LBDS Audit Follow-up Jan Uythoven Thanks to: Etienne Carlier and Brennan Goddard 1.

Slides:



Advertisements
Similar presentations
Jan Uythoven, AB/BTLHCCWG, 3 May 2006 Page GeV Commissioning Machine Protection Needs to be commissioned to: Prevent damage with the used, higher.
Advertisements

André Augustinus 15 March 2003 DCS Workshop Safety Interlocks.
EECE499 Computers and Nuclear Energy Electrical and Computer Eng Howard University Dr. Charles Kim Fall 2013 Webpage:
1 Commissioning ABT Equipment in the LHC Jan Uythoven ABT TCM 13/01/2015.
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
LHC UPS Systems and Configurations: Changes during the LS1 V. Chareyre / EN-EL LHC Beam Operation Committee 11 February 2014 EDMS No /02/2014.
LHC Beam Dumping system
1 MKBH Erratic Jan Uythoven On behalf of the ABT team (Viliam, Nicolas M., Etienne, Laurent, Francesco etc…..) MPP meeting 8/5/2015.
Failure mode impact studies and LV system commissioning tests
Vegard Joa Moseng BI - BL Student meeting Reliability analysis summary for the BLEDP.
Alessandro Cappelletti for CTF3 collaboration 5 th May 2010 RESULTS OF BEAM BASED RF POWER PRODUCTION IN CTF3.
Technical review on UPS power distribution of the LHC Beam Dumping System (LBDS) Anastasia PATSOULI TE-ABT-EC Proposals for LBDS Powering Improvement 1.
LBDS Kicker Electronic and Slow Control Etienne CARLIER AB/BT/EC.
LHC Beam Screen Heaters: System overview, consolidation needs and project planning 4 February TE-CRG/JCC (Beam Screen Heater Review) 1.
LHC Beam Dump System Technical Audit Trigger Synchronisation Unit.
LHC ARC Commissioning report during LS1 Agenda: VRGPE documentation (former VRJGE) Active Penning modification By-Pass Valves modification LHC ARC commissioning.
Drive beam magnets powering strategy Serge Pittet, Daniel Siemaszko CERN, Electronic Power Converter Group (TE-EPC) OUTLINE : Suggestion of.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
1 LBDS Testing Before Operation Jan Uythoven (AB/BT) Based on the work of many people in the KSL, EC and TL sections.
LBDS Power Triggering Etienne CARLIER & Jean-Louis BRETIN AB/BT/EC.
Operational tools Laurette Ponce BE-OP 1. 2 Powering tests and Safety 23 July 2009  After the 19 th September, a re-enforcement of access control during.
1N.Voumard, AB/BT/ECLBDS Audit, CERN 2008 Presentation of the Beam Energy Tracking System Definition : The Beam Energy Tracking System (BETS) monitors.
Beam Loss Monitor System – Preliminary Feedback November 11 th, 2010.
Introduction to availability modelling in ELMAS Arto Niemi.
B. Todd et al. 25 th August 2009 Observations Since v1.
BCT for protection LHC Machine Protection Review April 2005 David Belohrad, AB-BDI-PI
MKI Erratics: Hardware and Electronics Related Aspects M.J. Barnes Acknowledgements: A.Antoine, R.A. Barlow, P. Burkel, E. Carlier, N. Magnin, V. Mertens.
Time Management.  Time management is concerned with OS facilities and services which measure real time, and is essential to the operation of timesharing.
1 Beam Plans for Accelerator Systems: The Machine Protection System Jan Uythoven On behalf of the MPWG and the MPS Commissioning WG Special thanks to R.Schmidt,
Etienne CARLIER, LBDS Audit, 28/01/2008 LBDS Environmental Aspects EMC, radiation, UPS… Etienne CARLIER AB/BT/EC.
