Large Generator Interconnection Procedures Reform 2 nd Stakeholder Meeting May 5, 2009.

Slides:



Advertisements
Similar presentations
GEORGIA POWERS SMALL POWER PRODUCERS FUNDAMENTALS.
Advertisements

Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore.
Open Season MT to Idaho Calendar of Events Posted on NWE OASIS September 30, 2004 (Slide 8 updated 2/28/05)
Revised Draft1 Distributed Generation Interconnections - Group Study Process Option: Voluntary Rolling Window Presented to Massachusetts Distributed.
March 26, 2014 Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting.
Allan Wick, CFE, CPP, PSP, PCI, CBCP Chief Security Officer WECC Joint Meeting October 8, 2014.
Public Service Company of New Mexico
1 RTWG Tariff update to the BOD, MOPC, SPC, and RSC January 4, 2005.
Military Deposits. Making a Military Deposit Military Deposit Objectives Explain the effect of not paying a military deposit Understand and explain how.
WELCOME Western Area Power Administration1. Where did the journey begin? Western Area Power Administration2.
Queue Reform at the Midwest ISO NARUC February, 2008.
WECC PCC Meeting Salt Lake City, UT March 26, 2014.
SPP.org 11. SPP Delivery Point Addition (DPA) Process Effective May 1, 2010.
Duke Energy Carolinas Quarterly Stakeholder Meeting Independent Entity Services Thursday, January 19, :00 to 4:00 p.m. EST 4 th Quarter
1 ®  Overview Benefits of a Good Construction Schedule Baseline Schedule Development Schedule Updating and Maintenance Managing Project Changes USACE.
Federal Energy Regulatory Commission Large Generator Interconnection Final Rule RM July 23, 2003.
Topics to Cover Interconnection Process Overview
Joint Meeting: Department Grant Administrators Budget Managers January 26, 2011.
[INSERT APPLICABLE REGIONAL ENTITY NAME/LOGO] [ENTITY NAME] [FUNCTION CERTIFYING] Certification Review for [RELATED ENTITIES] [LOCATION] – [DATES OF ON-SITE.
2013 Calendar Year Customer Survey Results
Reliable Power Reliable Markets Reliable People Performance Targets for the Customer Interconnection Process January, 2008.
Duke Energy Carolinas Quarterly Stakeholder Meeting Independent Entity Services Thursday, May 13th, :00 to 3:00 p.m. EDT.
WINDPOWER 2003 Austin, TX May 18-21, 2003 Session 4A: Regulatory Issues Monday May 19, :40-5:00 pm Wind Generation Interconnection to Transmission.
Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.
2014 Calendar Year Customer Survey Results. Background Open for comment February 12, 2015 through March 31, 2015 for evaluation of prior year – 21 close.
OSC Meeting April 27, Transmission Cost Allocation Overview.
Discussion of Market Participant Choice for Transmission Connections Stakeholder Session October 14, 2011.
ISO Outlook Summer 2005 and Beyond Senate Energy, Utilities and Communications Committee February 22, 2005 Jim Detmers Vice President of Grid Operations.
NPRR514, Seasonal Generation Resource Wholesale Market Subcommittee April 12, 2013 Amanda Frazier.
PJM©2010 PJM Regional Transmission Planning Experience Andrew Ott Senior Vice President, Markets 2010 NASUCA Mid-Year Meeting June 15, 2010.
1 Interconnection Update Jay Zimmerman Manager, Transmission Policy Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
Icfi.com © 2006 ICF International. All rights reserved. Wyoming Collector and Transmission System Project – Status Report Presented to: Wyoming Infrastructure.
Entergy AFC Stakeholder Meeting February 16, 2005 Houston, TX.
Implementation Strategy July 2002 STANDARDS DEVELOPMENT LIFECYCLE PROCESS ORP Publishes & Maintains 8 Standing Committee Recommends Approval / Disapproval.
Implementing SB 1525: An Update Cheyenne Walsh Squire Sanders (US) LLP Government Finance Officers Association of Arizona Winter Conference Prescott, Arizona.
October 6, 2006 Public Stakeholder Review Portland, Oregon Conditional Firm.
March 30, 2012 Wholesale Generation Interconnection Process Photovoltaic Program Power Purchase Agreements Request for Offers.
University of Minnesota Internal\External Sales “The Internal Sales Review Process” An Overview of What Happens During the Review.
Mod 166 Review Group Incremental Exit Capacity at New and Existing Exit Points.
Duke Energy Carolinas Quarterly Stakeholder Meeting Independent Entity Services Wednesday, January 28, :00 to 3:00 p.m. ET.
2013 Wind Conference. Transmission Service Study Process Steve Purdy.
Long-Term Solution for Negative Generation Entergy Transmission AFC Stakeholder Meeting August 22, 2006.
Transmission Studies for New Long Term Network Resources Doug Powell Manager Technical System Planning Entergy Services, Inc. September 11, 2006.
Entergy AFC Stakeholder Meeting March 9, 2005 Houston, TX.
Update on the North Carolina Transmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public.
August 24, 2007 ERCOT Regional Planning Group Meeting CREZ Transmission Optimization Study Warren Lasher System Assessment.
Annual ARR Registration Workshop January 7, 2015.
DRAFT – FOR DISCUSSION PURPOSES ONLY © 2013 New York Independent System Operator, Inc. All Rights Reserved. EIPC Roll-Up Powerflow Model Zach Smith Director,
Summary Overview: Maryland Straw Man Interconnection Rule Prepared by Brad Johnson* January 11, 2007 ACN Energy Ventures *National.
Generation Interconnection Overview 2007 Transmission Summit July 31, 2007 New Orleans, Louisiana.
Slide 1 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N BPA Network Open Season 2013 Cluster Study ColumbiaGrid Planning Meeting May 2, 2013.
Open Access Transmission Tariff Amendment No. 9 Greg Broeking, Chief Financial Officer March 7, 2012.
Sample Fit-Gap Kick-off
Duke Energy Independent Entity Update
Duke Energy Carolinas Quarterly Stakeholder Meeting
Generation Interconnection Summary
Duke Energy Carolinas Quarterly Stakeholder Meeting
Implementation Strategy July 2002
ICT System Impact Study Process
Transmission Service Requests Overview
ISO 9001:2015 Auditor / Registration Decision Lessons Learned
Pseudo-tie business procedure
Proposal for Distribution Group Studies
IID Generating Facility Interconnection Process
[INSERT APPLICABLE REGIONAL ENTITY NAME/LOGO]
Rates & Regulatory Updates
[INSERT APPLICABLE REGIONAL ENTITY NAME/LOGO]
Duke Energy Carolinas Quarterly Stakeholder Meeting
Assigned to the WEQ OASIS and BPS Subcommittees
Pseudo-tie business procedure
Presentation transcript:

Large Generator Interconnection Procedures Reform 2 nd Stakeholder Meeting May 5, 2009

2 Agenda Background Review of Overall Process and Discussion of Comments Proposed Schedule

May 5, February Proposal Most of the changes adopted in January 2009 were retained. Interconnection process based on Load and Resource Study and related Transmission Study. New options for determining Network Upgrades. Biannual Interconnection Request Windows.

May 5, February Proposal Queue Management: –First Come-First Served through the System Impact Study; –First Ready-First Served after the System Impact Study. Multiple Customer options for proceeding to Facilities Study.

Customer Shows Designation as Network Resource & submits deposit Review Published Load & Resource Trans- mission Study LGIA 100% Site Control Required Two month windows to submit application. IR Applications reviewed on semi-annual basis. Attend Information Session at Beginning of IR Application Window Customer will have access to Base Case Data and may perform own Optional Feasibility Studies Facilities Study Customer submits deposit & TSR or proceeds at own risk Defer up to 1 year Submit IR Network Upgrade Studies Customer TSR Path At Risk Path $250,000 Study Deposit for >75 MW Projects OR, $125,000 Study Deposit for ≤ 75 MW Projects (Includes $25,000 non-refundable for both generation levels) Proof of 50% site control at time of application SIS Scoping Meeting Three levels of generation allowed and specified for study at time of meeting SIS After power flow portion of SIS, customer is must select one generation level SIS Review (with cost estimates) and FS Scoping Meeting Verify 50% of Site Control ABCD IC Facilities & Unit Specific Network Upgrades

