1 4/2/2009 PHENIX WEEKLY PLANNING 4/2/2009 Don Lynch.

Slides:



Advertisements
Similar presentations
1 4/9/2009 PHENIX WEEKLY PLANNING 4/9/2009 Don Lynch.
Advertisements

1 12/3/2009 PHENIX WEEKLY PLANNING 12/3/2009 Don Lynch.
1 05/14/2009 PHENIX WEEKLY PLANNING 5/14/2009 Don Lynch.
1 2/11/2010 PHENIX WEEKLY PLANNING 2/11/2010 Don Lynch.
1 4/30/2009 PHENIX WEEKLY PLANNING 4/30/2009 Don Lynch.
2/2/20121 PHENIX WEEKLY PLANNING 2/2/2012 Don Lynch.
1 3/19/2009 PHENIX WEEKLY PLANNING 3/19/2009 Don Lynch.
2/9/20121 PHENIX WEEKLY PLANNING 2/9/2012 Don Lynch.
PHENIX WEEKLY PLANNING 5/17/2007 Don Lynch. 5/17/2007 Weekly Planning Meeting 2.
1 7/02/2009 PHENIX WEEKLY PLANNING 7/2/2009 Don Lynch No Meeting this week due to July 4 th holidays. Slides have been updated. Next planning meeting will.
1 3/12/2009 PHENIX WEEKLY PLANNING 3/12/2009 Don Lynch.
1 2/12/2009 PHENIX WEEKLY PLANNING 2/12/2009 Don Lynch.
1 1/22/2009 PHENIX WEEKLY PLANNING 1/22/2009 Don Lynch.
1 1/13/2011 PHENIX WEEKLY PLANNING 1/13/2011 Don Lynch No Meeting Today Due to snow shortened work week, today’s planning meeting has been cancelled. Slides.
1/5/20121 PHENIX WEEKLY PLANNING 1/5/2012 Don Lynch.
1 3/5/2009 PHENIX WEEKLY PLANNING 3/05/2009 Don Lynch.
PHENIX WEEKLY PLANNING 4/10/2008 Don Lynch. 04/10/08 Shutdown ’08 Schedule Purge Flammable Gas, Magnet & DAQ TestsDone Remove lock-out & open shield wallDone.
PHENIX WEEKLY PLANNING 3/8/2007 Don Lynch. 3/8/207 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Continues…. All Up Commissioning In Progress.
12/29/20121 PHENIX WEEKLY PLANNING 12/29/2011 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
1 2/26/2009 PHENIX WEEKLY PLANNING 2/26/2009 Don Lynch.
1 4/16/2009 PHENIX WEEKLY PLANNING 4/16/2009 Don Lynch.
1 11/12/2009 PHENIX WEEKLY PLANNING 11/12/2009 Don Lynch.
PHENIX WEEKLY PLANNING 3/6/2008 Don Lynch. 3/6/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
Technical Support /1/08 PHENIX WEEKLY PLANNING 5/1/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/27/2008 Don Lynch. 3/27/2008 Weekly Planning Meeting2 Shutdown ’08 Schedule CM Crane ReviewMar Purge Flammable Gas, Magnet.
PHENIX WEEKLY PLANNING 2/2/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 3/22/2007 Don Lynch. 3/22/2007 Weekly Planning Meeting 2 Schedule Re-Start 5 man shifts 3/20/07 Beam: blue ring 3/8/07, in yellow.
1 3/24/2011 PHENIX WEEKLY PLANNING 3/24/2011 Don Lynch.
PHENIX WEEKLY PLANNING 1/10/2008 Don Lynch. 1/10/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going1/18 Gas.
PHENIX WEEKLY PLANNING 2/9/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
Technical Support /8/08 PHENIX WEEKLY PLANNING 5/8/2008 Don Lynch.
PHENIX WEEKLY PLANNING 12/6/2007 Don Lynch. 12/6/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn GoingOn Going.
