ERCOT Project Process & Budgeting Rob Connell Director, Program Management Office TAC Update August 5, 2004.

Slides:



Advertisements
Similar presentations
VP, CIO Information Technology
Advertisements

Page 1 Program Management Office “PMO” Update Steve Wallace February 3, 2003.
2006 Project Prioritization Process
Enterprise Information Services (EIS) - Review Ray Chase Manager, EIS.
1 Emerging Issues. 2 Enterprise Data Warehouse (EDW)
ERCOT 2005 Budget Public Meeting September 1, 2004.
Objectives: Upgrade Siebel to a supported application Upgrade Oracle database to current version Deliver all existing user functionality with no degradation.
ERCOT IT Update Ken Shoquist VP, CIO Information Technology Board Meeting May 2004.
ERCOT PMO Update Robert Connell Director Program Management Fourth Quarter Results (Through 12/31/04) January 11, 2005.
1 ERCOT Financial Summary For the Period Ending August 31, 2004 Board of Directors Meeting September 21, 2004.
RO Project Priority List Update EDW Projects Update RMS Meeting Adam Martinez Mgr, Market Ops Divisional Projects Organization ERCOT April 12, 2006.
Finance & Audit Committee Meeting December 13, 2005.
Public Meeting on ERCOT’s Proposed 2004 Budget September 3, 2003 Preliminary - Subject to ERCOT Board Approval.
IO – CART Project Status Protocol Revision Subcommittee Update 06/22/06.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee June 4, 2009.
1 Business Integration Update to PRS September 20, 2012.
SO – CART Project Status Protocol Revision Subcommittee Update 2/23/06.
PMO Update to PRS Troy Anderson Program Management Office April 20, 2007.
EDS 2 Early Delivery Systems Review and Request for Approval May 2007 John Webb.
PMO Update to RMS Troy Anderson Program Management Office April 12, 2005.
ERCOT IT Update Ken Shoquist VP, CIO Information Technology Board Meeting November 2003.
ERCOT Program Management Update RMS Meeting – May 15, 2003 Steve Wallace.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee August 7, 2008.
ROS Meeting – 12/06/071Texas Nodal Program - TPTF Update Texas Nodal Transition Plan Task Force ROS Meeting Stacy Bridges, ERCOT Thursday, 12/06/2007.
September 8, 2008 TPTF Nodal Core Projects Updates Nodal Project Managers.
COMMERCIAL OPERATIONS ORGANIZATION Betty Day Director, Commercial Operations (office) (cell) (fax)
Objectives: Upgrade Siebel to a supported application Upgrade to Oracle 9i database Deliver all existing user functionality with no degradation in performance.
ERCOT PMO Update Robert Connell Director Program Management Board of Directors Update September 2005.
Overview of MID, MIR, & Extracts for DEWG 9/24/07 Steve Cox.
ERCOT PMO Update Robert Connell Director Program Management Board of Directors Update February 2005.
ERCOT PMO Update Robert Connell Director Program Management March Board of Directors March 8, 2005 (Through 2/28/05)
PMO Update to PRS Troy Anderson ERCOT Program Management Office December 17, 2009.
Page 1 TAC Program and Projects Update March 6, 2003.
MO Projects Update Adam D. Martinez Mgr, Market Ops Divisional Projects Organization ERCOT COPS Meeting May 23, 2006.
COPS – ERCOT PROJECTS UPDATE WHOLESALE MARKET DEVELOPMENT Paula Feuerbacher February 22, 2005.
Project Funding Report November 1, Business Integration Update – Agenda –Project Portfolio Updatep Revision Request Funding Reconciliation.
February 20, 2006 Nodal Architecture Overview Jeyant Tamby 20 Feb 2006.
ERCOT PMO Update Robert Connell Director Program Management May Board of Directors May 17, 2005 (Through 4/30/05)
Protocol Revision Subcommittee Report to ERCOT Technical Advisory Committee October 9, 2003.
1 New RO Projects Hope Parrish June NEW RO Projects for 2008 Requested by ERCOT - Overview Objective Objective of the following information is to.
PMO Update to PRS Troy Anderson ERCOT Program Management Office January 21, 2010.
1 TAC Report to the ERCOT Board February 16, 2005.
Feb 18, TAC Report to the ERCOT Board February 18, 2003.
ERCOT Market Services Organization Dale Goodman Director, Market Services (office) (cell) (fax)
September 21, Data Extract Projects Jackie Ashbaugh Commercial Operations Data Integrity & Administration September 21, 2006.
Objectives: Upgrade Siebel to a supported application Upgrade Oracle database to current version Deliver all existing user functionality with no degradation.
2008 Project Prioritization Review Troy Anderson ERCOT Program Management Office.
EIS Overview and Project Updates for DEWG Jackie Ashbaugh ERCOT April 13, 2006.
1 New MO Projects June COMS Extract, Report & Web Services Monitoring & Usage Statistics Jackie Ashbaugh.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee October 1, 2009.
© Property of ERCOT EMMS Improvements Operations Review Group 11/17/04.
Role of Account Management at ERCOT 2006 TAC Subcommittee Review ERCOT Board February 21, 2006.
PMO Update to PRS Troy Anderson ERCOT Program Management Office June 17, 2010.
EIS Projects Update COPS Meeting Adam D. Martinez Mgr, Market Ops Divisional Projects Organization ERCOT April 28, 2006.
Protocol Revision Subcommittee Report to ERCOT Technical Advisory Committee September 4, 2003.
1 Business Integration Update to PRS October 18, 2012.
1 Project Prioritization Review May 14, Approved Revision Requests “Not Started” – Planned to Start in Future Months Revision Request Target Start.
ERCOT Project Process Karen Farley COPS 3/22/05. Project Process  Overview of Project Requests  Process for Market Requests  Process for Internal ERCOT.
Commercial Operations Sub-Committee Update to TAC January 8, 2009 Lee Starr, BTU.
07/27/2006 Overview of Replacement Reserve Procurement ERCOT Staff PRS RPRS Task Force.
1 TAC Report to the ERCOT Board July 18, TAC Summary 4 PRRs for approval (3 unanimous) 4 PRRs for approval (3 unanimous) 5 Nodal PRRs for approval.
August 17, 2006 Data Extract Working Group EDW Project Updates 2006 / 2007 MO & RO PPL.
MODPO Project Update Overview of December Implementations & EDW Changes Commercial Operations Subcommittee December 11, 2006.
PMO Update to RMS Troy Anderson Program Management Office December 16, 2004.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee May 7, 2009.
Role of Account Management at ERCOT EIS Project Updates Jackie Ashbaugh Mgr., Commercial Operations Data Integrity & Administration DEWG October 19, 2006.
1 PR70007 – MarkeTrak Ph2 ERCOT Project Strategy 07/30/2007.
Troy Anderson Program Management Office August 10, 2005
TAC Report to the ERCOT Board
Presentation transcript:

ERCOT Project Process & Budgeting Rob Connell Director, Program Management Office TAC Update August 5, 2004

Aug 2004 Project Process & Budgeting  Project Process  Project Progress & Program Updates  Annual Budgeting & Prioritization Key Dates  Projects Needing Market Priority for 2005 Budget at PRS this Month  Questions

Aug 2004 Project Management Process Program Management Project Management Software Development Prioritizing Initiating Planning DesigningAnalyzingTestingImplementingDeveloping ClosingExecuting & Controlling Monitoring Approvals Prioritizing Initiating Planning Prioritization, Initiation & Planning Deliverables and Requirements Software Development Planning Phase Develop Work Breakdown Structure Project Deliverables are Defined Business Case is Developed Project Schedule is Developed Detail Cost Estimates for the Project

Aug 2004 Project Management Process Program Management Project Management Software Development Prioritizing Initiating Planning DesigningAnalyzingTestingImplementingDeveloping ClosingExecuting & Controlling Monitoring Approvals Executing & Controlling Closing Executing & Controlling Managing People and Resources Monitoring and Measuring Controlling Budget Managing Project Schedule Managing Project Scope Facilitating Seamless Delivery Project Closure/Signoff

Aug 2004 In Progress Release 3 Resource Plan Change Indicator Resource Plan Improvement Release 4A PRR413 - Optimization for the Whole Operating Day in RPRS Procurement Process Enhancement to OOM tools for congestion management PRR423 - Dispatch of Gen Resources Below Min Operating Level PIP137/PRR211 Association of BE Bids with RPRS PRR422 - OOM Zonal Dispatch Instructions Improvements to VSA/DSA EMMS Parameters Capture for MMS Reclear Fidelity Improve Data Elements for Local Constraints & OOMs Unit Specific Bid Limits based on Generic Costs PUCT Upgrade SPD PUCT Add Corrected MCPEs to the MOS dbase and MMS OOM Participation in Providing Ancillary Services Automate the Implementation of MCSM Special Protection Schemes AS Simultaneous Selection Release 4B Outage Scheduler Dynamic Ratings Constraint Activity Manager CSC Congestion Zone Changes MOMS Enhancements Market Monitoring MOMS Phase I SO Growth/Program Status PRI 1 (31) PRI 2 (24) PRI 3 (15) 70 To Date 1/31/046/30/04 Remaining PRI 1 (27) PRI 2 (26) PRI 3 (14) 40 NO PRI (45) 107 PRI 1 PRI 2 PRI 3 NO PRI 63 Completed 2 In Planning SCR723 Remote Access CSC Thermal and Volt Limits Calcualtions/Posting Automate DC TIE Schedule tracking process Load Forecast Performance Performance monitoring of SCADA /State Estimator Enhancement to Outage Scheduler/ STNET System protocol violation notification application/ownership transfer Increase State Estimator Observability & Improve SE Response to Input Data Conditions Performance Monitoring for ERCOT, TDSP and QSEs LAAR /BUL Enhancements Market Monitoring MOMS 2 Topology Estimation System System Operations Program Summary

Aug 2004 Completed Release 3 PRR424 - Elimination of Resource Specific Deployment used for Energy Purposes Stop Oscillation of constraint management UBES-DBES Ramp Rates Resource Test Mode OOME as Instructed Deviation Archival of Shift Factors Handling of Equipment Name Changes CA RAP Contingency Analysis Enhancements Canceled Monitor A/S Performance and Freq Cntrl Algorithms - Duplicate Enhancements to FasTrak – Duplicate System Operations Program Summary (cont.) SO Growth/Program Status PRI 1 (31) PRI 2 (24) PRI 3 (15) 70 To Date 1/31/046/30/04 Remaining PRI 1 (27) PRI 2 (26) PRI 3 (14) 40 NO PRI (45) 107 PRI 1 PRI 2 PRI 3 NO PRI 63 Completed In Planning In Progress Canceled 2

Aug 2004 Market Operations Program Summary MO Growth/Program Status PRI 1 (15) PRI 2 (8) PRI 3 (11) PRI 1 (28) PRI 2 (16) PRI 3 (11) NO PRI (5) To Date 1/31/046/30/04 Remaining PRI 1 (9) PRI 2 (7) PRI 3 (8) NO PRI (4) Completed Lodestar Data Loading Improvements PRR371 - OOM Compensation Settlement Reengineering CASUP (Phase I) Oracle upgrade for L* TGR Trading PRR440 Interim Removal of Market Solution In Planning RPRS Market Redesign – 1.1 PRR359 Improve Resource Plan – 2.2 IDR Estimation logic changes – 1.1 Q2 Enhancement SIRs – 1.1 TCR Report Enhancement – 1.2 In Progress Q1 Enhancement SIRs – 1.1 Energy Procured from ERCOT - PRR404 – 1.1 Clarification of Ancillary Services Obligation Calculation – 1.1 SCR ERCOT Settlement Estimation – 1.3 Load Research Sampling – 1.3 Tradable Generation Rights – 1.3 CASUP Lode* 3.7 – 2.1 CASUP Oracle Upgrade – 2.1 PRR359 Improved Resource Plan – 2.2 PIP204/PRR283 EPS Meter Data – 3.3 Completed In Planning In Progress 9 Canceled ERCOT Run Day Ahead Market Rule Duplicate IDR Estimation logic changes – Duplicate SCR 727 ESID Service History – 1.1 Switcher Extract PCOOM Adjustment Requirements – 2.2 Change Perl Scripts to all 2 Finals/2 Trueups – 2.3 MOStoBE Data Recovery – 3.3 PIP204/PRR283 EPS Meter Data - Duplicate MOStoLodeStar Re-write Testing -

Aug 2004 Retail Operations Program Summary PRI 1 (5) PRI 2 (5) PRI 3 (7) RO Growth/Program Status PRI 1 (7) PRI 2 (9) PRI 3 (7) NO PRI (7) PRI 1 (2) PRI 2 (3) PRI 3 (7) NO PRI (4) /31/04 6/30/04 Remaining To Date Completed In Planning In Progress Completed Competitive Metering in 2004 for Large Non-Residential Customers – 1.1 Texas Set 1.6 – 1.1 EDI Pipeline Arch & Trans – 1.1 Commercial Systems Upgrade: SeeBeyond, Paperfree and Oracle Upgrades – Performance Enhancement HTTP/HTTPS for Market Certification – 2.1 NAESB In Planning Replace TCH See PR – 2.1 Enhancements to FasTrak ETS Performance – 1.2 Siebel Upgrade – Enhancement SIRs – TS – Enhancement SIRs – ETS – 1.2 In Progress TML Phase 1 & 2 – 1.1 MIMO – 1.1 Siebel Upgrade/Replacement - Actually CRM – 2.1 Canceled Account Management CRM - Duplicate Canceled 1

