Nuclear Decommissioning in the UK Presented by Chris Jones.

Slides:



Advertisements
Similar presentations
Building pride in Cumbria Do not use fonts other than Arial for your presentations NuLeAF Steering Group 24 October 2012 Nuclear site waste management.
Advertisements

Prepare Strategic Business Cases for NDA Consolidate nuclear materials at Sellafield –Work underway with Sellafield Ltd. –Developing final business case.
Site Director, Trawsfynydd Nuclear Site Dave Wilson Date: 22 June 2011.
NuLeAF Opportunities for Storage Consolidation of Higher Activity Wastes 4 th November 2011.
Overview of Environment Agency Decommissioning and Clean up programme – delivering Nuclear site restoration Peter Orr, decommissioning and clean up programme.
1 KRB-A (Grundremmingen, Germany). 2 Type:Boiling Water Reactor Power: 250 MW(e) Started in 1966, shut down in 1977 First commercial power reactor in.
Civil decommissioning market – an update Presented by Ron Gorham Head of Supply Chain Development and Commercial Relationships.
Research and Development in the NDA The UK National Cleanup Programme Neil Smart Nuclear Research Coordinator, NDA.
1 Status of DOE Cleanup in Idaho Presentation to the “LINE Commission” By Rick Provencher Manager, DOE Idaho Operations Office April 7, 2012 Idaho Falls,
1 Best Practices for Risk-Informed Remedy Selection, Closure, and Post-closure Control for DOE’s Contaminated Sites October 30, 2013.
Challenges in LLW Management: a Local Government Perspective Fred Barker, Executive Director, NuLeAF SAFESPUR FORUM 29 April 2009.
Remediation - A Time for Learning - A Time for Action presented by Mark Bassett, Sellafield Programme Director on behalf of Mike Weightman, Chief inspector.
Decommissioning of Nuclear Power Plants Case Study: Dounreay Nuclear Facility Case Study: Dounreay Nuclear Facility Samuel Chapman Heriot-Watt University.
Dounreay Nuclear and Chemical Land Contamination.
UK Nuclear Policy Andrew Beirne
MODULE “PROJECT MANAGEMENT AND CONTROL” EMERGENCY PLANNING SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP , Programme “Leonardo.
School for drafting regulations Nuclear Safety Decommissioning Vienna, 2-7 December 2012 Tea Bilic Zabric.
CH/1 © Dr. Christian Hicks and Dr Tom McGovern An analysis of the impact of the restructuring of the UK civil nuclear industry on tier 1 and tier 2 suppliers.
The Cons of Nuclear Reactors By Michelle Trojanowsky.
The UK Nuclear Market. Paul Lester CEO Lord Mandelson Secretary of State for Business, Innovation and Skills.
Nuclear Energy Targets: Explain how the nuclear fuel cycle relates to the true cost of nuclear energy and the disposal of nuclear waste. Describe the issues.
TRP Chapter Chapter 4.2 Waste minimisation.
Safety of Nuclear Power Reactors Final Presentation ESL Fall 2006 Anatoliy Borodin.
Decommissioning Nuclear Reactors. Background Before a company decides to close it’s power reactors the facility must be put in to a state that no longer.
Decommissioning Nuclear Reactors. Background Before a company decides to close it’s power reactors the facility must be put in to a state that it no longer.
MODULE “STRATEGY DEVELOPMENT”
NRC Decommissioning Activities for the San Onofre Nuclear Generating Station Bruce A. Watson, CHP Chief, Reactor Decommissioning Branch Division of Decommissioning,
Spent Nuclear Fuel Timothy Pairitz. Nuclear Power 101 Uranium-235 is enriched from 0.7% to 3-5%. Enriched fuel is converted to a uranium oxide powder.
UK Cleanup Market Overview A Strategic approach to Cleanup & Hazard Reduction Nov 2010 Marcus Mackay mercury stone.
World Nuclear Association 38th Annual Symposium September 2013, Central Hall Westminster, London Nuclear Operation and Radioactive Waste Management.
Magnox Swarf Storage Silos Programme Decommissioning Delivery Partnership Requirements February 2014 Gavin Askew.