PHENIX WEEKLY PLANNING 3/23/06 Don Lynch. MPC Electronics MPC rack installed without cards. Cards to be installed As available and as access time is available.
1 05/07/2009 PHENIX WEEKLY PLANNING 5/07/2009 Don Lynch.
1 3/10/2011 PHENIX WEEKLY PLANNING 3/10/2011 Don Lynch.
PHENIX WEEKLY PLANNING 10/4/2007 Don Lynch. 10/4/2007 Weekly Planning Meeting 2007 PHENIX Shutdown October 2007: Finish MPC South Installation, replace.
PHENIX WEEKLY PLANNING 12/7/06 Don Lynch. 12/7/06 Weekly Planning Meeting 2.
1 12/30/2010 PHENIX WEEKLY PLANNING 12/30/2010 Don Lynch.
1/26/20121 PHENIX WEEKLY PLANNING 1/26/2012 Don Lynch.
1 10/15/2009 PHENIX WEEKLY PLANNING 10/15/2009 Don Lynch.
1 05/21/2009 PHENIX WEEKLY PLANNING 5/21/2009 Don Lynch.
5/12/11 1 PHENIX WEEKLY PLANNING 5/12/2011 Don Lynch.
PHENIX WEEKLY PLANNING 12/27/2007 Don Lynch. 12/27/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn GoingOn Going.
Technical Support /19/08 PHENIX WEEKLY PLANNING 6/19/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/15/2007 Don Lynch. 3/15/2007 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Done All Up Commissioning On Going Re-Start.
PHENIX WEEKLY PLANNING 3/02/06 Don Lynch. BLM Test.
Technical Support /15/08 PHENIX WEEKLY PLANNING 5/15/2008 Don Lynch.
5/24/20121 PHENIX WEEKLY PLANNING 5/24/2012 Don Lynch.
Technical Support /18/08 PHENIX WEEKLY PLANNING 12/30/2008 Don Lynch.
PHENIX WEEKLY PLANNING 5/7/2007 Don Lynch (Thursday is Monday this week)
1 3/31/2011 PHENIX WEEKLY PLANNING 3/31/2011 Don Lynch.
1 12/17/2009 PHENIX WEEKLY PLANNING 12/31/2009 Don Lynch.
PHENIX WEEKLY PLANNING 1/31/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going Switch.
1 1/28/2010 PHENIX WEEKLY PLANNING 1/28/2010 Don Lynch.
1 12/17/2009 PHENIX WEEKLY PLANNING 12/17/2009 Don Lynch.
1 5/19/2011 PHENIX WEEKLY PLANNING 5/19/2011 Don Lynch.
5/30/20131 PHENIX WEEKLY PLANNING 5/30/2013 Don Lynch.
1 1/29/2009 PHENIX WEEKLY PLANNING 1/29/2009 Don Lynch.
1 7/16/2009 PHENIX WEEKLY PLANNING 7/16/2009 Don Lynch.
3/7/20131 PHENIX WEEKLY PLANNING 3/7/2013 Don Lynch.
Technical Support /16/08 PHENIX WEEKLY PLANNING 10/16/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/1/2007 Don Lynch March: in like a lion Out like a lamb.
1 6/4/2009 PHENIX WEEKLY PLANNING 6/4/2009 Don Lynch.
1 7/9/2009 PHENIX WEEKLY PLANNING 7/9/2009 Don Lynch.
PHENIX WEEKLY PLANNING 6/8/06 Don Lynch. 6/8/2006 Weekly Planning Meeting 2 This Week Rec’d TOF West Access: move HBD to Dead Turtle Position Sec’y of.
1 8/20/2009 PHENIX WEEKLY PLANNING 8/20/2009 Don Lynch.
1 2/19/2009 PHENIX WEEKLY PLANNING 2/19/2009 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 2/14/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
1 2/4/2010 PHENIX WEEKLY PLANNING 2/4/2010 Don Lynch.
Presentation transcript:

1 4/2/2009 PHENIX WEEKLY PLANNING 4/2/2009 Don Lynch

2 4/2/2009 Next Maintenance Access Day – April 15 (A Very Taxing Day) - Replaced HBD resistor - RPC noise problems improved significantly with LV filter - Measurements for RPC Installation Done - AC Compressor replaced Ac is good? [for now] - Tunnel scintillator clock problem fixed (fiber swap) Yesterday’s Maintenance Access Day

3 4/2/2009 Tunnel northeast side Some basket tray and a few cables that will need to be moved Tray with a few cables and a couple of pipes that will need to be moved

4 4/2/2009 Crystal Palace needs to be completely removed for installation, modified and reinstalled for run 10 Vapor Barrier to be removed prior to commencing RPC installation. Barrier to be replaced by new thermal insulating wall attached to the existing imbedded unistrut. 80” from MuID steel.

5 4/2/2009 South East corner of IR North East corner of IR. This is most accessible corner 30+” of clearance North West corner of IR South West corner of IR. This is the tightest spot, just 26” of east west clearance

6 4/2/2009 These are the locations where the crane supports could interfere with moving the half octants back and forth for installation purposes. Roughly +/- 7 feet from centerline.

7 4/2/2009 Run Support & Other Ongoing Work Run Technical Support (mech, elec., gas) As needed  always takes priority RPC Factory Support (continuing) (see slides later) Prep for 2009 Shutdown Design PC1 East maintenance support fixtures design 3/31, fabrication 5/31 MMS Scaffolding Design design Done, ordering/fabrication 5/1 RPC3 North installation Prep Installation plan (including inst’n site prep plan) 3/31 Installation fixture design 4/30 Installation fixture fabrication 6/26 Upgrades Support New Beampipe supports (back logged) NCC prototype design support (on-going) VTX fabrication tooling design (on-going) VTX installation design (on-going) FVTX design/eng’g support (no support req’d yet) Maintenance & Overhead Tasks Procedure Review/Updates (ongoing) Rack Room, AH, Trailer, Mixing House, etc. (ongoing) ’09 Technical Support

8 4/2/2009 PC1 East Repair Fixturing Design Repairs to be performed during ’09 Shutdown New Column Supports Under railway extensions New Railway extensions will allow DC to be pulled out ~ 3 feet more Access to PC1 is adequate to remove and replace module Drawings done CS quote is next

9 4/2/2009 MMS scaffolding Designed for MuTr installation. Approved in 2000 for use. Stress analysis done for worst case. Current design has minor modifications. Concept approved at C-A Design Review Bargaining Unit negotiations are next

10 4/2/2009 RPC Factory Support Tasks: Design and order environmental control system for Burn-In Test Stand (in progress) Assemble gap & module storage with humidity control, 1 st humidity control unit received. (assembly in-progress) Assemble tilting transport table (in progress) Assemble burn-in test stand (bike rack) (after TTT complete) Extend gas, electric and safety systems to Burn-In Test Stand (in progress)

11 4/2/2009 RPC Factory

12 4/2/2009 RPC Factory Concept approved at C-A Design Review, with minor corrections Fabrication in progress Tilting Transport Table

13 4/2/2009 RPC Factory Burn In Test Station For Octant and Half Octant Burn-in Tests Mechanical Requirements: Slots for 20 detector units, max. 10 under test and 10 storage Each detector weighs ~ 750 lb Each slot to have 2 rollers Separation between rollers spaced to allow half octant to rest in slot with unit center of gravity mid way between rollers Rollers must be sufficiently close to catch unit before center of gravity passes first roller Concept approved at C-A Design Review waiting in the task queue

14 4/2/2009 RPC 3 North Installation Tooling Concept

15 4/2/2009 Original concept: Separate upper and lower detector supports attached independently to upper and lower I-beams

16 4/2/2009 BNL concept: Single support structure attached at 3 points to west detector sled, 6 degrees of adjustment

17 4/2/ DOF (Y & Z) 1 DOF (Z) 0 DOF Kinematic Mounts for mating east and west detector halves

18 4/2/2009 West detector to be mounted on 2 precision railways. Detector to Railway mounting at 3 points to allow West detector to be aligned in situ to CM. (Note: beampipe is also aligned to CM. CM is aligned to IP. Precision stops to be mounted on both rails to return west half to closed position after opening for maintenance.

