2015 Shutdown Joe Compton 3/11/2015
RIL PIP Work Install operational laser notcher 5 days Dave Johnson & Todd Johnson
RIL Non PIP Work Source B fiber optic upgrade Install if problems with Source A are remedied RFQ rotation Not sure if this work will be done on this shutdown
Linac Work No PIP work for this shutdown Regular Linac maintenance will be performed Pulse transformer oil samples and quality control baseline Plan under development
Booster PIP Work Finish remaining turbo stations Ben, Jason, Justin Finish replacing remaining sector valves Ben, Jason, Justin Upgrade anode power supplies with new PS EE Support Replace east gallery house transformer EE Support
Booster PIP Work Continued Perform rack work for RF station 20 EE Support, Electricians Outfit RF stations 21 & 22 in tunnel Trades personnel Continue cavity refurbishment Ben, Jason, Justin RF personnel Alignment Continue bias supply refurbishment EE support RF personnel
Booster LCW Work Multiple LCW jobs Cavity LCW valves Install drain hoses Install flow meters, pressure gauges, resistivity & temperature sensors Add taps upstairs for BRF21 & 22 (modulator, BS, Driver) Replace RF station hosing with flexible stainless steel hose Install bypass strainers Booster LCW will need to be drained and refilled Repair leaks & other preventive maintenance
LCW Schedule
Other Booster Work Several cavities pulled out for LCW valve replacement Kicker & chopper maintenance General maintenance