Authorization and Inspection of Cyclotron Facilities Authorization for the Decommissioning of the Facility.
NuLeAF presentation Magnox ILW strategy 14 th May 2015 May 14th
Nuclear Energy and Nuclear Waste The Good, The Bad, and the Ugly…
Group New Projects Related to Decommissioning. 29 th May 2008 KNPP Richard Benbow – Head of Kozloduy PMU.
VERMONT YANKEE Transitioning into SAFSTOR ​SEPTEMBER 2, 2015 Paul Paradis Director Decommissioning.
1 SAFEGROUNDS SAFety and Environmental Guidance for the Remediation of UK Nuclear and Defence Sites.
BY SEAN ZDEB AND JORDAN CHANG Nuclear Energy Reborn: The Pro’s, Con’s and Rebirth of a World-Changing Fuel.
AP Environmental Nuclear Energy. NUCLEAR ENERGY When isotopes of uranium and plutonium undergo controlled nuclear fission, the resulting heat produces.
MODULE “COST ESTIMATION, CALCULATION AND COST CONTROL” SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP , Programme “Leonardo da.
First Generation Magnox Storage Pond (FGMSP) Programme Partner Requirements February 2014 Steve Topping.
Clean-up of former nuclear sites and the role of the Planning regime Jim Cochrane.
MODULE “PROJECT MANAGEMENT AND CONTROL” SAFETY ASSESSMENT DURING DECOMMISSIONING SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP ,
Howard Cooper Head of Quality, Sellafield Ltd The Sellafield Excellence Journey Date: 2 nd November 2011.
Integrated Used Nuclear Fuel Management Regulatory Information Conference U.S. Nuclear Regulatory Commission March 11, 2009 Steven P. Kraft Senior Director.
MODULE “PREPARING AND MANAGEMENT OF DOCUMENTATION” SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP , Programme “Leonardo da Vinci”
Robert Fookes Although separate applications must be made for the generating station and the grid upgrade. Government believes that both applications.
Nuclear Energy and Waste By: David Long ( ); Chris Marcyniuk ( ); Adam Foster ( ) IMS3 Sustainability.
Nuclear Waste Disposal By: Tierra Simmons. Nuclear Waste Disposal Controversy Nuclear energy provides enough efficient sources of energy than all fossil.
1 ESTABLISHMENT OF REQUIREMENTS Module “DECOMMISSIONING PROCESS” Project BG/04/B/F/PP , Program “Leonardo da Vinci”
Just Do It Now – E Problems 1.Given that the electricity for home use is five cents per kilowatt- hour, how much would it cost to operate five fluorescent.
Phil Reeve Decommissioning Head of Strategy and Technical Sellafield Ltd – Key to Britain’s Energy Future 9 April 2014.
Training for Decommissioning Author – Andy Dietzold – UKAEA Presenter – David Reay - UKAEA.
Liquid Fluoride Thorium Reactors. Overview Introduction to nuclear reactors Fundamentals of LFTR (Liquid Fluoride Thorium Reactors) Economic viability.
Calder Hall Sellafield Decommissioning Martin Adam Heriot-Watt Edinburgh 2008.
 Before a company decides to close it’s power reactors the facility must be put in to a state that no longer has a residual radioactive level, clean.
Introduction Radioactive waste in Iraq arises mainly from decommissioning of destroyed nuclear facilities and waste related to previous nuclear research.
New-Build Nuclear – A Review of Labour Market Research NESG July 16, 2009 Una Borte –Market Analyst.
Vermont Yankee. Boiling Water Reactor Reactor Building Carbon steel 370 Ci/m3 Concrete 3.8 Ci/m3 Spent fuel pool.
Spent Fuel Management and Nuclear Materials (SFM&NM) July 2016 Update
PhD Bursary Scheme Rick Short, Research Manager 1
Preliminary Decommissioning Plan for the Canadian Light Source
guardian. co
Janet R. Schlueter Senior Director, Radiation and Materials Safety
NDA Draft Strategy.
مستلزمات بناء المحطات النووية ضو مصباح الهيئة العربية للطاقة الذرية
NDA Draft Strategy.
Possible Transition from Operating to Decommissioning
Tom McGovern and Chris Hicks Newcastle University Business School
Anni Podimata, Vice President ITRE
Presentation transcript:

Nuclear Decommissioning in the UK Presented by Chris Jones

Introduction Britain has 23 working reactors Reactors decommissioned/ out of use 21 Generating almost 20% of nations electricity First reactor in 1956 Peak production 1997 – 26% Since then it has declined as stations are closed 6 more to closed by 2015 Although it is thought due to the ‘energy gap’, the lifespan of some stations will be increased beyond 2015 Energy gap caused by closing of coal stations and the need for consumer power

What is it Usually when it is seen as uneconomical. The plant is taken apart and hazardous waste removed. The site is left safe in visually acceptable state. Each project is undertaken on its own merits. The process is similar to decommissioning in the chemical industry. Decommissioning is when a nuclear power station is shut down.

Decommissioning Run by the Nuclear Decommissioning Authority (NDA), which was formed in April 2005 Its purpose is to deliver savings in the decommissioning and clean-up of the UK’s nuclear sites in a safe and cost-effective manner accelerate programmes of work that reduce hazard introducing innovation and world class contractor expertise Done through competitions as first done in American has strategic responsibility for the UK's nuclear legacy

Their Strategic Priorities Encourage the highest standards in safety, security and environmental management; Drive hazard reduction; Secure our funding framework; Gain the support and confidence of our stakeholders Develop integrated waste solutions; Maximise commercial value; Build an effective industry; and Create a world class organisation

Decommissioning It includes all clean-up of radioactivity and progressive demolition of the plant. Once a facility is decommissioned, there should no longer be any danger of a radioactive accident or to any persons visiting it. There are 3 methods of decommissioning Immediate Dismantling Safe Enclosure Entombment

Three Methods Immediate Dismantling: allows for the facility to be removed from regulatory control soon after termination of regulated activities. Usually, the final dismantling or decontamination activities begin within a few months or years. Afterwards the site is available for re-use. Safe Enclosure: This option postpones the final removal of controls for a longer period, around 40 to 60 years. The facility is placed into a safe storage configuration until the eventual dismantling and decontamination activities occur. Entombment: This option entails placing the facility into a condition that will allow the remaining on-site radioactive material to remain on-site without ever removing it totally. This option usually involves reducing the size of the area where the radioactive material is located and then encasing the facility in a long-lived structure such as concrete, that will last for a period of time to ensure the remaining radioactivity is no longer of concern.

3 Stages of Dismantling Initial Decommissioning Reactor are defuelled and fuel is moved away from reactor. All none fixed components are removed For non-reactor facilities, all radioactive sources and equipment are removed The structure is maintained intact and the atmosphere inside the buildings are controlled

Decontamination and Dismantling Contaminated equipment is dismantled in carefully planned steps. This involves decontamination to minimise the amount of radioactive waste generated Once a building is stripped of all its internal equipment, it is carefully surveyed to determine the extent of contamination in the building fabric. Simple processes of washing and removing a thin layer of concrete from a structure (scabbling) are generally fine to decontaminate the building 3 Stages of Dismantling

Demolition Once all radioactive and hazardous material has been removed the building is refurbished for alternative uses or demolished Demolition is carried out with stringent controls to monitor possible presence of radioactivity The land is then remediated and returned to a condition where there is no hazard. 3 Stages of Dismantling

Sites The NDA took ownership of the sites involved, but the operational work itself is carried out by contractors These various sites are being restructured into seven Site licence Companies. The 11 Magnox sites are grouped together in a north south divide. Magnox North Ltd - Chapelcross; Hunterston A; Trawsfynydd; Wylfa and Oldbury Magnox South Ltd - Berkeley; Bradwell; Dungeness A; Hinkley Point A and Sizewell A

The rest have more localised site licences. Sellafield Ltd - Calder Hall; Windscale and Capenhurst uranium enrichment plant Dounreay Site Restoration Ltd Research Sites Restoration Ltd - Harwell and Winfrith facilities LLW Repository Ltd - low level waste repository near Drigg Springfields Fuels Ltd Sites

Timescale Due to the latent radioactivity in the reactor core, the decommissioning of a reactor is a slow process which has to take place in stages; The plans of the Nuclear Decommissioning Authority for decommissioning reactors have an average 50 year time frame

Costs NDA estimate decommissioning will cost about £72 billion (about €90 or 2.3 trillion CZK) over a 100 year period. Sellafield taking up £31.5 billion. New estimates are increasing every Year. Greenpeace say it will over £10bn

Berkeley Most sites are passed the stage of defuelling and are in the process of decommissioning and termination. The first site to start decommissioning in the UK was at Berkeley nuclear power station which wasclosed for economic reasons in 1989 after 27 years of operation, defuelling took 3 years. The cooling ponds were then drained, cleaned and filled in and the turbine hall was dismantled and demolished. The reactor buildings are in the final stages of preparation for an extended period of care and maintenance in the Safestore phase. Ultimately they too will be dismantled (approx. 2080), leaving the site to be leveled and landscaped. The same pattern is being followed at other UK reactor sites.

Site Restoration Restoring the site involves lots of projects working together. The end point of decommissioning depends on the potential of the site. Ideally the site will be available for unrestricted use New business premises at Harwell Restored greenfield site at Winfrith