What will we do for Beam Preparation: Injection and Beam Dump Jan Uythoven Thanks to M.Barnes, E.Carlier, L.Ducimetière, B.Goddard, R.Jones, Y.Kadi, V.Kain,
1 Beam Dumping System MPP review 12/06/2015 Jan Uythoven for the ABT team.
The LBDS trigger and re-trigger schemes Technical Review on UPS power distribution of the LHC Beam Dumping System (LBDS) A. Antoine.
1 Will We Ever Get The Green Light For Beam Operation? J. Uythoven & R. Filippini For the Reliability Working Group Sub Working Group of the MPWG.
BA6 Cooling Towers Test Day Process Control Functionality and Performance Tests TCR – PCR Monitoring.
Vegard Joa Moseng BI - BL Student meeting Reliability analysis of the Input Monitor in the BLEDP.
LMC 27 November 2013 Status of LBDS LS1 activities and plans for 2014 reliability run Jan Uythoven for the many, many people working on the mentioned equipment.
LHC Beam Dumping System Experience from reliability run and Re-commissioning procedures MPP Nicolas Magnin – TE/ABT/EC.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
Risk Analysis P. Cennini AB-ATB on behalf of the n_TOF Team  Procedure  Documents in preparation  Conclusions Second n_TOF External Panel Review, CERN,
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
TRIGGER DELAY 100µs. G. Gräwer AB/BT/ECLBDS Trigger Delay2 The trigger delay is a back-up system that generates an asynchronous dump trigger for MKD and.
1 J. Mourao (TE/MPE/CP) Enhanced DQHDS functionality  Status for 2011  Increase Magnet diagnostic capabilities  Our proposals.
AC-Dipole Upgrades LHC Optics Measurement and Corrections review June CERN N. Magnin – TE/ABT/EC Thanks to E.Carlier, R.A.Barlow, J.Uythoven.
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
Commissioning / Reliability Runs / Dry runs 1 Jan Uythoven, LIBD meeting on LBDS Reliability Run 04/02/2014 Nov – Dec 2013 Commissioning individual MKDs.
BEAM INSTRUMENTATION GROUP DEPENDABILITY APPROACH CERN, Chamonix 26th January 2016 William Viganò
LHC machine protection close-out 1 Close-out. LHC machine protection close-out 2 Introduction The problem is obvious: –Magnetic field increase only a.
Eva Barbara Holzer MPP, CERN July 31, Eva Barbara Holzer, CERN MPP CERN, July 31, 2009 BLM System Audit Sequel.
RF Commissioning D. Jacquet and M. Gruwé. November 8 th 2007D. Jacquet and M. Gruwé2 RF systems in a few words (I) A transverse dampers system ACCELERATING.
Reliability and Performance of the SNS Machine Protection System Doug Curry 2013.
Outcome of BI.DIS Fast Interlocks Peer Review
Data providers Volume & Type of Analysis Kickers
LBDS TSU & AS-I failure report (Sept. 2016)
Beam Interlock System SPS CIBU Connection Review
Dependability Requirements of the LBDS and their Design Implications
The LHC Beam Dumping System
LHC Beam Dumping System Reliability Run Summary
LV Safe Powering from UPS to Clients
LHC Beam Loss Monitor System (BLM)
the CERN Electrical network protection system
LHC Risk Review: Kicker Magnet Reliability
Beam Dumping System and Abort Gap
J. Emery, B. Dehning, E. Effinger, G. Ferioli, C
Knowing When to Stop: An Examination of Methods to Minimize the False Negative Risk of Automated Abort Triggers RAM XI Training Summit October 2018 Patrick.
1v1.
Will We Ever Get The Green Light For Beam Operation?
Jan Uythoven For the LBDS Team
Review of hardware commissioning
Presentation transcript:

LBDS Audit Follow-up Jan Uythoven Thanks to: Etienne Carlier and Brennan Goddard 1

LHC Beam Dump System Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June MKD: 2 x 15 Systems MKBH: 2 x 4 (4) MKBV: 2 x 6 (4) Magnet operates under vacuum TCDQ TCDS

LBDS Audit Follow-up Audit held between January 28 th and February 15 th 2008 Outline: Quick overview of what we learned since the audit took place Point-by-point check of recommendations Conclusions Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June2009 3

Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June What we learned since the audit in 2008: Reliability Run Operation only below 5.5 TeV, due to MKB break down Operation ‘with beam’ at injection energy Beam 1Beam 2 # Pulses23’53415’469 Time considered10.5 months9.1 months Continuous running (p <13 h) 2.7 months1.7 months Data from 8/11/07 to 19/09/08 Beam 2 System pulses = 19 magnets

Reliability Run: Internal and External Post Operational Checks (IPOC / XPOC) Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June ’057 Magnet Pulses Analysed with IPOC and XPOC Systems > 10 years of operation Some hardware problems discovered  No critical failures on the MKD system which would have resulted in a non-acceptable beam dump even if redundancy would not be there No ‘asynchronous’ beam dumps were recorded (erratics). No missings. However, unexpected MKB breakdown  MKD pulse

MKB failures Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June Unexpected common mode failure on the MKB system. Flashovers in 3 out of 4 magnets simultaneously after operation under bad vacuum: stopped operation above 5 TeV. Measures taken: Vacuum interlock was implemented but not yet tested Additional vacuum interlock: digital + analog HV insulators, identified as weak point, being changed for 2009 Reduced conductance between adjacent MKB tanks by smaller aperture interconnects 50  s Moment of break down I [kA] Measured MKB wave form

MKD Issues Discovered Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June Four switch failures due to short circuit on one of the GTO discs Within limits of reliability calculation assumptions Would not have given an unacceptable beam dump but internal dump request resulting in synchronous dump Problem with voltage distribution of GTO stacks: internal dump request All checked and redistributed for 2009 Only affected availability, not safety Re-soldering of trigger contacts on GTO stack Decreasing value of compensation capacitors: capacitor changed on three systems Re-optimisation of synchronisation and compensation voltages on 2 systems Power trigger powering circuit units were under designed: refurbished for 2009 Two power converter failures One ADC card for IPOC failed Power trigger cables badly connected All failures were detected by diagnostics, IPOC/XPOC !

XPOC successfully used for detecting badly connected trigger cables Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June Generators A and D give XPOC fault Fault on XPOC: Rise time changed 50 ns, window ± 50 ns Delay changed 100 ns, window ± 50 ns Amplitude changed 0.9 %, window ± 1 % (fault on 1) Access on 16/09/08: showed on those two generators trigger cable badly connected, due to intervention on power trigger unit. 50 ns Rise time [µs]

MKD Generator Temperature Effect Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June Measure kick currents at 1 TeV Tunnel temperature down by 4 degrees, kick gone up by about 0.7 – 0.8 %, Kick response appears to lag behind temperature change, which seems logical. Yellow curve is tunnel temp. dt = 4 degrees Starting 13:00, biggest drop reached at 20:30 stable 24 hours later Series data start at 15:00, so in the middle of biggest drop in temp 6 hours 15:00 24 hours

MKD Cooling Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June Peltier temperature regulation units installed on each of the 30 MKD generators Together with temperature isolation and ventilation Humidity sensor & interlock Set regulation temperature at tunnel temperature = 23 degrees Interlock +/- 1 degree Synchronous Beam Dump if temperature gets out of regulation window Restart only possible when correct conditions are back Some weeks of operational experience required before first beam

TCDQ Energy Interlock Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June TCDQ position is a function of energy, and gets triggered by a timing event (like collimators) Sensitive to errors related to timing system and the transmission of the timing signal within the LBDS control system (from gateway to PLC) For 2009 there will be an ‘independent’ check on the TCDQ position, taking the beam energy as input parameter Dump the beam if the TCDQ is at the wrong position as expected relative to the beam energy For 2009 – 2010: software solution After 2010: hardware solution

Follow-up of Audit Recommendations Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June Section 4: General Impression: “The auditors agree that the XPOC and IPOC tests and their connections to the connection to the Injection Inhibit are critical and must be able to cover most if not all of the failure modes. However, neither the XPOC nor the IPOC currently seem to be fully mature. Areas of concern have been listed in Section Although the inherent LBDS hardware does not show evidence for potentially correlated failure modes, the auditors are concerned about external “common mode” influences in particular due to Single Event Effects (SEEs; see Section )” The Reliability Run has shown that IPOC and XPOC work very reliable for IPOC and XPOC processes, see previous slides. Single Events Upsets: R2E working group; Monitoring of Radiation; Slow increase of beam intensity (=radiation) covered by system redundancy.

