The Status of ESS Accelerator Shielding and Accident Scenarios Lali Tchelidze www.europeanspallationsource.se May 26, 2014.

Slides:



Advertisements
Similar presentations
Stefan Roesler SC-RP/CERN on behalf of the CERN-SLAC RP Collaboration
Advertisements

1 Activation problems S.Agosteo (1), M.Magistris (1,2), Th.Otto (2), M.Silari (2) (1) Politecnico di Milano; (2) CERN.
1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007.
Shielding Studies using MARS Monte Carlo code Noriaki Nakao (SLAC) Jan. 6, 2005, WORKSHOP Machine-Detector Interface at ILC, SLAC.
C. Theis, D. Forkel-Wirth, S. Roesler, H. Vincke.
UCN Phase 2 Design Status September 10, Design Components Bulk Shielding Target Crypt Cryogenic Insert Target Insert UCN Port Beam Window Cooling.
BROOKHAVEN SCIENCE ASSOCIATES Radiological Design Considerations of Synchrotron Radiation Facilities P.K. Job Radiation Physicist National Synchrotron.
ALPHA Project Safety Assessment Document Vladimir Anferov.
Lali Tchelidze Safety work package leader
Shielding calculation for ESS accelerator Lali Tchelidze TAC meeting April 2, 2014.
ELI-NP: the way ahead, March Anna Ferrari An overview of the shielding problems around high energy laser-accelerated beams Anna Ferrari Institute.
J. G. Weisend II Deputy Head of Accelerator Projects April 2, 2014 Actions at ACCSYS Resulting from the Recommendations of the Annual Review.
First AWAKE dump calculations Helmut Vincke. Beam on dump Muon axis inside and outside CERN Distances: Beam impact point to end of West hall: ~300 m Beam.
Highlights of RP activities in support of ISOLDE operation and projects Joachim Vollaire, Alexandre Dorsival and Christelle Saury with material from others.
Thickness of the Kamaboko Tunnel Shield Wall under Different Assumptions Ewan Paterson Technical Board June 23,
Radiation safety evaluation for “KAMABOKO” Main Linac Tunnel KEK-APL : T.Sanami, S.Ban KEK-ACC : A.Enomoto, M.Miyahara ILC Mechanical & Electrical Review.
PSB dump: proposal of a new design EN – STI technical meeting on Booster dumps Friday 11 May 2012 BE Auditorium Prevessin Alba SARRIÓ MARTÍNEZ.
SiriusUVX LNLS – National Synchrotron Light Laboratory CNPEM – Brazilian Center for Research on Energy and Materials A R Rodrigues, M Lisboa, R Madacki.
F. Regis, LINAC4 – LBS & LBE LINES DUMP DESIGN.
Managed by UT-Battelle for the Department of Energy Residual Does Rate Analyses for the SNS Accelerator Facility I. Popova, J. Galambos HB2008 August 25-29,
Operated by Los Alamos National Security, LLC for NNSA Slide 1 LANL Proposal for Hazard Assessment Beam Spill Criteria Charles Kelsey, Mike Baumgartner,
First radiological estimates for the HIRADMAT project H. Vincke and N. Conan 1.
Radiation Protection aspects for SHIP Doris Forkel-Wirth, Stefan Roesler, Helmut Vincke, Heinz Vincke CERN Radiation Protection Group 1 st SHIP workshop,
Activation around dump shielding, and design of beam line mask Mathieu Baudin, RP Genevieve Steele, EN-STI Helmut Vincke, RP.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS2 Bulk Shielding calculations Methodology P.K. Job Radiation Physicist Peer Review 2007 March 27, 2007.
Risk Analysis P. Cennini AB-ATB on behalf of the n_TOF Team  Procedure  Documents in preparation  Conclusions Second n_TOF External Panel Review, CERN,
Overview of HINS Operations and Radiation Shielding Considerations in the Meson Detector Building Bob Webber August 16, 2006.
Considerations for an SPL-Beamdump Thomas Otto CERN in collaboration with Elias Lebbos, Vasilis Vlachoudis (CERN) and Ekaterina Kozlova (GSI) Partly supported.
