7/26/2006 Wyatt Merritt 1 DECam CD1 Documentation DOE Critical Decision Process Documentation Requirements.

Slides:



Advertisements
Similar presentations
Executive Session Director’s CD-1 Follow-Up Review of the APUL Project November 2-3, 2009 Dean A. Hoffer.
Advertisements

Mu2e WGM 2/22/2011 R. Ray Mu2e Project manager. CD-1 Our sole focus is on CD-1 and in particular, the Director’s Review scheduled for April 3-5. To be.
Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review 1 DOE/NSF Review of the Dark Energy Survey (DES) Project SC 6/7 Cost, Schedule.
Project Management Process Project Description Team Mission/ Assignment Major Milestones Boundaries Team Identification Measures of Success Roles & Responsibilities.
1 DOE Annual Review -June 15,2005 An Overview of Conventional Facilities (Civil Construction) U. S. ILC Civil studies and cost issues for Snowmass Fred.
LSU 07/07/2004Communication1 Communication & Documentation Project Management Unit – Lecture 8.
Project X RD&D Plan Conventional Facilities (Civil Construction) Russ Alber AAC Meeting February 3, 2009.
FY2010 PEMP Notable Outcomes October 15, FRA, LLC Board of Directors 10/15-16/2009 Office of Quality and Best Practices Performance Evaluation Management.
Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.
1 BROOKHAVEN SCIENCE ASSOCIATES Authorization Basis Plan Steven Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting December 10 – 11, 2009.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck Deputy Director (Project Management)
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier Director for Conventional Facilities CD-2 Planning May 8, 2007.
Lab-Wide Earned Value Management System Project Core Team Meeting October 01, 2008 Dean A. Hoffer/Elaine McCluskey.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck NLSL II Deputy Director (Project Management)
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
7/26/2006 Wyatt Merritt 1 DECam Preparations for Critical Decision 2/3a Preparations for CD2 Preparations for CD3a DECam MOUs.
Initiate Technology Development Finalize AoA Plan, AS, ICD, TDS, Develop CDD, and TEMP Initiate Milestone B Program Review Planning Process Initiate Acquisition.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Status & Charge to ASAC Steve Dierker Associate Laboratory Director for Light Sources, NSLS-II Project Director.
12 GeV Upgrade Project Status Allison Lung Hall C Users Meeting Jefferson Lab January 18, 2008.
John Peoples for the DES Collaboration BIRP Review August 12, 2004 Tucson1 DES Management  Survey Organization  Survey Deliverables  Proposed funding.
LBNE Working Group Meeting December 20, :00– 5:00 PM Snake Pit.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
Executive Session Director’s CD-1 Review of the LBNE Project September 25, 2012 Jim Yeck.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
3.1.1 Optics, Optical Corrector, Mechanical Systems M. Johns, C. Claver.
WBS x.11 Conventional Facilities Americas Region ILC Fermilab ART Meeting1 Conventional Facilities and Siting Global Group Americas Region FY.
Status Report on ILC Project in Japan Seiichi SHIMASAKI Director, Office for Particle and Nuclear Research Promotion June 19, 2015.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science Office of Science Review of the LCLS.
LHC CMS Upgrade Project CD-1 Alternative Selection and Cost Range Steve Webster Federal Project Director August 26, 2013 CD-1 Executive Session.
Project X RD&D Plan Beam Transfer Line and Recycler Injection David Johnson AAC Meeting February 3, 2009.
Brenna Flaugher October 30, 2007 Preliminary Directors Review 1 Outline This talk will describe progress on DECam since the joint NSF/DOE CD-1 review in.
Brenna Flaugher July 25-27,2006 Directors Review 1 The Dark Energy Survey Camera: DECam 1.1 Management 1.2 Focal Plane Detectors 1.3 Front End Electronics.
Plan to go forward Peter Wilson SBN Program Coordinator 27 September 2014.
Project X Working Group Meeting January 15, :00 PM Snake Pit.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
UCLA - March 8, 2006 US TBM Cost Estimate Status March 8, 2006 Tom Mann.
V. O’Dell, L0 Workshop 25-Sep Run 2b Layer 0 Workshop u Layer 0 proposal from project Management perspective s History/News s Schedule.
Brenna Flaugher, PMG, April 6, 2007 DECam Funding Need Profile (Dec 06) (then yr $, Overhead included) This gave a technically driven schedule resulting.
1 Ventilation Systems Capital Asset Projects Safety Significant Confinement Ventilation System (15-D-411) Exhaust Shaft (15-D-412) Ronald.
Proposal for ESS DTL Roadmap. Divide Into Four Phases 1.Conceptual Design Phase (In progress) 2.Technical Design Phase 3.Prototyping Phase 4.Construction.
Office of Baseline Change Proposal (BCP) Approval or Brief Presented by: Draft version Jun 16, 2015.
DOE Review of LARP – Feb 17-18, 2014 DOE Critical Decision Process Ruben Carcagno February 17,
Cost and Schedule Breakout Session Paul Weinman Pacific Northwest National Laboratory.
K. Long, 25 June, 2016 IDR: structure and overall timeline: Slides are to introduce discussion of how we prepare IDR. Propose to revise slides as we discuss.
Challenges to get LBNF ready for Far Detector installation ASAP Elaine McCluskey ELBNF Proto-Collaboration Meeting 22 Jan 2015.
Office of Project Management Oversight and Assessments Office of Critical Decision-3 Approve Start of Construction or Brief Presented by:
CMS HL-LHC Detector Upgrades Project Planning Workshop, 26th – 30th Sept 2016, Fermilab Lucas Taylor Associate PM (for Cost, Schedule, Risk) Overview and.
Principal Investigator ESTCP Selection Meeting
Camera PDR/CD1 Planning 19 September 2008
Head, Office of Project Management Oversight (OPMO)
Project Management W. J. Foyt
Tribal Hazard Mitigation Planning
Francesco Forti University and INFN, Pisa
Preparations for a Lehman Review
DOD’S PHASED SYSTEM DEVELOPMENT PROCESS
ESS Project Status Roland Garoby – Technical Director August 2018.
Elettra Sincrotrone Trieste
PULSE Building Renovation
Conventional Facilities (WBS 1