19 4/2/2009 Summary of Alignment Concept: CM is aligned to IP, accuracy limited by repeatability is currently ~+/- 2 mm Beampipe is aligned to CM centerline using supports tied to CM through RXNP/Nosecone/FOCAL (expected accuracy ~+/- 0.2 mm) West detector half is aligned to west support structure on bench prior to installation (nominal placement) East detector half is aligned to West detector half on bench prior to installation (accuracy ~+/-.05 mm) West detector half + support structure aligned by survey to CM and around beampipe (accuracy/repeatability TBD) East detector support structure loosely attached (used for parking east half near enough to self align with west half and parking east ½ when halves are separated for maintenance. VTX/FVTX electronics “big wheels” to be hard mounted to west and east support structures. Upper rails to be used for cabling maintenance, plumbing support and cabling strain relief.

20 4/2/2009 New Beampipe PHENIX SCD Brush- Wellman CAP CAP Approval sent to B/W. Quotes rec’d from CS for spools & Transitions

21 4/2/2009 Gas Pad Upgrade & Ar Dewar Additional 20’ x 20’ Pad area for storage of empty gas bottles New Liquid Argon Dewar to meet current and future demand on 16’ x 20’ pad General location as shown, footprint (size) TBD We are preparing a spec package for the additional pad req’ments. New dewar to be leased; supply company to provide requirements for dewar section of pad.

22 4/2/2009 Mixing House thermometers not working properly Roof leaks in utility bathroom at northwest corner behind tech offices and over door between rack room and assembly hall. Trailer bathroom slop sink (for Custodians). Heat wrap tape for trailer bathroom toilet drains to preven freeze/clogging in winter. Improved Rack Room AC performance (This item has been addressed time and again but unsatisfactorily. Currently the AC fails periodically and is repaired only to fail again. On-condition maintenance is not adequate…an engineered solution is needed.) Back bathroom plumbing noise AH slop sink leak Icy conditions at mixing house north stairs 2009 Building Maintenance Issues These items passed on to Fred K.

23 4/2/2009 Shutdown ’09 Major tasks (expect 5 month shutdown): 2009 shutdown Begins June 28 End run, remove wall, MuID collars down, EC to AH (3 weeks) Install Station 1 South scaffolding (1 week) Install Station 2/3 scaffolding (2 weeks) PC1 East repair (4 weeks) Install stations 1, 2 and 3 south MuTrigger FEE’s (12 weeks) MuTr decapacitations: station 3 south (3 weeks) RPC Station 3 North (see next slide) Mechanical/Electrical Plumbing installation of (4) new DCM racks Add Ar Dewar and expand gas pad to add storage (12 weeks) Prep for future upgrades/existing equipment maintenance & Repair (as necessary) Shutdown ’09

24 4/2/2009 RPC3 North Installation Schedule Installation Concept FinalizedMar. 31 Half-Octant Brackets, Connecting Blocks, under detector translating support designMar. 31 Installation Fixturing and Tooling DesignApr. 30 Redesign crystal palace/IR Gas BarrierMay 29 End of Run 9 June 28 Fixturing/Tooling, Brackets/Block/support FabricationJune 30 Move Shielding/Remove Crystal PalaceJune 29-July31 Move cable trays and piping in gap 5June 29-July 31 Simulated (practice) installation with new fixturing/ toolingJuly 13-July 31 Install, level & survey support structure Aug. 3 - Aug 14 Half Octant Testing and Assembly Complete Aug. 17- Sep. 18 (1 st half Octant ready by Aug.17, 16 th by Sep.18) Mechanical Install Align & survey RPC3 N Aug 17 – Sep. 30 Install 3 elect. Racks, all cables & gas systemOct. 1 – Oct. 30 Commissioning Nov. 1 – Nov. 30 Install new crystal palace/IR Gas Barrier & ShieldingNov. 1 – Nov. 30 Start Run 10Dec. 1

25 4/2/2009 Safety, Security, etc. 1. CPR Training for Electrical Safety 1 – Let us know if you need it we’ll set up a class 2. This week’s tier 1 inspection - Any Problems?

26 4/2/2009 Where To Find PHENIX Engineering Info Links for the weekly planning meeting slides, archives of past meeting slides,long term planning, pictures, videos and other technical info can be found on the PHENIX Engineering web site: