Accelerator and NuMI Upgrades Shutdown Update Cons Gattuso July 02, 2012 July 2, 2012 Cons Gattuso1.

Slides:



Advertisements
Similar presentations
NuMI Target Pile Fan Repair Michael Andrews 3/15/10.
Advertisements

Muon Campus Projects Mary Convery 1. Background on Muon Campus plan Earlier Plan had 5 Common Projects:  MC1 Building (GPP)  MC Beamline Enclosure (GPP)
ANU Cooling Systems Karl Williams Fermilab Accelerator Division CD-2/3a DOE Review of NO A October 23-25, 2007.
Proton Source Workshop Booster Downtime Wednesday, December 8, 2010 T. Sullivan.
KICKOFF AS PRESENTED 6/17/11, SEE THIS WEEKS SCHEDULE FOP THE LATEST UPDATE Shutdown Shutdown ‘11.
PEUGEOT 206 INSTALLATION 99’— 05’ TU5JP4
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
NUMI NuMI Hot Handling Jim Hylen (FNAL) NBI02 March 13, 2002 Page 1 NuMI Target Hall Radioactive Component Handling NuMI Target Hall Utilizes Three Basic.
All Experimenters’ Meeting January 09, Accelerator Operation Summary Calendar Week # 51 NuMI Weekly Integrated Intensity 8.81E18 protons BNB Weekly.
Re-commissioning the Recycler Storage Ring at Fermilab Martin Murphy, Fermilab Presented August 10, 2012 at SLAC National Laboratory for the Workshop on.
The Tevatron Decommissioning Plans AEM 10/17/11 Paul C. Czarapata.
ANU Shutdown Status AEM meeting Cons Gattuso 6/3/2012.
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
Machine Advisory Committee Review APS Upgrade Installation Plan and Schedule John Noonan November 15, 2006.
NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS Page 1 1 Infrastructure Review - W.B.S Water Systems Water Systems –Upstream.
NuMI NBI2006 September 9, 2006 NuMI Repairs for Hot Components Jim Hylen / FNAL Page 1 NuMI Repairs for Hot Components (1 sievert = 100 rem) Problem On.
F MI High Power Operation and Future Plans Ioanis Kourbanis (presented by Bruce Brown) HB2008 August 25, 2008.
Muon Campus Projects Jerry Annala Jan 23, µ AIP Scope Recycler RF system to provide needed bunch structure to future Muon Experiments Recycler RF.
Beam Transport AIP Beam Transport to Delivery Ring Instrumentation and Controls Update Brian Drendel December 15, 2014.
09/28/07Shutdown’07 Week 8 F.G. Garcia1 MTA beam line installation Weekly Report September 28, 2007 Period covered: September 24 th September 28 th (Week.
ANU Shutdown Status AEM meeting Cons Gattuso 7 May 2012.
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
Recycler Status and Plans Shekhar Mishra MID/Beams Division Fermilab AAC Review 2/4/03 Introduction to the Recycler Ring Recycler Improvements and status.
Ff NO A Accelerator Upgrades: Status Phil Adamson Fermilab
NuMI NuMI Target Hall Air System Review Introduction July 30, 2003 Jim Hylen / FNAL Page 1 NuMI Target Hall Air System Review Introduction Air system for.
Machine status – December 28  Machine status - overview  Blue ring: ramp development  Yellow ring: obstruction update  Set-up and ramp-up.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
1 Target Station Design Dan Wilcox High Power Targets Group, Rutherford Appleton Laboratory EuroNu Annual Meeting 2012.
Refurbished Booster RF John Reid October 24, 2012.
Proton Improvement Plan Keith Gollwitzer January 5th, 2015 All Experimenters’ Meeting 11/5/2015Gollwitzer AEM.
MINU GPP WBS 1. Main Injector Neutrino Upgrades - Infrastructure Project Dixon Bogert APD Department Report – March 7, 2007 Russ Alber - FESS Engineering.
TD Help for Shutdown 2012 Preliminary, will be updated April 18, 2012.
All Exp Mtg July 7, 2008 NuMI-MINOS Status Report – Laura Loiacono FAR DETECTOR: FD live time was 95.7% for cosmics last week (ROP7 problems reported at.
AP2 Line & Debuncher Studies Status Keith Gollwitzer Antiproton Source January 9, 2006 Many people involved with providing the hardware and software that.
Proton Plan PMG 9/27/07 E Prebys 1 Proton Plan Status Eric Prebys.
F All Experimenters' Mtg - 2 Jun 03 Weeks in Review: 05/19/03 –06/02/03 Keith Gollwitzer – FNAL Stores and Operations Summary Standard Plots.
Accelerator Status and Plans
Updated Overview of Run II Upgrade Plan Beam Instrumentation Bob Webber Run II Luminosity Upgrade Review February 2004.
F Booster Long Straight Corrector Package Installation Craig Drennan 2007 Shutdown Planning Meeting April 6, 2007.
Overall Layout 1 IP2 64 m LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity.
2/17/2016 Recycler -Gattuso Recycler Shut Down Status  Flying Wire Status  Wire Vacuum Certified  Tunnel Bake Prep status Disconnection of BPM, Correctors,
Main Injector Beam Position Monitor Upgrade: Status and Plans Rob Kutschke All Experimenters’ Meeting April 3, 2006 Beams-doc-2217-v3.
Status of the Accelerator Complex Keith Gollwitzer Antiproton Source Accelerator Division Fermilab 2009 Fermilab Users’ Meeting.
Users' Mtg - 4 Jun 08 FNAL Accelerator Complex Status Ron Moore Fermilab – AD / Tevatron Dept.
Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
All Experimenters’ Meeting November 25, 2013 Photo by Martin Murphy.
All Experimenters’ Meeting November 4, Accelerator Operation Summary Calendar Week # 44 NuMI Weekly Integrated Intensity 5.97 E18 protons BNB.
Mike Andrews May 10, Week 54 NuMI Activities Initial test controls on the MI65 RAW exchange skid Complete hydrostatic test of the MI65 exchange.
March 7 th Shutdown Shutdown Begins: Monday morning, March 7 th :00 Beam OFF Safety System Testing 08:00 Rack out KRSS, switch MI house power to.
Mike Andrews August 30, Weeks 1-5 Activities Rad survey open to supervised access & re-core Install crane electronics & remove shield wall Retrieve.
Muon Long Term Schedule August 15, µ Points to discuss What is the schedule What is the schedule Shutdown schedules Shutdown schedules How do we.
PIP Shutdown Status 9/17/2014. RIL/Linac Jobs L1 Transformer ◦Rigging complete ◦Electrical work started ◦Turn on this coming weekend Laser notcher flange.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
Work in the Tevatron A0 D0 B0 C0 E0 F0 Separators A49 Separator B48 TEL 2 installation A0 Xtal Collimator 1.5 m collimator A48 Shimming 6 magnets/day At.
Mike Andrews August 17, Week 16 NuMI Activities Leak testing of DI bottles & Casks Complete all bottles & casks RAW Impulse line upgrade Finished.
MI/RR Shutdown 2012 Dec Gev Lines/Injection region: Staging equipment, cleaning and prepping new part to start vacuum work. Preparing to modify the.
10/3/2014 Proton Source Update. RIL Update Source B is back in place and under vacuum It will be baked over the weekend It will be started early next.
Mike Andrews January 31, Weeks Activities Target Pile Fan Upgrades Install piping for new cooling coil units Install controls for new coil.
All Experimenters Meeting PIP Report Fernanda G. Garcia on behalf of PIP team 10/06/2014.
Proton PMG May 7 th 2015 Cons Gattuso AD Shutdown Manager.
ELENA installation progress F. Butin / ELENA collaboration.
Alignment Work for June 03, June 07, 2013 Assignment Days Contact Task ManagerStarting DateEnding DateCrew Assigned Main Injector4.0 Days Work for.
Report Technical Director Storage-Ring-Installation Completed
Report Technical Director Storage-Ring-Installation Completed
CBETA Technical Review
AD consolidation activities in LS2
Action People Time [h] Shutting down the SR 2 1
Polarized 3He target installation
Presentation transcript:

Accelerator and NuMI Upgrades Shutdown Update Cons Gattuso July 02, 2012 July 2, 2012 Cons Gattuso1