Review Published Load & Resource Transmission Study Attend Information Session at beginning of IR Application Window Customer will have access to Base Case Data and may perform Optional Feasibility Studies Customer A

$250,000 Study Deposit for >75 MW Projects OR, $125,000 Study Deposit for ≤ 75 MW Projects (Includes $25,000 non-refundable for both generation levels) Two-month windows to submit application IR Applications reviewed on semi-annual basis. Submit IR B Proof of 50% site control at time of application

SIS After power flow portion of SIS, customer is asked to select one generation level SIS Scoping Meeting Three levels of generation allowed and specified for study at time of meeting IC Facilities and Unit-Specific Network Upgrades C

Customer shows designation as Network Resource & deposits 50% of IC Facilities & unit-specific Network Upgrades money LGIA SIS Review (with cost estimates) and FS Scoping Meeting Verify 50% of Site Control Facilities Study Customer deposits 50% of IC Facilities and unit-specific Network Upgrades money and submits TSR or proceeds at own risk Defer up to 1 year Network Upgrade Studies TSR Path At Risk Path D

May 5, Network Resource Path Network Customers submit Annual Load and Resource Plan. Tri-State prepares Load and Resource Plan and related Transmission Plan. –Resource Zones identified –Network Upgrades identified –Tri-State funds the cost of Network Upgrades Customer demonstrates that it is a planned Network Resource within Resource Zone.

May 5, Network Resource Path Facilities Study includes: –Interconnection Facilities –Unit-specific Network Upgrades required to interconnect the facility Example: Ring Bus at Interconnection Substation is considered a Network Upgrade Interconnection Customer will fund Interconnection Facilities and unit-specific Network Upgrades. Interconnection Customer will receive transmission credits for Network Upgrades.

Customer shows designation as Network Resource & deposits 50% of IC Facilities & unit-specific Network Upgrades money LGIA SIS Review (with cost estimates) and FS Scoping Meeting Verify 50% of Site Control Facilities Study Customer deposits 50% of IC Facilities and unit-specific Network Upgrades money and submits TSR or proceeds at own risk Defer up to 1 year Network Upgrade Studies TSR Path At Risk Path D

May 5, Transmission Reservation Path Customer’s Generating facility is not a Network Resource within a Resource Zone. Customer requests transmission under Tri- State’s Open Access Transmission Tariff. Tri-State performs Transmission System Impact Study. –Identifies Network Upgrades required to deliver power across the system, not unit-specific Network Upgrades.

May 5, Transmission Reservation Path Interconnection Facilities Study: –Studies Interconnection Facilities and unit-specific Network Upgrades. –Incorporates results of Transmission System Impact Study Interconnection Customer funds Network Upgrades. Interconnection Customer will fund Interconnection Facilities and unit-specific Network Upgrades. Interconnection Customer will receive transmission credits for Network Upgrades.

Customer shows designation as Network Resource & deposits 50% of IC Facilities & unit-specific Network Upgrades money LGIA SIS Review (with cost estimates) and FS Scoping Meeting Verify 50% of Site Control Facilities Study Customer deposits 50% of IC Facilities and unit-specific Network Upgrades money and submits TSR or proceeds at own risk Defer up to 1 year Network Upgrade Studies TSR Path At Risk Path D

May 5, At-Risk Path Customer’s Generating facility is not a Network Resource within a Resource Zone. Customer chooses not to request transmission. Interconnection Facilities Study: –Studies Interconnection Facilities and unit-specific Network Upgrades Interconnection Customer will fund Interconnection Facilities and unit-specific Network Upgrades. Interconnection Customer will receive transmission credits for Network Upgrades. Customer may use transmission system on an as-is basis, at its own risk for deliverability.

May 5, Facilities Study Deferral If Customer has not met all Facilities Study requirements, it may request one-time delay of up to 1 year. When Customer is ready for Facilities Study, it is scheduled behind any other request that has previously met Facilities Study milestones. –First Ready First Served Tri-State will use the original System Impact Study but may be required to update the study to reflect system changes during the deferral period.

