1 MICE Report to the Oversight Committee February 2008 Ken Long, Andy Nichols and Richard Apsimon 25th Feb 2008 MICE Phase 1 Status MICE Phase 2 Overview.

Slides:



Advertisements
Similar presentations
Report from MICE project teams Proposed MICE organogram: revised Revised request for resources for financial year 2003/04 Review of iMICE schedules – status.
Advertisements

1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
1 MICE Video Conference Installations to date Future installation work Plans for May shutdown MICO organisation Use of Technical Board.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
1 VLPC system and Cosmic Ray test results M. Ellis Daresbury Tracker Meeting 30 th August 2005.
March 2003 Paul Drumm MICE Collaboration Meeting, CERN 1 Beam Line & Installation Plans Paul Drumm CLRC Rutherford Appleton Laboratory.
Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports.
1 MICE Tracker Readout Update, Preparation for Cosmic Ray Tests Introduction/Overview AFE-IIt firmware development VLSB firmware development Hardware progress.
MICE FAC Alain Blondel 7 October   MICE The International Muon Ionization Cooling Experiment MICE CM19.
paul drumm; 3rd December 2004; AFC MM 1 Cost & Schedule Review I Terms of reference: –To review the Cost and schedule of the MICE Muon beam –To review.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
Tracker 2 Cryo &Electronics Update Linda Coney, UC Riverside Terry Hart, U Mississippi Ben Freemire, IIT Malcolm Ellis, Brunel University ADB MICE Collaboration.
1 Implications Of Infrastructure Build The Infrastructure Project is bigger than anyone thought, but now it’s understood The cost was underestimated, but.
CMPB Alain Blondel 14 April STATUS OF MICE.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
An updated Baseline Design for MICE From proposal to technical reference Paul Drumm, Dec 2003.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
1 MICE Report to the CMPB February 2008 Ken Long, Andy Nichols and Richard Apsimon 22nd Feb Project Manager’s Report 2.Project Status, risks and.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
MICE Status (with a UK slant) Paul Drumm, MICE Collaboration UK-NF June 2003.
1 MICE Tracker Update M. Ellis UKNFIC Meeting 25 th August 2005.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.
Project manager report paul drumm CM16 October 2006.
K. Long, 14 October 2003 MICE-UK: progress report Progress: WP1: B&I: Target u/g (Sheffield) … PD Focus coil assembly Spectrometer Software Issues: Scientific.
K. Long, 10 October 2015 Project Manager’s report Status/progress since CM18 Looking forward Organisation Conclusions.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
MICE Collaboration meeting (CM20) At RAL 10 – 13 Feb 2008 AFC Magnet – Status and Progress W. Lau, Oxford University.
Tracker Summary Alan Bross MICE CM October 10, 2007.
1 MICE Tracker Readout Update, Preparation for Cosmic Ray Tests Cosmic Ray Tests at RAL AFE-IIt Firmware Development VLSB Firmware Development Summary.
Technical Board and Safety Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Norman McCubbin1 Report from the Collaboration MICE Project Board (CMPB) Norman McCubbin Director, Particle Physics Department MICE/UKNF Oversight Committee.
U.S. Muon Accelerator Program: MICE Milestones & Resource-Loaded Schedule M. A. Palmer, Director October 31, 2012.
RLSR 16/4/2015 UK Financial Plan & Risks. Content Finances – Cost to Completion Risks – Top level to completion – R9 working space – Summary 2 RLSR 24/11/2014.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
Report from MICE project teams Feedback from PPRP MICE funding: various scenarios Issues  Financial year 2003/04  iMICE common fund.
Project Managers Report CM40 Collaboration Board – Rome Roy Preece 28 th October 2014.
MICE Oversight Committee Meeting RAL, 24 April 2014 Paul Soler on behalf of the MICE Collaboration Status of MICE and Spectrometer Solenoids.
Paul Drumm, cm10, 27 Oct 2004 MICE Project Report Paul Drumm Collaboration Meeting 10 Rutherford Appleton Laboratory October 2004.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
VLPC System Update A.Bross MICE CM Feb 9, Cryo  Production cryostats 1 and 2 ran smoothly at operating temperature  However, Cassette 109 in cryo.
US Project Plan for MICE Mark Palmer Peter Garbincius, Alan Bross, Rich Krull Fermilab November 24, 2014.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE Tracker Readout Update Introduction/Overview TriP-t hardware tests AFE IIt firmware development VLSB firmware development Hardware progress Summary.
MICE CM20 Alain Blondel 10 February The International Muon Ionization Cooling Experiment MICE CM20 Spokesmouse remarks.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
Malcolm Ellis – Brunel University – 8th April The International Muon Ionization Cooling Experiment.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
Finance Roy Preece STFC RAL Oversight Committee Meeting 27 th November 2015.
Tuesday 9 th January Project Status Report Project Achievements Project Schedule Issues Finance Summary Risk Register Photos.
RLSR 16/4/2015 UK Financial Plan & Risks. Content Finances – FY 2014/15 – Cost to Completion Risks – Top level to completion – R9 working space – Summary.
UK Project Plan (Finance & Risk) Alan Grant STFC DL RLSR 5 th April 2016.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
21 Mar 2007ALICE - Paul Dauncey1 ALICE CR07: Installation and Commissioning Paul Dauncey Material from: L. Leistam: “ALICE Status” W. Riegler: “Commissioning.
1 UK Project Finance & Schedule. Overview Finance  Budget Setting 2013/14  June Finance  Forward look to complete stepVI Schedule  Overview 2.
UK Project Plan Roy Preece STFC RAL RLSR 26 th October 2015.
Reported by Ron Prwivo for Ian Robson. Overview Response to Recommendations from the RLSR of November 2014 – very good, RF staffing remains an issue Very.
Resource Loaded Schedule and Budget Profile
Status of the MICE Construction Project
UK Financial Plan & Risks
MICE CM31 Schedule summary
MICE Project in the US: Completion of Efforts
MICE PM Report Progress with the Infrastructure A few problems
Presentation transcript:

1 MICE Report to the Oversight Committee February 2008 Ken Long, Andy Nichols and Richard Apsimon 25th Feb 2008 MICE Phase 1 Status MICE Phase 2 Overview Progress from the MICE Collaboration since the last OsC meeting

2 Contents Phase I:  Status: What’s complete What will be complete by 31Mar08 What will over-run  Principal milestones – overview Organisation Phase I finances:  Outturn forecast  Request for contingency  Option for re-definition of scope Status of tracker build Phase II finances: Conclusions/issues

3 Phase I: status See RA, AN

4 Principal milestones

5 Progress since Jun08 September 2007 June 2007 February 2008

6 Organisation

Project-management: Discussions started within collaboration to define MOM team: Plan to start Nov07 iMICE positions, Project Manager/Technical Coordinator and MICE Operations Managers must be agreed by MICE Collaboration Board ant CM19 (Oct07) New team:

8 Organisation Project management team established:  A.N. Other PPD: P. Flower, in place from October Took responsibility for testing completed Q35s and D2 (and other things!)  MOM team now in place: Past: Blondel, Long, Zisman Present: Gianninni (present MOM) Future: Apollonio, Kyberd, Ellis, Grauhlich, Long, Bross, Zisman, Kaplan, Blondel Project on much better footing, but:  PM (R.Apsimon) has applied for early retirement Consultation over successor has started  P.Flower has applied for early retirement  Other staff have applied for redundancy/retirment Uncertain times! WBS: change in infrastructue work package manager:  T.Hayler replaced C.Nelson from January 2008 Preparation of reports:  Much better, but still some work to do …  For Phase II plan to set up a data-base (in common with UKNF) …

9 Phase I finances:

10 Phase I finances:

11 Phase I: possible re-definition of scope Outturn forecast in excess of allocaiton +WM + contingency  Therefore seek a re-scope that will bring the total spend+requitement with the £9.72 envelope Option:  Move procurement/installation of magnetic shield walls out of Phase I  Undertake redesign with a view to simplification of design and reduction of cost as part of Phase II Technical details from Andy Nichols Magnetic shielding will be required in Phase II  Possibilities for cost reduction: Reduction in quantity of iron –Thickness –Perhaps north (linac side) wall need not be as thick »Extreme possibility: north wall is not needed (unlikely) If less weight of iron, then may be possible to simplify support –But, structure needs to support magnetic forces

12 Phase I: possible re-definition of scope Present schedule for build of magnetic shielding:  Start April; complete end of June  Heavy civil construction in conflict with running MICE with tracker: Concrete dust/metal swarf incompatible with tracker electronics Agreement with FNAL precludes heavy construction work in vicinity of VLPC cryostats (VLPC cassettes are D0 live spares)  Significant schedule issue Delay/redesign magnetic shielding: pros and cons:  Pros: Design for a cost saving: reduce capital cost and perhaps a staged build Staged build: –Would allow ‘just enough’ steel to be installed for each stage in MICE build up –May allow data-taking to be scheduled in between sections of build  Cons: Redesign implies delay to installation start and increase in staff effort required Staged build might result in an overall increase in cost: –Though the spend profile may be more easily managed

