“we believe the reason why the first bunch is more intense than the following 3 is that it's on that one that the SPS RF loops are locked” Philippe & Django.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
LHC progress Saturday 2 nd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
LHC progress Thursday 30 th April 2015 Coordination: Mike Lamont, Wolfgang Hofle.
LHC 14 & 15 April :22: Ramp to 6.5 TeV lost due to MUFO, resulting in quench 10:30: Access during cryo recovery 16:00: Pre-cycle 17:05: RB.A78 short.
Monday 4 th to Friday 8 th Technical stop  Coordination: Katy Foraz  Machine back to Operations Friday evening on schedule Major cryogenics intervention.
1 MKBH Erratic Jan Uythoven On behalf of the ABT team (Viliam, Nicolas M., Etienne, Laurent, Francesco etc…..) MPP meeting 8/5/2015.
Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
Friday 23 rd November - morning Coming out of loss maps over night Thu – Fri  in shadow of MKD problem in SPS (and CMS cryo recovery) 07:35 Start pre-cycle.
LHC 30 th and 31 st July :10 Finish scrubbing fill 25 ns trains by operator dump. –No XPOC data … 08:40 Inject for another scrubbing fill 09:09.
V. Kain, G.H. Hemelsoet AB/OP1Nov 08, 2007 LHC Injection System V.Kain, G.H. Hemelsoet, AB/OP Input from: E. Carlier, B. Goddard, J. Wenninger What do.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
LHC Status Sat Morning 18-June Bernhard Holzer, Gianluigi Arduini et al Tentative Planning: Luminosity 1092 x 1092 Access: installing low pass filter at.
R.Giachino / M.Albert Be/op 12 th March 2012 LHC Machine check out 1v1.
Friday March 4 th LHC morning report the short story: from a global point of view we had basically only one access !!!
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
LHC Status Mo Morning 20-June Bernhard Holzer, Gianluigi Arduini et al 7 runs The Week.
Friday morning Dump fill due to the trip of the RQF.A78  intervention had been just planned for the morning on the circuit Access, interventions:  RQF.A56/78,
Status of ABT beam tests preparation 9-Oct-14. Preparation of sector test without beam I MKI: – Open valves, conditioning to 55 kV, softstart – Check.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
Wednesday ● 02h04: Stable beams # b x 121b. – Peak luminosity 1.2e25 cm-2 s-1 ● 08h32: Beams dumped on request. – Length=6h28. Rampdown.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
08h15: Injection.  Correction injection oscillations.  Transfer line steering.  Losses at 30% of dump threshold, limited by SPS scraping. 12h35: Start.
Last night Lhc closed 15:00 Beam on Ti 8 /Ti2 Prepulse check synchronisation ok with LHCb /RF 17:00 Open Point 4 PC’s and RF 19:00 LBDS energy tracking.
From yesterday LHC status Wednesday 26 th Welcome Verena back on shift 07:08 Access in PM85 for piquet EPC (O.Fournier).  Fuse on RD2.R8 circuit.
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
Tuesday 26 th April – morning shift 08:00 Great news, cryo is back! Unluckily it was followed by many other problems, one after the other one. So, spent.
– Machine closed. Ramp for powering tests & pre-cycle – Pilots through nominal cycle up to collisions. Measure chroma during squeeze. Check dump of pilots.
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
Injection issues overnight 10:50 Access  QPS & EPC  Vacuum leak SPS – magnet to be replaced Monday – cycling for FT and LHC only over the weekend 12:15.
Another typical LHC day. 06:15 Fill 2000 dumped 08:44 Stable beams – fill 2001  1.675e14  1.21e11  ~2 microns normalized emittance 11:34 Beams dump.
Saturday 14:10 Cryogenics back [26 hours 40 minutes] Pre-cycle 15:30 Beam 2 in  Interlock on TCLIB.6R2.B1. Alessandro Masi found a broken sensor, it would.
Thursday 27 th October 00:57 fill 2257 dumped during squeeze (RQTF.A67B1) 03:52 stable beams fill #2258 4:33 Dumped, problem of LBDS dilution kicker power.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
Tuesday 3 rd October STABLE BEAMS until 12:25 when we switched to ADJUST for a EOF test for Tobias  dump B2 first and then B1.  Dump at EOF test because.
LHC Beam Commissioning Meeting V. Kain & R. Alemany
DRY RUNS 2015 Status and program of the Dry Runs in 2015
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Wednesday 21 March 2012.
Thursday 25/11/10 & Night Work on: 16:15 Inject fill #1520
Tuesday Fill lost #1855 at 7:28 due to the trip of RQX.R1. This was traced to a software bug in the FGC… The Class 51 (LHC_PC) FGC software has been upgraded.
A/N 26 16:00 Access finished problem with the BLM test. one crate is failing the beam permit test. Fixed. Access required in sector 78 for QPS to fix a.
Monday 11/07: Recovery Plenty of accesses.
Saturday 30th June - Sunday: Rocky !
Tue :25 Beams dumped due to RF vacuum interlock
LHC Morning Meeting - G. Arduini
Saturday 12:00 Fill 1992 in stable beams.
Thursday morning – optics correction
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Yesterday Issue of injection kicker not pulsing:
Wednesday 31 October: Morning
Dry Run 0 Week 13: BI test of...everything circulating beam: all fixed displays and BI applications OP directories for 2009, concentrators running Need.
Bernhard Holzer, Joerg Wenninger
Thursday 10th May - morning
Monday February 28th 8h00: Injection
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
Not the most productive 24 hours on record
Friday Morning 7:30 injection for fill 2908
Aims for the week Recover from technical stop and precycle at 10A/s
Monday 14:00 beam dump Access:
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
LHC Morning Meeting - G. Arduini
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Saturday Wire scans at end of fill 1253 B1H : 4.2 B1V : 4.3 B2H : 5 B2V : 7.2 Beams dumped (after ~14h of collisions) Some issues during refill.
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
Thursday
Wednesday 26 October 2011.
Presentation transcript:

“we believe the reason why the first bunch is more intense than the following 3 is that it's on that one that the SPS RF loops are locked” Philippe & Django Etienne explained to Jan that the LBDS is reading the energy at three different levels:  The MKD/MKB generators get the energy directly from the BETS – this was fine for the dump this morning.  The IPOC for the MKD and MKB get the energy from the SMP distributed over the timing system - – this was fine for the dump this morning.  The XPOC gets the energy over CMW – this was not ok for the dump yesterday morning. As the BLMs also get the energy over the SMP / timing system; there should have been no problem with the BLM thresholds yesterday morning. From yesterday 1

07h08: RCBXH1.R2 fixed. Board bypassed. Problems during access:  lights on  ODH alarm, fire brigade in,  patrol dropped by fire brigade (wrong MAD key)  problem in 81, PP60A (earth fault in a 18 Kv cell  PC problem),  lights off  ODH alarm again 16h35: Access finished. Recover and pre-cycle Thursday 11 th November 2

18h17: Ready for injection. 18h23: No beam from injectors: LEIR/PS problem. The beam is not extracted. LHC had mastership. 21:00 Beam presence flag problem  BEAM PRESENCE FLAG gives FALSE, there is 9 10^9 in B1 though  rebooted cfv-ua47-bctfra and after we had to reboot the proxy, and then it worked again. 21:30 Timing missing  The MHz LHC bunch-crossing clock and kHz orbit signals presumably, plus BI prepulses and 400 MHz  Alarm on BST crate – CCC  Andy “there was a flash” Butterworth diagnoses problem - VME power supply – replaced very efficiently by CO piquet.  cfv-ccr-allfo1 Thursday evening 3

20h08: Injection  pretty ratty, long, big beams, unequal bunch intensities  intermittent problem in LEIR Note: - we OP disable one BPM in 9L3 B1V because guess the reading is wrong. - we asked Verena to unmask injection oscillation in the IQC as data came back when the RF clock was published again 23:50 Start ramp 00:53 Stable beams 68 on 69 Thursday evening 4

1488 5

New collimator fixed display 6

Lifetime in stable beams 7

beams lost : trip of RQD.A23 trip of sector 67 when loading the ramp-down start BP. In the hands of MP3 (Mike & Knud) This morning 8

RF voltage modulation during injection  Philippe & Delphine 1 – 2 hours Tidy up injection  check injection oscillations  LEIR Try for a cleaner 69 on 69 Today 9