Customer Shows Designation as Network Resource & submits deposit Review Published Load & Resource Trans- mission Study LGIA 100% Site Control Required Two month windows to submit application. IR Applications reviewed on semi-annual basis. Attend Information Session at Beginning of IR Application Window Customer will have access to Base Case Data and may perform own Optional Feasibility Studies Facilities Study Customer submits deposit & TSR or proceeds at own risk Defer up to 1 year Submit IR Network Upgrade Studies Customer TSR Path At Risk Path $250,000 Study Deposit for >75 MW Projects OR, $125,000 Study Deposit for ≤ 75 MW Projects (Includes $25,000 non-refundable for both generation levels) Proof of 50% site control at time of application SIS Scoping Meeting Three levels of generation allowed and specified for study at time of meeting SIS After power flow portion of SIS, customer is must select one generation level SIS Review (with cost estimates) and FS Scoping Meeting Verify 50% of Site Control ABCD IC Facilities & Unit Specific Network Upgrades

May 5, Proposed Schedule May 15 th —Tri-State will post draft LGIP. June 12 th —Comments due on draft LGIP. 30 days prior to Effective Date—post final LGIP on OASIS. Late Summer 2009—LGIP is effective. 30 days after Effective Date—publish Load and Resource Transmission Study.

May 5, Addendum Summary of Comments and Tri-State responses

May 5, Key Comments and Responses Feasibility Studies—elimination of Feasibility Study has negative impact on applicants — Establish Pre-Application Queue process and make Feasibility Study optional. Experience for Tri-State is that Feasibility Studies provide little value. Encourage applicants to conduct own screening studies using available WECC base-case data.

May 5, Key Comments and Responses Deposits—request for reduced, staged deposits: $40,000 to $90,000 Tri-State deposits are intended to cover the estimated cost of Interconnection Studies and administration costs. –The suggested deposits will not cover study costs. –$25,000 will be non-refundable The deposits will be used for study costs plus cost of administering requests.

May 5, Key Comments and Responses Site Control—requirements are too burdensome and too soon in the process. Site Control is key to assessing the validity of interconnection requests. –Retain existing requirement for 50% of site control at application. –Delay 100% site control until execution of LGIA. Strict site control requirements benefit both Tri- State and Interconnection Customers by helping to identify valid projects.

May 5, Key Comments and Responses Site Control—continued Tri-State expectations: At application Tri- State expects the application to include documentation of lease or ownership rights as along with a GIS map of the entire site with the areas under contract or option highlighted on the map. Documentation would typically include copies of leases, deeds, or option agreements, which Tri-State will treat as confidential information.

May 5, Key Comments and Responses Cluster Studies will be more effective than stand- alone studies proposed by Tri-State. Tri-State does not agree that cluster studies will be more effective way of studying Interconnection Requests. However, Tri-State has retained the right to use cluster studies where it determines that they may be a more efficient way of studying Interconnection Requests. Tri-State is prepared to discuss this issue as part of the stakeholder process.

May 5, Key Comments and Responses Interconnection Studies should be linked to Long- Range Transmission Planning. Tri-State will continue to use WECC base-cases modified to meet the needs of the Interconnection process. –Facilities identified in long range plans are often scheduled after the generators’ in service date. –Long-Range projects do not have CPCNs and can not be counted out for planning Network Upgrades.

May 5, Key Comments and Responses Suspension—Tri-State should expand ability to suspend construction—developers need more flexibility. Suspension undermines certainty of planning process. Customer has the ability to delay in-service date up to 5 years, but construction will proceed if it affects other requests. Option to delay Facilities Study for up to one year.

May 5, Key Comments and Responses Proposal is discriminatory and may violate FERC Order 2003 Tri-State, as a non-jurisdictional, is subject to limited FERC jurisdiction –Tri-State must meet FERC’s comparability and non- discrimination requirements –Tri-State’s proposal meets those thresholds Tri-State proposes 3 paths for interconnection. –The paths are not intended to be equivalent but to provide customers options to interconnect