Aug 2004 IO/CO Program Summary IO/CO Growth/Program Status PRI 1 (18) PRI 2 (15) PRI 3 (7) 40 To Date 1/31/046/30/04 Remaining PRI 1 (36) PRI 2 (25) PRI 3 (8) NO PRI (7) Completed In Planning PRI 1 (16) PRI 2 (12) PRI 3 (6) NO PRI (5) 39 Completed MS Project Phase I EDW-Enterprise Data Warehouse Database Management Market Operations Test Environment Enterprise Physical Security Remaining Employee and Node Access System Upgrade Taylor Blue Building Remodel Taylor Plaza Buildout Taylor Plaza Cardshop Buildout SCR727 Phase IB In Progress EDW EMMS RSS EDW Generic RSS to ODS Transformation EDW Lodestar ODS EDW EMMS ODS IT Computing Servers and Data Storage HW/SW; includes HP Openview Professional Services (Labor) Hawk/Tibco EMMS 3.0 Hardware Change request Data Center Upgrade and Mgmt ITEST Buildout EDW Phase 2 EDW Generic Data Delivery Module NICE Playback System New Taylor Office Complex Austin MET 1st Floor Finish Out Network Systems Management Software ISO CyberSecurity MS Project Phase II Console Operations Service Desk Document Imaging system HR System Canceled 170 Systems Enhancements MS Project Phase III SIR on HEAT (Consolidated tracking tool) 3 In Progress Canceled

Aug 2004 Overview of Project Requests ERCOT PMO ERCOT PMO ERCOT PM Process ERCOT PM Process PUCT Market Participants ERCOT Program Management Office Overall Management of: Project portfolio Project budgets, priorities and approvals Project Management Process Management of: Project delivery Project resources, costs, timelines Initiation of Project Requests PUCT Rulings System Change Requests (SCRs) Protocol Revision Requests (PRRs) Project Requests (PRs)

Aug 2004 Annual Prioritization Process  Priority categories are high, medium, and low, with subcategories of high, medium, and low, which result in the following priorities:  High-High (1.1), High-Medium (1.2), High-Low (1.3), Medium-High (2.1), Medium-Medium (2.2), Medium-Low (2.3), Low-High (3.1), Low-Medium (3.2), Low-Low (3.3)  High – Critical to continued operations and reliability of the market, or in response to legal requirements. (Assumes that current services or functions provided are below acceptable level.)  Medium – Important to improve service or efficiency of operations of the market. (Assumes that the current services or functions provided are tolerable but not up to the desired state or target.)  Low – Recommended to further automate operations or improve efficiencies of services currently provided by the market. (Assumes that the current services or functions provided are acceptable but action is needed to prevent degradation of services.)  The subcategories (H/M/L) prioritized the projects within the category in terms of the value/impact to the market.

Aug 2004 Key Dates  Please take note of the following important dates in the 2005 prioritization process:  8/19 – ERCOT completes internal prioritization process  8/27 – PRS Prioritization Meeting  September – Prioritized list goes to Finance & Audit Committee

Aug 2004 Projects Sponsored Not Initiated - SO  From SO CART – projects that will not be executed in 2004 and is sending back to the market.  PRR307Controllable ResourcesPR  PRR457Block Deployment for Resp. & Non-spinPR  PRR496Balancing Energy Down RequirementPR  PRR359Improved Resource PlanPR  PRR492/513/515 Congestion Mgmt ReportsPR  Entity Name Change in ERCOT  RT Market Ramp RatePR-30018

Aug 2004 Projects Sponsored Not Initiated - MO  From MO CART – projects that will not be executed in 2004 and is sending back to the market.  PIP106Direct Load Control  PRR478Lagged Dynamics PR  PIP128 Synchronous Condenser Compensation PR  UFE Analysis Metering PR  TCR Synchronization of Credit Payment PR with Settlement Invoices  BLT OOME PR  Day Ahead/Forward MarketPR  PRR408 DC-TIE Transaction AccountingPR  PRR409/PIP102 Voltage Support Compensation PR  TGR (trading piece) (related to PRR397)PR  PRR426URC for Uncontrollable RenewablePR-40057

Aug 2004 Projects Sponsored Not Initiated - RO  From RO CART – projects that will not be executed in  PR40038–1.2 – Mass customer transition  PR40037–3.3 – MSP competitive metering phase 2  PR40039–3.3 – Day-ahead market (cross impact to MO)  SCR734 – CSA Report for CRs  PR30133–3.3 – Fix retail XML transaction format to MPs

Aug 2004 Questions?