Hall D Online Meeting 27 June 2008 Fast Electronics R. Chris Cuevas Jefferson Lab Experimental Nuclear Physics Division 12 GeV Trigger System Status Update.

Slides:



Advertisements
Similar presentations
Trigger & DAQ Ole Hansen SBS Collaboration Meeting 19 March 2010.
Advertisements

GlueX Collaboration Meeting June 3-5, GeV Trigger Electronics R. Chris Cuevas 1.Hardware Status  Production Updates 2.DAq and Trigger Testing 
Level-1 Trigger Commissioning H.Dong, A.Somov Jefferson Lab Trigger Workshop, Jul 8, 2010.
GlueX Collaboration Meeting October 2-4, 2014 Trigger System Update R. Chris Cuevas Trigger Hardware/Firmware Status  Hardware Status  Performance Test.
Integrated Tests of a High Speed VXS Switch Card and 250 MSPS Flash ADC Hai Dong, Chris Cuevas, Doug Curry, Ed Jastrzembski, Fernando Barbosa, Jeff Wilson,
CHL -2 Level 1 Trigger System Fully Pipelined Custom ElectronicsDigitization Drift Chamber Pre-amp The GlueX experiment will utilize fully pipelined front.
GlueX Collaboration Meeting May 12-14, GeV Trigger Electronics R. Chris Cuevas Trigger Hardware/Firmware Status  Global Trigger  Installation.
Level-1 Topology Processor for Phase 0/1 - Hardware Studies and Plans - Uli Schäfer Johannes Gutenberg-Universität Mainz Uli Schäfer 1.
Target Controller Electronics Upgrade Status P. Smith J. Leaver.
1.Status update from May 2011  FADC250 and Trigger modules  Two crate testing success 2.Schedule  How about those requirements?  What’s happened since.
GlueX Collaboration Oct '06 C. Cuevas 1 Topics: Projects and Progress 250Msps Flash ADC Energy Sum Module The Bigger Picture DAQ/Electronics Work Plans.
Global Trigger H. Bergauer, K. Kastner, S. Kostner, A. Nentchev, B. Neuherz, N. Neumeister, M. Padrta, P. Porth, H. Rohringer, H. Sakulin, J. Strauss,
Status and planning of the CMX Philippe Laurens for the MSU group Level-1 Calorimeter Trigger General Meeting, CERN May 24, 2012.
 Brief status update of DAQ/Trigger production hardware  Firmware development for HPS application  CLAS12 CTP ‘upgrade’ notes  Summary Status of the.
DAQ Status & Plans GlueX Collaboration Meeting – Feb 21-23, 2013 Jefferson Lab Bryan Moffit/David Abbott.
TID and TS J. William Gu Data Acquisition 1.Trigger distribution scheme 2.TID development 3.TID in test setup 4.TS development.
Prototype of the Global Trigger Processor GlueX Collaboration 22 May 2012 Scott Kaneta Fast Electronics Group.
GlueX Collaboration Meeting February , GeV Trigger Electronics R. Chris Cuevas Hardware Status ( A top down view,, )  Global Trigger Processing.
Hall A DAQ status and upgrade plans Alexandre Camsonne Hall A Jefferson Laboratory Hall A collaboration meeting June 10 th 2011.
TRIGGER-LESS AND RECONFIGURABLE DATA ACQUISITION SYSTEM FOR POSITRON EMISSION TOMOGRAPHY Grzegorz Korcyl 2013.
GlueX Collaboration Meeting February , GeV Trigger Electronics R. Chris Cuevas 1.Hardware Design Status Updates  Production News  Status.
DAQ Status Report GlueX Collaboration – Jan , 2009 – Jefferson Lab David Abbott (In lieu of Graham) GlueX Collaboration Meeting - Jan Jefferson.
Atlas L1Calo CMX Card CMX is upgrade of CMM with higher capacity 1)Inputs from JEM or CPM modules – 40 → 160Mbps (400 signals) 2)Crate CMX to System CMX.
AIDA FEE64 development report August 2010 Progress after Texas CAD work Manufacturing 25th August
SBS meeting VETROC application for Cerenkov triggering Alexandre Camsonne March 18 th 2015.
SBS meeting VETROC application for Cerenkov triggering Alexandre Camsonne March 18 th 2015.
GlueX Collaboration Meeting 12GeV Trigger Electronics October 4 - 6, 2012 R. Chris Cuevas 1.Hardware Design Status Updates  Production News  Acceptance.
DAQ MICO Report Online Monitoring: –Status All histograms are now implemented Still not fully online –Only monitoring from data file (slightly offline,
06/07/041 F1TDC Status Update Hall D Collaboration Meeting Indiana University – Bloomington, IN May 20-22, 2004 Fernando J. Barbosa
Yuri Velikzhanin NuTel TV meeting, June 13 (Friday), 2003 Status of electronics for NuTel prototype.
Update on the HBD Craig Woody BNL DC Meeting June 8, 2005.
Hall D Online Meeting 28 March 2008 Fast Electronics R. Chris Cuevas Group Leader Jefferson Lab Experimental Nuclear Physics Division System Engineering.
CPT Week, April 2001Darin Acosta1 Status of the Next Generation CSC Track-Finder D.Acosta University of Florida.