13 Tracker #1 complete in R8 Tracker #2:  All stations available and QAed  Waveguides in production Expect to polish at FNAL in March  All components for space frame available  Will complete fabrication of tracker #2 by end of March Location pieces for installation in solenoid all manufactured  Procedure defined, space-envelope discussion will be coordinated by PM Spare stations:  Bodies being machined, will complete and QA by end of March 2008 Status of tracker build: mechanical

14 Status of tracker build: station QA

15 Station QA summary:

16 Status of tracker build: slow controls

17 Production cryostats 1 and 2 ran smoothly at operating temperature  But, cassette in cryo #2 has developed an internal leak and will have to be pulled Cryo #3 is cooling down  Operating not yet satisfactory (6.2K at 60Hz?) Cryo #4 has its cassettes installed  Almost ready for cool down AFE power mods complete for Cryo #1,2,3  No longer have low voltage power problems Target is to ship system (Cryo #1 and Cryo #3) by end of February Status of tracker build: cryo system and VLPCs

18 VLPC system: photos:

19 Significant progress in D & A FPGA code:  Issues: Programmable look-up table code (S.Galagadera) support Debugging of AFPGA buffer –Ongoing Test of PLL on frequency-varying ISIS clock  Goal: complete by April Zero-suppression scheme implemented Fast-clear implemented Testing of VLSB has revealed some issues:  Set-up time unacceptably long, implementation of correction for this uncovered some ‘bugs’ Work is in hand to correct this Goal: send system back to RAL in March Status of tracker build: electronics and DAQ

20 Read-out and DAQ: timing signals: Timing r/o demonstrated:  Crucial for step V

21 Status of tracker build: schedule Tracker schedule:  Tracker #2 to be fabricated by end March ’08 (means assembled space frame in coffin)  Cosmic ray test of tracker #1 started before end March ’08  Continuing resolution of installation: Run with cosmics, install in solenoid, run with cosmics? Run with cosmics, install/deinstall in Hall, run with beam?

22 Phase II finances: MICE-UK Phase II deliverables:

23 Phase II finances: profile in line with PPRP recommendation As presented at September OsC: STFC funding cuts likely to imply a significant reduction in resources …

24 Phase II finances: guidelines from J.Womersley Seek to defend a continuing accelerator R&D programme at the level of ~£10M / year Guidelines for the MICE-UK and UKNF programmes:

25 Phase II finances: first attempt to satisfy guidelines:

26 Phase II finances: consequences: Significant (and unrecoverable) delay:  Above assumes contract for focus-coil modules is let on the 29Feb08 Implies first payment this financial year  To get close to requested profile, had to introduce arbitrary 3 month delay to start of manufacture of second set of coils Moves payments into financial year 2010/11 11 months 14 months Urgent action is required!

27 Risks: Scientific:  MICE results lose impact because results are not timely Damage to international partnership:  Integral of cost to international partners rises significantly STFC/RAL reputation:  Over the past year, the international collaboration (the US in particular) has increased its investment in MICE Phase II  For the UK to delay the schedule of the experiment risks not only the timely inward investment, but the UK reputation as a reliable collaborator and host

Personal comment: Everything to play for! Only ‘elephant in the room’ is the target dust issue Being addressed appropriately Much to do but: Likely to meet be ready for Christmas shutdown Likely to be able to carry out work required in Christmas shutdown Tracker likely to be available when required for Steps I and II Phase II: International and UK preparations well advanced Lack of UK resources beyond March 2008 may hold up project! Conclusions/issues September OsC

29 Conclusions and principal issues: Conclusions:  The increase in the pace of the MICE-UK project has now been maintained since June 2007 Technical progress from RA and AN …  The outturn forecast is in excess of the £9.72M envelope A possible re-scope option (magnetic shield wall redesign) has been identified Issues:  Phase I resources need to be carried over into financial year 2008/09  Since some magnetic shielding walls are required for Phase II, the best way forward needs to be identified: Noting that the infrastructure project now has gathered momentum, the project teams preference is: –To review rapidly the design with a view to reducing cost and identifying whether a staged build is possible; and –To push ahead as close to the present schedule as possible  It is urgent to resolve the funding of Phase II