Bunker Internal Review Welcome & Charge
Imaging & Engineering STAP Meeting 12th-13th of April 2018

Welcome Update on ESS Construction Project
Preliminary Project Execution Plan
Conventional Facilities
LCLS Instrument MIE Project: Staffing, Schedule
Presentation transcript:

7/26/2006 Wyatt Merritt 1 DECam CD1 Documentation DOE Critical Decision Process Documentation Requirements

7/26/2006 Wyatt Merritt 2 The DOE Critical Decision Process CD-0: Determination of Mission Need –For DES, this is a based on a generic CD-0 for dark energy experiments including several options, issued Nov 22, –DES matches the description of Option 1 (CDR Section 6) CD-1: Preliminary Baseline –For DECam, this will be a paper review, with documentation due in Sept 06 –This week’s review is the preliminary determination by the Fermilab Director of DECam readiness for CD-1 –Need to provide ranges for cost and schedule –Approval hoped for in Nov 06

7/26/2006 Wyatt Merritt 3 DOE Critical Decision Process CD-2: Performance Baseline –DECam target dates: Directors Review Feb 07 CD2 ReviewMar 07 –Need to provide definite baseline for cost and schedule –Approval hoped for in Jul 07 CD-3: Full Construction –DECam target dates Directors Review Jul 07 CD2 ReviewAug 07 –Need to provide definite baseline for cost and schedule –Approval hoped for in Sep 07 –Matches hoped-for funding profile with construction funds arriving in FY08

7/26/2006 Wyatt Merritt 4 DOE Critical Decision Process CD-4: Project Completion –DECam target date: 1 st Q FY11 DECam milestone date:3 rd Q FY11 –Defined as successful completion of acceptance tests by reassembled instrument at CTIO Does NOT include installation on the Blanco

7/26/2006 Wyatt Merritt 5 Documentation Requirements Collaboration documents (need circulation to full collab) –Conceptual Design Report (CD1) / Technical Design Report (CD2) CDR demonstrates significant progress on CCDs, optics, FEE –Science Requirements and Technical Specifications –Project Management Plan –Cost Estimate and Resource Loaded Schedule (WBS) Complete versions exist, have circulated through collaboration –Revisit cost and schedule range after review –Continue to understand WBS tuning required to meet funding profile

7/26/2006 Wyatt Merritt 6 Documentation Requirements Fermilab documents (need approval of FNAL management) –Preliminary Hazard Analysis (CD1) / Safety Assessments (CD2,3) –Configuration Management Plan (Draft at CD1) –Risk Management Plan (Draft at CD1) –Value Management Plan Reasonable drafts for each of these exist –Have consulted PPD ES&H for PHA –L2 managers consulted for the other three –For September: ramp up documentation efforts

7/26/2006 Wyatt Merritt 7 Documentation Requirements DOE Site Office documents (need approval at DOE level) –Acquisition Strategy (draft by CD1, final by CD2) –Project Execution Plan (draft by CD1, final by CD2)