 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.

Slides:



Advertisements
Similar presentations
Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting
Advertisements

CERN IT Department CH-1211 Genève 23 Switzerland t Mobile services: Sunrise SWAP Rodrigo Sierra IT/CS.
Proton Source Workshop Booster Downtime Wednesday, December 8, 2010 T. Sullivan.
CERN TS Department / Civil Engineering Group 8 February 2008 Civil Engineering Layouts & Tunnel Cross Section 1 CLIC/ILC Collaboration Meeting 8 Feb 2008.
Intervention Priority Management This talk will show the CERN priority list, the corresponding check list and the tools used by operators to diagnose a.
CURRENT STATUS OF CV INSTALLATIONS, WORKS DURING LS1 AND PROBLEMS ENCOUNTERED DURING START-UP NORTH AREA Bill Bannister / Jani Lehtinen EATM – 7 th October.
Fibres & copper Cabling activities LIU meeting 27/09/2013 F Duval 27/09/2013 F Duval Cabling acxtivities LIU 1.
The new MEF Group S. Baird 12 th December The new MEF Group Mandate for the MEF Group MEF structure Support for LHC experiments Formal meetings/committees.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
IEFC Workshop 2011 David Mcfarlane Superintendent for SPS EN/MEF/ABA 1.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
LHC Hardware Commissioning Review May 2005 T.Pettersson - EDMS: TS Department Utilities Safety Access SU - a plea for co-ordination of co-activities.
TS Department / Civil Engineering Group 17 October 2007 Civil Engineering Layouts & Tunnel Cross Section 1 CLIC workshop – Working group: Two beam hardware.
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013.
LHC Access System August 2006 LHC Access System – Status and Planning August 2006 Elena Manola-Poggioli Eva Sanchez-Corral TS-CSE on behalf of the LHC.
LS1 Injectors K. Foraz on behalf of N. Gilbert, S. Mataguez, D. Hay & D. McFarlane LSC 24 th May /05/2013LSC – EN-MEF-OSS1.
LS1 : EL Upgrades & Consolidation Chamonix– February 8 th 2012 F. Duval on behalf of EN/EL The goal of LS1 is to implement everything needed for a safe.
Claudio Bortolin. 1 st June: PT100 electrical connection failure (Temp Chiller water In&Out) 1) it required an access to the cavern to be fixed 2) access.
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
Technical Support Activities in PH-ADO-PO
ECRs and ES for the LHC Last presentation on the 26 th of August 2015 (LMC 232) S. Chemli for EN-MEF-DC LMC xxx.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
EN-CV interventions during YETS
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix January 2010.
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
Cooling & Ventilation feed-back M. Nonis – EN/CV.
LHC-YETS Coordination meeting #9 24 th November, 2015.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
12th February 2010David Mcfarlane EN-MEF-ABA1. History of Booster The accelerator was built in The Proton Synchrotron Booster is the first, in the.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
On behalf on EN-EL October 1 st, 2015 YETS Works EN-EL [ CF excluded ]
Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
Survey activities during LS1 Dominique Missiaen On behalf of the SU section.
SPS YETS 2015/2016 Planning meeting for BE-BI 09/12/15 David Mcfarlane EN-MEF D.Mcfarlane1.
Planning of Injector Activities for Linac4-to-PSB Connection and LS2 Thanks to all the valuable input from the LIU project leaders and LIU work- package.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 17 th December 2013.
ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts AB / RF GROUP MTTR, SPARE PARTS AND STAND-BY POLICY FOR RF EQUIPMENTS C. Rossi on behalf of.
Injectors & LHC report K. Foraz on behalf of OSS members 01/08/2013LSC - K. Foraz1.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
TE-CRG Activities D. Delikaris, TE-CRG.
Activities related to BE-BI during LHC-YETS 7 th December, 2015 Maria Barberan, Marzia Bernardini.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 15 th August 2012.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
Managing the survey activities during the Long Shut-down 1 Dominique Missiaen D. Missiaen, Iwaa14, October 2014, IHEP, Beijing, China1.
PIP Shutdown Status 9/17/2014. RIL/Linac Jobs L1 Transformer ◦Rigging complete ◦Electrical work started ◦Turn on this coming weekend Laser notcher flange.
CV works in the non- LHC accelerator complex during 2008 and plans for 2009 ATOP days 2009.
PS - SPS Day 18-Jan-2006 PS Ring by Ray Brown.. 2.
ELENA installation progress F. Butin / ELENA collaboration.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
Update on the PSB Cooling and Ventilation Systems
YETS & LS2 Works EN-EL / Power distribution
SPS LS1 Planning meeting (N019) 04/09/13
SPS Winter stop Planning meeting (N06) 05/01/2011
EYETS David Hay EN-OSS.
Installations, modifications, consolidation in 2005:
PS Booster Hardware Tests & Cold Check-out planning 16th of March 2017
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS EN-CV Planning LS (initial draft)
High Radiation to Materials 16th Project Team Meeting – May 20, 2010
SPS Planning for the EYETS Meeting 8 (07/12/2016)
SPS Planning for the EYETS Meeting 9 (14/12/2016)
YETS & LS2 Works EN-EL / Power distribution
PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
Experimental Areas – LS2 planning
Presentation transcript:

 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention periods  Closing remarks David MCFARLANE (EN_MEF_INJ)1

 1988 to 1999  SHELL UK: Senior Operations and Instrument technician.  3 year apprenticeship in Aberdeen, Scotland.  8 years working 2 week shift on gas platforms in the southern sector of the North Sea. David MCFARLANE (EN_MEF_INJ)2

3

4

 Designed and supervised the installation of the Gas Distribution Systems for the 4 main LHC experiments. (ATLAS, CMS, ALICE & LHCb)  100s of individual small diameter stainless steel pipes.  over 60km of piping  over 40 primary gas storage panels David MCFARLANE (EN_MEF_INJ)5

6 ATLAS Gas Distribution System

David MCFARLANE (EN_MEF_INJ)7 Flammable Gas Room Flammable Gas Racks Gas Pipes

 Oversaw the installation of the RADmons throughout the LHC  20 Gateways  307 Monitors David MCFARLANE (EN_MEF_INJ)8 Areas covered Shown in red

David MCFARLANE (EN_MEF_INJ)9 Point 7 - UJ76 Point 8 R – Q1 UJ88 – end of TI8

 Technical Coordinator for the:  PS Booster  LEIR  AD machine. David MCFARLANE (EN_MEF_INJ)10

The SPS Technical Coordination Team  David MCFARLANE  SPS Technical coordinator  Responsible for coordinating all works in the SPS during T.S and Shutdowns.  Franck Baïs  TSO of the SPS  Technical Support David MCFARLANE (EN_MEF_INJ)11

 Official interpretation  Supervise and coordinate the work of technical specialists  My interpretation  Ensure that as much work is done safely, in the short time available.  Ensure that no conflicting works are done at the same time  Anticipate potential problems and solve them before they occur.  Maintain good communication with all equipment specialists. David MCFARLANE (EN_MEF_INJ)12

 6.9km of accelerator tunnel.  2.5km of transfer tunnels.  7 main access points.  Over 20 surface buildings.  10 pits and 15 lifts.  Access to the underground areas is only possible for very short periods of time. David MCFARLANE (EN_MEF_INJ)13

 Unplanned Stops of the SPS  Planned short technical stops  Planned Shutdowns David MCFARLANE (EN_MEF_INJ)14 The machine remains under the control of Operations and any works carried out during these times is coordinated by them.

