PULICHINTALA PROJECT NSP Reservoir Barrage Halia Musi Paleru Munneru Non Over Flow Left Dam (442.60M) Barrage Spillway 754.90M) Halia Musi Paleru Munneru Wyra Kattaleru Pulichintala Project NOF Reservoir Spillway Non Over Flow Right Dam (91.50M) NOF 115 km 85 km FRL: +53.34m Gross Cap: 45.75 TMC Head works under progress Live Cap: 36.23 TMC
SCHEMATIC DIAGRAM OF PULICHINTALA PROJECT Spillway : 755.90 M Left NOF : 422.60 M Right NOF : 91.50 M Gross Storage : 45.75 TMC Live Storage : 36.23 TMC MFD : 20,36,000C/s. No. of Gates : 33Nos. River Training wall POWER HOUSE RIVER SLUICES Dam Axis Length–1289 Mts. Spill Way – 755.90 M River Bed Portion 400 Mts NOF 91.50 L/S NOF – 441.60 M CH 875M CH 1275M 2116.60 M River
PULICHINTALA PROJECT 1 Project Profile: Construction of Pulichintala Project (Balancing Reservoir) across river Krishna near Pulichintala (V), Guntur District. 85 Kms. U/S of Prakasam Barrage. 2 Administrative Sanction : G. O. Ms. No. 171, I & CAD, Dt: 30-10-2003 for Rs. 565.87 Crores G.O.Ms.No.208, I&CAD, Dt.18-11-2005, for Rs.681.604 Crs. 3 No. of EPC Packages 1 No 4 Agreement value of 1 package Rs.268.87 Crs. 5 Budget provision for 2006-07 Rs.190.00 Crs. 6 Expenditure of the project 2004 – 05 Rs. 66.82 Crs. (works Rs.2.26 Crs., LA=Rs.0.7 Crs., Estt. Rs.43.66 Crs., Misc. Rs.20.20 Crs.) 2005 – 06 Rs. 172.31 Crs. (works Rs.2.20 Crs., LA=Rs.79.08 Crs., Forest Rs.58.54 Crs., Mob. Adv. Rs.26.42 Crs.) Cum. Exp. Rs. 239.13 Crs 7 Ayacut Stabilisation(Krishna Delta) 13.08 lakh acres 8 Land Acquisition Required 21310 acres Acquired 82 acres
Submergence of Villages 9 Forest Land : 2859.441 acres. Forest clearance accorded from MOEF in Lr.No.F/8-7/05-Fc Div., New Delhi, dt.18-7-05. An amount of Rs. 109.21 Crs is to be deposited with forest authorities PCCF, Hyd. Rs.58.54 Crs. deposited to forest department. 10 Estimate cost of LA Rs.230.62 Crs. 11 Estimate cost of R & R Rs.139.72 Crs. 12 Submergence of Villages 13 Mob. Advance (Rs. in Crores) Paid Recovered 2005-06 : 26.42 -
PULICHINTALA PROJECT Pkg.No. 12 : Construction of Pulichintala Project (Balancing Reservoir, Head works & its Components works) Name of the Contractor : M/s. Srinivasa Const CR-18G-JV Agreement Amount : Rs. 268.87 Crs. Agreement Date : 30-09-2004 Period of completion : 30 months (10 milestones) Target date of completion : 3/2007 Investigation : Completed Designs (Earth dam, NOF dam and spillway) : approved 3 Nos. against 5 Nos. Power house : with CE, CDO Gates : to be submitted by the agency Execution : In progress Qty. of earth work done : 1,18,000 cum against 25,98,000 cum No. of Machinery : 29 Nos. Expenditure : 2004-2005 - Rs. 66.82 Crs. 2005-2006 - Rs. 172.31 Crs. Cum. Inc. Mob. Adv. only - Rs. 239.13 Crs Land Acquisition : Required 21310.23 Acres, Acquired 78.825 Acres