Section 5: Recommendations 1. Connection to the BIS Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “The interfaces between the BIS and the LBDS are crucial for the overall safety chain. Thus, these should be properly discussed, agreed upon, and documented. The resulting solution should minimize the complexity of the overall, combined system without deteriorating overall safety.” Slide Benjamin Todd Tests done in the SPS Test procedure to check on all documented faults under discussion with BIS-people; should be done.

2. RF-Synchronisation Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “Measures must be put in place to ensure that the LBDS is always synchronous and in phase with the right and proper beam revolution frequency. This might also require actions from experts of the RF system.” Swapping Master RF B1 / B2 f rf : Commissioning procedures; however weak point is swapping the fiber optics cables for B1/B2. Brought to the attention of the RF-Group: A.Butterworth / Ph. Baudrenghien. If RF-Trip -> debunching: for higher beam intensities an RF-trip should dump the beam. Beam should always follow the f rf Back-up by: Abort Gap Monitor Abort Gap Keeper during injection, independent of f rf

3. MKD Kick Synchronisation Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “Alternatives to compensate this additional delay should be discussed.” To avoid having to use a individual trigger voltage defined as a function of energy. Worked fine during the Reliability Run: no XPOC fault

4. MKD Switch “Degradation” Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “The first experience of the LBDS has shown a slight, but constant degradation of the kicker magnet switches, presently studies by the experts. A deeper study must be conducted to understand this behaviour and alternative solutions must be elaborated.” Some capacitors found to be degrading: replaced and stable afterwards Temperature stabilisation of the MKD generators Redistribution of the GTO discs Affects availability only Long-term upgrade to 12 wafers being studied

5. MKD Rise Time is and Trigger Tolerance / Synchronisation is Tight Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “Possibilities to increase this tight time window in order to add some safety margin should be investigated.” Adapting the LHC bunch filling to 4 µs instead of 3 µs is possible, but will reduce the machine luminosity (loose 72 bunches out of 2808). Not critical straight away and can be adapted when required.

6. Redundancy Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “Therefore, the redundancy and its correct and complete separation must be verified. Means to ensure that external cables can not be swapped must be applied. Furthermore, the consequences of the non-redundant signal paths on the PTM and TFOT boards on the overall availability must be reviewed.” That the present redundancy in the design is sufficient has been studied and found to be correct in the PhD thesis of R.Filippini. At start-up several weeks have been spent to again check the redundancy of the signals XPOC has proven to be able to detect the lack of redundancy due to small changes in the kick

7. UPS & Power Cut Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “Adequate tests should be conducted to confirm that the system remains being capable of dumping the beam in case of simultaneous main and UPS power failures.” Was tested in 2008, but ‘manual synchronisation of loosing UPS and mains Test foreseen in 2009 to test power loss during same mains period. UPS is also redundant.

8. ‘As Good As New’ Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “The respective procedures, still lacking in detail, should be carefully elaborated and implemented together with the persons responsible for the RF and BIS systems. Regular “toggle on/off”-tests prior to injection with cross-checks against a central database might be able to find errors in the data chain, false cabling, and wrong “inhibit”-switch settings. However, these tests should also take into account cases of sabotage or simple vandalism.” ‘As Good As New’ of the LBDS equipment is guaranteed by the IPOC and XPOC. XPOC interlock will this year have an interlock on the SIS. Connection to BIS is tested during automatic arming procedures before every fill. General procedures after interventions need to be worked on- need a ‘framework’.

9. Redundancy Tests Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “Special and automated connectivity test procedures must be deployed in order to detect bad or faulty cable connections.” Manual testing during start-up Redundancy tests are performed automatically in the IPOC process On HV pulsed output of power trigger under implementation XPOC also detects the effect

10. Procedures for Maintenance and Inspection Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “Additional procedures must be established for maintenance and inspection in order to detect degradation of the LBDS hardware, esp. of the kicker magnets.” Test program was carried out during shutdown, some magnets were visually inspected For EC section generator test procedures after shutdown are written down and used this re-start. Additional explicit / formal procedures might be required XPOC will check on degradation during operation

11. Procedures ‘Dry-Dumps’ and ‘Safe Beam Dumps’ Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “In particular it must be defined and documented when “dry dumps” and “safe beam dumps” are needed, and how this is enforced.” Yes, on my list to do ! Important !