David MCFARLANE (EN_MEF_INJ)15

 Request have to be made via the new IMPACT tool.  The technical coordinator will then create a planning for the technical stop.  This planning is then presented to the FOM for approval.  Once the work has been approved by the FOM, the technical coordinator will then approve the IMPACT requests.  A couple of days before the technical stop, the technical coordinator will meet with RP and go through the planning to ensure there are no problems regarding radiation. Where necessary, scheduling will be altered and arrangements made for teams to be accompanied by RP in specific areas.  RP give final approval on ALL IMPACTS David MCFARLANE (EN_MEF_INJ)16

 I liaise with Operations in the CCC and oversee all accesses into the SPS.  Ensure that the planning is respected.  Solve any issues that occur as soon as possible  Frank Bais is my eyes and ears on the ground.  Checking people are doing what they say they are doing  Keeping me up to date with progress of the works  Ensuring that all works are being done safely.  ….  Once all works are completed, I inform Operations that the technical stop is finished and they can start procedures to re-start the machine. David MCFARLANE (EN_MEF_INJ)17

 Winter stops.  2010/11 winter stop: Duration - 11 weeks.  2011/12 winter stop: Duration - 13 weeks. Only enough time for the bare minimum of maintenance.  Long Shutdowns.  LS1: Duration – 20 months Possible to do larger works and campaigns David MCFARLANE (EN_MEF_INJ)18

 Although the technical stop lasted 11 weeks (from the 6 th December 2010 until 21 st February, ) general access for works was only possible for 4 weeks  Works coordinated between multiple departments & groups: (EN/BE/TE/GS/DGS)  334 separate jobs requested.  17 required VICs (Visite d'Inspection Commune - Joint Inspection)  Changed 8 magnets  Replaced 2 kickers in BA4,  Replaced 2 Septa magnets in BA6,  Multiple cabling campaigns,  upgrades to the UA9 experiment located in BA5,  Installation works on the SPS collimators.  Measurement of the SPS quads in the Vertical plane and realignment where necessary.  Complete maintenance of the cooling water systems and compressed air systems  Maintenance of all SPS lifts  Lighting campaign around all of the SPS  HIRADMAT related works in BA6 and BA7 David MCFARLANE (EN_MEF_INJ)19 Magnet tests Xmas break General access EPC tests Start-up 1 week2 weeks4 weeks2 weeks

David MCFARLANE (EN_MEF_INJ)20 How do I juggle all these jobs?How do I make all the pieces fit?

David MCFARLANE (EN_MEF_INJ)21 Teams directly involved: Magnets, CV, Vacuum, transport, Survey. Teams indirectly involved: EL, Lift maintenance, any team working in the area.

David MCFARLANE (EN_MEF_INJ)22

David MCFARLANE (EN_MEF_INJ)23

David MCFARLANE (EN_MEF_INJ) separate lines

 IMPACT  Microsoft Project  Planning meeting  9 meetings for 2010/11 shutdown  9 meetings for 2011/12 meetings  Specific task meetings  Magnet change campaigns  CV works  Cable campaigns  Etc. David MCFARLANE (EN_MEF_INJ)25

 Beam off to Beam on: Duration is 20 months.  11 th February 2013 until 15 th October 2014  General access: Duration is 15 months.  25 th March 2013 until 27 th June David MCFARLANE (EN_MEF_INJ)26

 Majors works include:  Large cable campaigns at each point  Replacement of irradiated cables at BA1 and TCC2  Installation of Fibre optics at multiple points  Re-alignment of the entire SPS  18kV transformer consolidation,  Draining of the SPS cooling water ring main and replacing main valves.  Magnet replacement campaign  Installation of up to 16 new coated magnets in BA5  Replacement of Kicker tanks.  Vacuum consolidation works  Modification of sectorization.  SPS Dampers RF Power plant maintenance and upgrade  Replacement of Septas  ……. David MCFARLANE (EN_MEF_INJ) 27

 Planning is constantly evolving  A planning schedule is only complete the day after the machine is closed.  LS2 is already being mentioned!!! David MCFARLANE (EN_MEF_INJ)28 Thank you for your attention.