Accelerator and NuMI Upgrades April 30,2012 Cons Gattuso, AEM2 Recycler Ring, RR New injection line into RR 30% Done RR/MI 30 Straight Section Ecool Decommissioning Done RR30 Reinstallation Extraction line Installation New 53 MHz RF system Instrumentation Upgrades 65% Done New abort kickers 5% Done Decommissioning of pbar components 95% Done Main Injector Two 53 MHz cavities 65% Done Quad Power Supply Upgrade -Done Low Level RF System NuMI Change to medium energy beam configuration (new target, horn, configuration) 35% Done Cooling & power supply upgrades 35% Done

NuMI Target Hall Status New NoVA/ANU Target Pile fan cooling coil – Identified leaks in two original cooling coils – Disconnected leaking cooling coils and replaced(2) Installation of new DP dehumidifier condenser unit –Complete installation of the condenser coil housing –Complete reconfiguration of SR-3 ductwork above Target Pile fan housing –DP dehumidifiers units 4 &5 blower units not operating, those have since been repaired Target Pile dehumidifier repairs & upgrades –Install new diffuser cones for blow housing –Install remaining duct work July 2, 2012 Cons Gattuso3

DP Dehumidifier Condenser Unit July 2, 2012 Cons Gattuso4

TP Dehumidifier Upgrades July 2, 2012 Cons Gattuso5

Horn 1 and 2 RAW water systems NoVA/ANU upgrade –Completed Relocate target chase components –Horn 1 to morgue –Target to morgue –Horn 2 to work cell NoVA Horn 2 relocation –Remove R-block positioning strap –Relocated blue blocks from top of air dam –Cut out & remove welded sheet metal air dam –Remove 8 blue blocks from under air dam –Placed blue blocks in individual coffins –Move coffins to APO for temp storage July 2, 2012 Cons Gattuso6

Horn 1 RAW Skid Complete July 2, 2012 Cons Gattuso7

Target Hall Rail System July 2, 2012 Cons Gattuso8

T-Block Storage Area July 2, 2012 Cons Gattuso9

Target Hall Chase July 2, 2012 Cons Gattuso10

RR/MI Issues Encountered Injection Line –Assembly drawings –Interferences Magnets/stands Support structures Bake out systems –Heater Tape Failure Taking partial shipment of new tape from vendor Heater controller issues –Expertise issues Crew structure Vacuum components delayed –Beam pipe Meeting our Specifications Spool pieces creation –Off Project beam pipe expansion in the 400 and 520 regions July 2, 2012Cons Gattuso 11 RR RF cavities –Vacuum issues –External water line installation NuMI Cable Penetrations –Q620 cross over Cable penetration failing Main Injector General Maintenance –Water leak on Main Dipole MI327 Fixed Instrumentation –Multiwires (MI/RR/NuMI) Ti wire manufacture delay Split plan type stop issue –Slower motor –BPM Rack cabling issues 10% failure rate

Starting Plan Cons Gattuso 12 July 2, M 2M 3M 4M 7M 6M5M8M9M10M11M Jan 2013

Current Schedule 13 1M 2M 3M 4M 7M 6M5M8M9M10M11M RR RF shifted later MI Aperture upgrade Jan 2013

MI/RR Shutdown 2012 Mount Ranson New Cable pull approach has cut time nearly in half for cable pulls. Cable spooled to specific length Total cables pulls for the shutdown come to ~80 miles of cable. 3/4 of a service building pulls

MI/RR Shutdown 2012 June MIRF 4A in place Ion Pump Reconfiguration

NuMI V108 Cable that failed last year June

MI/NuMI Cable Penetration

E-cool Section

Lack of E-Cool

MI Mask at 307 July 2, 2012Cons Gattuso ft

Injection line July 2, 2012Cons Gattuso 21

July 2, 2012Cons Gattuso 22

July 2, 2012Cons Gattuso 23

July 2, 2012Cons Gattuso 24

Injection line July 2, 2012Cons Gattuso 25

MI-30 shielding July 2, 2012Cons Gattuso 26 5 pallets of lead blankets ~10-15 K lbs of lead

WWW-Cons July 2, 2012Cons Gattuso 27