12. Failures not to be detected with Safe Beam Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “Finally, an assessment must be conducted on how far the “safe beam dump”-tests resembles operation with full beam, which failure modes this test is able to cover, and which failures can not be detected by the “safe beam dump”-test.” LBDS Machine Protection System tests have been detailed now. Increase in intensity will be gradual XPOC being extended to BTVDD, BLM, BPMDD, BCT

13. Second, independent FMECA study Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “A second, independent analysis should be conducted to confirm and verify these initial results.” Ongoing; but focusing on Timing Synchronisation Unit (TSU) Results expected in October.

14. Review of Magnets and Switches Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “Since the focus of this review was on the trigger electronics, an independent review of the magnet components should be organised.” Not done Results from Reliability Run MKB vacuum weakness Followed up

15. Sensitivity Analysis of applied failure rates in reliability study Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “A sensitivity analysis should be conducted to estimate if the sources (Military Handbook and the methods) are directly applicable and realistic to power systems. For example, the value of 103 FIT for power converter failure (λps) was obtained from the corresponding manufacturer.” Included in Section of the Reliability Study, p.137

16. Relative failure rates / accelerated testing Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “A comparison of the estimated values (…failure rates…) and values derived by accelerated testing of specific components (components identified by the aforementioned sensitivity analysis) should be made.” Not done explicitly Reliability Run supports results of the Reliability Study.

17. Reliability Data Base Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “It is equally vital that failures are tracked in order to ensure that the assumptions made in the FMECA thesis hold. Therefore, a “reliability database” should be set up in order to track failures and to accumulate “real life” statistics. This can be done in collaboration with other groups concerned (e.g. BIS, BLM, QPS).” MTF system for LBDS description and follow-up of faults of components presently being developped Specific for the LBDS, no collaboration BIS/BLM?QPS

18. Procedures after Failure Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “Furthermore, it is crucial that failures which could potentially undermine the safety are fully understood. Procedures must be put in place to verify, after a failure, that no safety aspect has been compromised at a design level (see also Section 5.1.2).” No standard procedures in place. Difficult for different type of failures. Did follow-up for ‘faults’ which occurred in the RR: Interlock due to voltage distribution on MKD switch (availability) MKB vacuum

19. Fiber Links Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “…it is not clear in how far bit error rates of all the fiber links have been included in this estimation. Eventually, the Manchester decoder can be made more robust by oversampling.” Error check exists, some bits added after Audit. BETS triggers dump in case of transmission error OK during RR: no faults

20. EMC > Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “During the planned EMC testing period, it is strongly recommended to verify the impact of triggering the kicker magnets onto these crossing signal lines with respect to cross-talk and EMC. Eventually, additional shielding measures must be deployed.” Done But little feedback from other groups

21. EMC < Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “All external cables (from one crate to another, e.g. via the re-trigger lines) should be tested with burst tests to identify EMC potential susceptibility.” Done for re-trigger lines (longest cables, from UA63-UA67) Further tests can be done in 2009

22. – 27. Radiation Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “Thus, it is recommended to quantify what risks, if any, are posed to the LBDS by radiation effects. The risks of SEEs and “aging” on the LBDS hardware must be understood and critical locations and components must be identified. Simulations are advanced to determine the expected flux in UA63 and UA67; A list of potentially susceptible LBDS components is created (e.g. all CMOS devices on the critical signal path); An SEE expert coordinates irradiation experiments to identify failure modes and cross-sections of these components; A Xilinx FAE is contacted in order to quantify the risks of FPGA mal-functio with the given flux; An updated FMECA model is created, plotting safety versus flux to show the boundaries of the system operation.” Followed up by R2E working group Extrapolations from existing simulations giving expected flux rates have been studied Additional radiation diagnostics installed Radiation will go up slowly with beam intensity and energy Any increase of failures will be monitored by IPOC and XPOC Issue is likely to affect availability and not safety

28. Electronics Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “It is recommended to use components with higher margins like a 25V rating.” Some critical capacitors have been changed (4 or 5)

29. Infra Red Inspection Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “An infra red inspection of all PCBs should be done in order to ensure the current high reliability, to verify the power consumption of individual components, and to detect bad components being mounted.” Done: ok.

