Project Phases Review Questions
1. In which phase are the specifications produced? a. Construction Design Phase- Schematic Design Phase- Construction Documents Planning Phase
1. In which phase are the specifications produced? a. Construction Design Phase- Schematic Design Phase- Construction Documents Planning Phase
2. Whose responsibility is it to produce the shop drawings? The Architect/Engineer The Contractor The Owner The Sub-Contractor
2. Whose responsibility is it to produce the shop drawings? The Architect/Engineer The Contractor The Owner The Sub-Contractor
Design Phase- Schematic Design Phase- Construction Documents Phase 3. Which phase fixes and describes the size and character of the entire project? Design Phase- Schematic Design Phase- Construction Documents Phase Bidding/Contract Negotiation Phase Design Phase – Design Development Phase
Design Phase- Schematic Design Phase- Construction Documents Phase 3. Which phase fixes and describes the size and character of the entire project? Design Phase- Schematic Design Phase- Construction Documents Phase Bidding/Contract Negotiation Phase Design Phase – Design Development Phase
4. The Construction Phase begins… When the first clod of earth is moved by a bulldozer When the surveyor measures the site When the bids are received When the agreement is executed
4. The Construction Phase begins… When the first clod of earth is moved by a bulldozer When the surveyor measures the site When the bids are received When the agreement is executed
5. What activities take place in the planning/pre-design phase? The engineers develop the mechanical and electrical systems The site is selected and the demolition is done Feasibility studies and budget is set The program is evaluated and the engineers are selected
5. What activities take place in the planning/pre-design phase? The engineers develop the mechanical and electrical systems The site is selected and the demolition is done Feasibility studies and budget is set The program is evaluated and the engineers are selected
Bidding/Contract Negotiation Construction Post Construction 6. During which project phase does the A/E review the owner’s program and budget requirements and suggest alternative approaches? Planning/Pre-Design Design Bidding/Contract Negotiation Construction Post Construction
Bidding/Contract Negotiation Construction Post Construction 6. During which project phase does the A/E review the owner’s program and budget requirements and suggest alternative approaches? Planning/Pre-Design Design Bidding/Contract Negotiation Construction Post Construction
7. During the Planning/Pre-Design Phase, the A/E may be retained to: Develop outline specifications Describe the character of the mechanical system Prepare renderings Assist in financial feasibility studies
7. During the Planning/Pre-Design Phase, the A/E may be retained to: Develop outline specifications Describe the character of the mechanical system Prepare renderings Assist in financial feasibility studies
8. A project’s “life cycle” includes all of the following EXCEPT: Planning Financing Construction Evaluation Demolition
8. A project’s “life cycle” includes all of the following EXCEPT: Planning Financing Construction Evaluation Demolition
9. The Design Phase includes all of the following EXCEPT: Surveys Design Development Schematic Design Bid Security
9. The Design Phase includes all of the following EXCEPT: Construction Document Phase Design Development Phase Schematic Design Phase Bid Security
Outline Specification Rough Draft Specification UniFormat Elements 10. The specification type document prepared during the Design Development phase is called the: Outline Specification Rough Draft Specification UniFormat Elements
Outline Specification Rough Draft Specification UniFormat Elements 10. The specification type document prepared during the Design Development phase is called the: Outline Specification Rough Draft Specification UniFormat Elements
Answers C B D A