F-Wedge sensors Micron: All 125 sensors received Eurisys: Order of 65 sensors complete Enough sensors on hand to build full complement of F disks But, breakdown Voltage V at V depl =15-20 V for most One more batch processed with improved implantation. Received 9 sensors of last batch. Quality indeed better. Requested delivery of all sensors of this batch (~20) in exchange for lower quality sensors received.
PMG, June 15, 2000 Slide 3 Sensor Delivery p H Wedges additional 42 sensors needed which will arrive soon. ()() ()()
PMG, June 15, 2000 Slide 4 High Density Interconnect Status p 3-chip hdi’s done p 6-chip hdi’s All hdi’s in hand 40 to be stuffed at Promex p 9-chip hdi’s Last 46 hdi’s (short tail) on order; delivery next week 40 hdi’s at Promex for stuffing, 46 to go p F-wedge hdi’s All hdi’s in hand ~35 to go for stuffing at Promex p H-wedge hdi’s All hdi’s in hand 75 to go for stuffing at Silitronics
PMG, June 15, 2000 Slide 5 Ladder and Wedge Production p Axial detectors (3-chip): Ladder production has started again at rate 1/day No problems foreseen p 2 o detectors (9-chip): Production lagging due to availability of hdi’s »Reorder hdi’s »Problems with surface mounting components (Promex); e.g. problems with 27 hdi’s of one type (short tails) Production slowly proceeding p 90 o detectors (6-chip): Paced by Micron delivery, 107 sensors built so far p F Wedges (14-chip): Production proceeding at adequate pace Sensor and hdi availability not a problem Recently received most Eurisys detectors with low V depl Testing sensors is cumbersome p H Wedges (6-chip): 180 half wedges produced to date Half wedge production proceeding adequately Glued 39 full wedges of which ~21 detector grade Encapsulation and full wedge production is slow but not limiting process
PMG, June 15, 2000 Slide 6 Production Status and Projection p Projected rates: assumed yieldcapacity 9-chip: 9.0/week 80% 15/wk 6-chip: 5.4/week 85% 10/wk H-wedge: 6.2 week 85% 10/wk F-wedge: 4.3/week 90% 15/wk Nov 1, 00 Aug 10, 00 today 50% line
PMG, June 15, 2000 Slide 7 Production Status for first half cylinder p Last dates for detector production keeping original schedule with completion August 1: F Wedges: June 26, 2000 6/9-chip ladders: June 12, 2000 p 4 flavors of 9-chip ladders; current status: “short tails” Delay of ~ 3 weeks with respect to schedule
PMG, June 15, 2000 Slide 8 Production Rate
PMG, June 15, 2000 Slide 9 Barrel / Disk Assembly p First barrel (barrel 6) completed May 18 p Grounding problems observed in first barrel, coherent noise barrel will be moved to address these problems p Second barrel (barrel 5) completed June 13 p Work on third barrel started p Third F disk encountered set back remeasurement of alignment showed discrepancies of ~100 m Probably due to mislabeling of files OGP measurements performed today and disk should be completed today. p Next F disks, one of end disk assemblies, being prepared p Wedge production proceeding adequately for future assembly p H-disk still awaiting ORC sign-off for electrical tests
PMG, June 15, 2000 Slide 10 Silicon Support p Silicon Support Cylinder Fabrication of support at z=o Adding fiducials to end rings Finished installing H disk kinematic mounts Finished installation of adapter ring Add reinforcements to cylinder feedthroughs …... June 26 move CFT to DAB