Hardware proposal for the L2  trigger system detailed description of the architecture mechanical considerations components consideration electro-magnetic.
Comments from Physics Division Rolf Ent Associate Director for Experimental Nuclear Physics SOLID collaboration meeting, February 03, 2012 Thomas Jefferson.
CMX status and plans Yuri Ermoline for the MSU group Level-1 Calorimeter Trigger Joint Meeting CERN, October 2012,
Trigger Interface and Distribution J. William Gu Jefferson Lab 1. What is TID 2. TID Structure and functions 3. Possible usage in the system 4. TID related.
Status and planning of the CMX Wojtek Fedorko for the MSU group TDAQ Week, CERN April , 2012.
David Abbott - Jefferson Lab DAQ group Data Acquisition Development at JLAB.
Status of NA62 straw electronics Webs Covers Services Readout.
GlueX Collaboration Meeting 12GeV Trigger Electronics 10 May 2010 R. Chris Cuevas 1.FY10 Project Goals  Update from January 2010 Collaboration Meeting.
12GeV Trigger Workshop Christopher Newport University 8 July 2009 R. Chris Cuevas Welcome! Workshop goals: 1.Review  Trigger requirements  Present hardware.
MOLLER DAQ Aug 2015 meeting Team : R. Michaels, P. M. King, M. Gericke, K. Kumar R. Michaels, MOLLER Meeting, Aug, 2015.
Hall D Online Meeting 9 August 2007 Fast Electronics R. Chris Cuevas Group Leader Jefferson Lab Experimental Nuclear Physics Division Mission Who’s Who.
Orsay’s proposition for the L2  trigger system detailed description of the architecture distribution of the work costs schedule firmware Bernard Lavigne,
Electronics for HPS Proposal September 20, 2010 S. Boyarinov 1 HPS DAQ Overview Sergey Boyarinov JLAB June 17, 2014.
DAQ Status & Plans GlueX Collaboration Meeting – Feb 21-23, 2013 Jefferson Lab Bryan Moffit/David Abbott.
AFP Trigger DAQ and DCS Krzysztof Korcyl Institute of Nuclear Physics - Cracow on behalf of TDAQ and DCS subsystems.
HPS TDAQ Review Sergey Boyarinov, Ben Raydo JLAB June 18, 2014.
GTP Update 3 March Cuevas. CPUPP17PP15PP13PP11PP09PP07PP05PP03PP01SWASWBPP02PP04PP06PP08PP10PP12PP14PP16PP18 64x***SSP GTPA GTPB SSP TI DP1LVPECL.
ATLAS SCT/Pixel TIM FDR/PRR28 June 2004 TIM Requirements - John Lane1 ATLAS SCT/Pixel TIM FDR/PRR 28 June 2004 Physics & Astronomy HEP Electronics John.
Level-1 Trigger Commissioning Status A.Somov Jefferson Lab Collaboration Meeting, May 10, 2010.
Hall–D Level-1 Trigger Commissioning Part II A.Somov, H.Dong Jefferson Lab 12 GeV Trigger Workshop, July 8, 2010  Play Back Test Vector in Hall-D commissioning.
Electronics Workshop GlueX Collaboration Meeting 28 March 2007 Fast Electronics R. Chris Cuevas Group Leader Jefferson Lab Physics Division Topics: Review.
GlueX Collaboration May05 C. Cuevas 1 Topics: Infrastructure Update New Developments EECAD & Modeling Tools Flash ADC VXS – Crates GlueX Electronics Workshop.
Rutherford Appleton Laboratory September 1999Fifth Workshop on Electronics for LHC Presented by S. Quinton.
Electronics Status New DCM daughter card works. –Three cards has been assembled. –One daughter card has been send to Jamie yesterday by FedEx overnight.
1 DCS Meeting, CERN (vydio), Jun 25th 2013, A. Cotta Ramusino for INFN and Dip. Fisica FE Preliminary DCS technical specifications (v1.0) for the Gigatracker.
DAQ ELECTRONICS 18 March 2015MEG Collaboration Meeting, Tokyo Stefan Ritt.
DAQ Selection Discussion DAQ Subgroup Phone Conference Christopher Crawford
Super BigBite DAQ & Trigger Jens-Ole Hansen Hall A Collaboration Meeting 16 December 2009.
DAQ and Trigger for HPS run Sergey Boyarinov JLAB July 11, Requirements and available test results 2. DAQ status 3. Trigger system status and upgrades.
ECAL electronics schedule JFMAMJJASONDJFMAM Prototype 2 boards Design Layout Fabrication and assembly Testing, including VFE prototype tests Production.
LKr status R. Fantechi.
CMS EMU TRIGGER ELECTRONICS
GlueX Electronics Review Jefferson Lab July 23-24, 2003
JLAB Front-end and Trigger Electronics
Fernando J. Barbosa F1TDC Status Update Hall D Collaboration Meeting Indiana University – Bloomington, IN May 20-22, 2004 Fernando J.
LCLS Cavity BPM Electronics Undulator Week January 22, 2008
Report on ATF2 Third Project Meeting ATF2 Magnet Movers ATF2 Q-BPM Electronics Is SLAC ILC Instrumentation Group a good name?
Presentation transcript:

Hall D Online Meeting 27 June 2008 Fast Electronics R. Chris Cuevas Jefferson Lab Experimental Nuclear Physics Division 12 GeV Trigger System Status Update -- New module design progress -- Updates to System drawings -- Testing activities

Project Status 15 weeks until the end of FY08 Identified FY09 PED activities are defined for the ‘Test Stand’: FADC250 – -- Nine modules fully assembled and all required modifications have been added -- 8 channel 12 bit version delivered to IU. -- Test crate and CPU that is on loan to G. Vissar at IUCF has been moved to IU -- LabView test routines have been completed to fully test each FADC The LabView test programs will provide a nice platform for troubleshooting and repair -- CODA driver has been completed and is in use for testing with the Trigger Interface -- Development to download firmware through VME has started (Hai) Trigger Interface – -- 4 modules fully assembled and functional -- Successful synchronization of trigger and latency adjustment for 150m and 50m fiber -- Plans underway to test multiple FADC250 modules in two VXS crates - Trigger rate performance testing for FADC250 - Does FADC250 pipeline trigger readout meet specifications? - Data throughput testing -- Test stand software – Ben has created very useful routines to configure and display readout data.

Signal Distribution module – -- Functional specifications completed for May Review -- Schematics are behind ‘schedule’ - New circuits to regulate power to the module - FPGA has been selected -- Must begin component placement and routing by July Crate Trigger Processor – -- Functional specification has been completed for May Review -- Schematics are complete -- Significant progress with placement of components and routing of circuit board -- CNU Student working with Hai on interface firmware for CTP to TI communication SubSystem Processor – Global Trigger Processor – Trigger Supervisor – -- Functional specification document completed for May Review -- Design activities scheduled for FY09 Project Status

CTP Circuit Board Place & Route 2 Gigabit ‘Lanes’ from each FADC250

More updates,, Detailed System Drawings – -- Started converting the logical drawings to detailed rack drawings - Include ALL equipment ‘chassis’ - Drawings for each platform have been started -- Work closely with Mechanical Engineering to identify best cable routing method for each sub-system (platform) Tagger Area: Instrumentation Racks Crates and other equipment chassis shown. Need to add details to show AC mains panel assignments & Network hardware.

Testing updates,, Many tests are planned for multiple FADC250 boards in a crate Must test token passing scheme, and measure any noise and jitter effects with up to 8 FADC in a crate. Two crate trigger latency tests have been performed, and we have the fiber optic patch panels that will be used in the final installation. The test stand is a very good platform to simulate the final configuration in the Hall and to measure total system effects on clock jitter and other critical timing parameters Data display and GUIs to configure the test station have been developed by Ben.