30. – 31. Power Soak Tests & Thermal Aging Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “In order to detect faulty components and boards, additional power soak tests should be conducted. In addition, an accelerated thermal aging test of one system might be conducted as well, in order to check that the computed lifetime is not completely wrong.” Not done Reliability Run

32. Electrical Testing Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “Therefore, electrical testing is preferable to visual inspection and, if properly implemented, even faster. Errors on that level are very cumbersome to find once a unit is fully assembled. Electrical tests of all PCBs should be conducted. These are easily possible using standard automatic cable testers.” Automatic testing of PCB not done, only basic tests during production Full electrical testing of all cards is done before installation

33. Schematics Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “ Design schematics should always be kept up-to-date.” Errors brought to the attention during the Audit have been corrected

34. TSU Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “The implementation of the TSU’s DTACK should be changed in the next iteration of the design.” Card has been modified accordingly. Version V3 in preparation

35. Decoupling FPGA Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “Hence the PCB design should consider a proper decoupling of the FGPA to accommodate relatively high power consumption.” Implemented on new cards, like the TSU

36. Flash ROMs Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “The expected rate of errors in the FLASH ROMs used in the LBDS have to be verified with regard to these studies. If applicable, the use of EEPROMs instead of FLASH RAM (as e.g. done in the Safe Machine Parameters project) is strongly recommended.” Tested on test bench Found to be ok Also no problem in SPS

37. VHDL Code Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “A tighter collaboration on VHDL programming should be established by the LBDS programmers and other VHDL experts at CERN. A peer-review parallel to the development of the LBDS code should be conducted.” Done for new designs No general review of VHDL code done External TSU review includes VHDL code

38. – 42. VHDL Coding Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “However, in some designs the remaining few asynchronous resets should also be modified into synchronous resets. The “When others” clause is extensively used to make state machines safer, but at least left out on the BEC. Furthermore, it is very important to clock in asynchronous signals by three consecutive flip-flops (at least) using the system clock before propagating them further. However, in the TSU FPGA this has been omitted and the revolution clock is fanned out to a number of blocks before being synchronized. This can give problems with metastability and, subsequently, incoherent states in the different blocks. Proper documentation of the VHDL code inside a software repository like CVS is recommended.” All done “ Extensive tests must be performed every time a re-design of the FPGA VHDL code is conducted. This must include re-assessments if the VHDL compiler changes or is upgraded. A robust framework and simulation test bench must be put in place to assure that any upgrades are regression tested.” Remains to be done; test bench in preparation for TSU

PLC code Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June “A tighter collaboration on PLC programming should be established by the LBDS programmers and other PLC experts at CERN (e.g. in AB/CO and IT/CO). A peer-review parallel to the development of the LBDS code should be conducted. A high-level document describing the code, all programs and the data blocks, should be produced prior to the aforementioned peer-review” Not done “Appropriate commentary statements, currently widely missing, should be inserted into the different programs. The operational blocks (OBs) 80, 81, 82, 83, 84, 85, 86, 121, 122 have been deployed which is very good since this avoids stopping the PLC is case of internal failure. However, appropriate programs should be added in order to transmit failures to the supervisory control system.” “Proper version management of the PLC code inside a software repository like CVS is recommended. AB/CO is currently preparing guidelines for this. Methods must be put in place to ensure that the right code is loaded in the right PLC.” Done Waiting for AB/CO -> EN/ICE

Conclusions The Conclusions should be made by the Auditors My Conclusions: Many things have been followed up, some not Indicates the usefulness of the Audit Some of them are in the process of being followed up Parallel to this, work has continued on the reliability and reliability testing of the system The Reliability Run has been very useful: Confirmed global reliability numbers Pointed towards some weaknesses which have been followed up as well And there was beam: Jan Uythoven, TE/ABT LBDS Audit Follow-up, 15 June