1 BROOKHAVEN SCIENCE ASSOCIATES Summary of Shielding Calculations for NSLS2 Accelerators P.K. Job Radiation Physicist Peer Review 2007 March
1 Neutron Effective Dose calculation behind Concrete Shielding of Charge Particle Accelerators with Energy up to 100 MeV V. E Aleinikov, L. G. Beskrovnaja,
Radiation Shielding Assessment for MuCool Experimental Enclosure C. Johnstone 1), I. Rakhno 2) 1) Fermi National Accelerator Laboratory, Batavia, Illinois.
Radiation protection and radiation safety issues for HIE-ISOLDE. FLUKA calculations Y. Romanets ISOLDE Workshop and Users meeting 2010 CERN, 8 December.
Radiation Protection studies for the Linac4 / Linac2 interface Joachim Vollaire, DGS-RP 28/09/2015 Linac4 Coordination Meeting.
Radiation Protection and Radiation Safety for Particle Accelerator Facilities J. Vollaire, Radiation Protection Group CERN Compact Accelerators for Isotope.
1 Radiation Monitoring at CTF3 CTF3 Buildings – weak spots Radiation Monitoring system Monitoring results – First Lessons Idelette Floret, Thomas Otto,
Radiation Protection Considerations for the CDR Helmut Vincke DGS-RP.
AWAKE: D2E for Alexey beam properties Silvia Cipiccia, Eduard Feldbaumer, Helmut Vincke DGS/RP.
Summary of radiation shielding studies for MTA Muon production at the MiniBooNE target Igor Rakhno August 24, 2006.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Shielding Workshop R. Casey Activation Issues for NSLS-II March 28, 2007.
Ma zhongjian Ding yadong Wang qingbin Wu qingbiao Radiation Protection Group/IHEP.
Personnel Safety Systems Stuart Birch Senior Engineer, Personnel Safety Systems November 6 th, 2014.
Design for Radiation Shielding of PAL X-ray Free Electron Laser
EURISOL DS Task meeting Orsay, 07 Janvier Preliminary shielding assessment of EURISOL Post Accelerator D. Ene, D. Ridikas. B. Rapp.
Safety - Lessons learnt from the design, commissioning and operation of the HIE-ISOLDE cryomodules Safety overview ESS 8 June 2016 AP.Bernardes/EN on behalf.
SuperB Integration SuperB Experimental hall. Related topics of Slac D&D activities.
Neutron double differential distributions, dose rates and specific activities from accelerator components irradiated by 50 – 400 MeV protons F. Cerutti.
Dark Current in ILC Main Linac N.Solyak, A.Sukhanov, I.Tropin ALCW2015, Apr.23, 2015, KEK LCWS'15, Tsukuba, 04/2015Nikolay Solyak1.
EURISOL, TASK#5, Bucuresti, November 1 Preliminary shielding assessment of EURISOL Post Accelerator D. Ene, D. Ridikas. B. Rapp.
1 How Many Protons can we afford to loose in the PS ? Thomas Otto SC-RP.
Activation by Heavy-Ion Beams
Dark Current and Radiation Shielding Studies for the ILC Main Linac
Primary Radiation Calculation for Sun Yat-Sen Proton Hospital
MARS15 Simulation of Radiation Environment at the ESS Linac
Induced-activity experiment:
S. Roesler (on behalf of DGS-RP)
Measurements and FLUKA Simulations of Bismuth and Aluminum Activation at the CERN Shielding Benchmark Facility(CSBF) E. Iliopoulou, R. Froeschl, M. Brugger,
Desirable BCM Performance
Radiation protection of Linac4 M. Silari Radiation Protection Group
TI8/WIC Incident & UJ87/UA87 Radiation Levels & Analysis
CLIC Civil Engineering Update
Estimation and Protection on Synchrotron Radiation in CEPC Main Ring
Vashek Vylet RadCon Manager UITF Internal Safety Review May 10, 2016
Andreas Jansson, Lali Tchelidze
Operations Section Leader
Preliminary Hazard Analysis of Bunker
Radwaste: status & way forward
Shielding requirements for the baseline bunker shielding (current CATIA version ) Günter Muhrer
Radiation fields During 1st stage beam commissioning
Vashek Vylet, RadCon UITF Conduct of Operations Review April 24, 2019
CEPC Radiation and Shielding
Presentation transcript:

The Status of ESS Accelerator Shielding and Accident Scenarios Lali Tchelidze May 26, 2014

Outline Prompt radiation shielding design criteria. Accidental cases. Shielding results (with an attention to earth berm shielding on top of the linac). – Skyshine radiation. Conclusions. 2

November 2013 Review Recommendations related to beam loss and shielding : ”Basic assumption of 1 W/m used for shielding calculations needs to be confirmed by realistic end-to- end beam simulations, showing sufficient margin. Normal operations scenario should include accidental beam loss scenarios.” “Accidental beam loss: need to establish “worst case” scenarios based on risk analysis and to conduct simulations to determine appropriate shielding and system interlocks for personnel protection.” 3

Event classes and exposure limits at ESS Frequency (1/y)NameLimit to rad workersLimit to public H1> 1Normal operation10 mSv/y0.05 mSv/y H Anticipated events20 mSv/event0.5 mSv/event H Unanticipated events50 mSv/event5 mSv/event H Design basis accident (DBA) 50 * mSv/event20 mSv/event 4 * Used to be 100 mSv, until SSM (Swedish Radiation Safety Authority) asked to reduce the limit.

Normal operation H1 Limit is driven by requirements for activation/hands-on maintenance limits. Adopt 1 W/m (SNS specification above 100 MeV) – dose rates below ~1 mSv/h measured at 30 cm from component surface for 100 day/4 hour irradiation/cooling condition. 1.1 mSv/h At 30 cm 1 W/m 1 GeV protons on beam pipe 100 days/4 hours. FLUKA simulations from I. Strasik et al., Phys. Rev. ST AB 13,

Anticipated events H2 Adopt 30 MJ beam spill (LANSCE design criterion) – A burn through at LANSCE at 800 MeV proton coupled cavity linac occurred with an estimated 40 J of beam spill. – At PSI, at 600 MeV proton beam experience showed that leak at vacuum seal occurred at deposited energies of 30 kJ. – TJNAF (Thomas Jefferson National Accelerator Facility), 10 MJ energy spill. – No spill events greater than 10 MJ were identified! 6

Beam Spill Limits Summary Comparing (accidents) LANSCE 1.7 mSv/MJ TRIUMF 2.2 mSv/MJ SLAC 0.6 mSv/MJ ESS 0.08 mSv/MJ Frequency (1/y)NameDescriptionExposure limit > 1Normal operation1 W/m10 mSv/y – 1Anticipated events30 * MJ/event20 mSv/event – Unanticipated events 150 * MJ/event50 mSv/event – Design basis accident (DBA) 600 * MJ/event50 mSv/event 3 μSv/h for normal operation 7 * LANSCE design criterion

Accident duration as a function of lost beam power 8

Outcome of the recommendations 1.Beam spill limits for all event classes H1 – H4 (normal operations – incidents of various types) – ESS “Beam Spill Limits for Various Event Classes”. – ESS “Hands-on Maintenance Conditions at ESS Accelerator”. Both documents reviewed and approved at SAG. Final step – get an approval at EPG – Scheduled for 2/6/2014. – This will close this recommendation. 9

Tools used Verifying that 5 m earth berm shielding is sufficient for all types of events. – Analytical approach. – Monte-Carlo simulations code MARS. 10

Normal operation 1 W/m “Sullivan”-s analytic approach Lateral shielding for 1 W/m beam loss. – H=(H 0 /R) exp(-t/0.94λ) – H 0 is a source term, representing a dose equivalent per interacting proton, at 1 m from the interaction point and no attenuation, equals to 0.4 Sv/h. – λ is a hadron attenuation mean free path – t is a thickness of a shield – R is a distance from beam loss to outside of the shield. 5 m earth berm – 0.26 μSv/h (limit is 3 μSv/h). 11

Normal operations 1 W/m Monte-Carlo simulations Geometry: – Linac tunnel, tunnel walls and earth berm around it. – Klystron gallery building. – Waveguide penetrations. – Cable penetrations. – Personal emergency exits. – HEBT loading bay. – Smoke evacuations. – Alignment penetrations. – Cryogenic transfer line. 12

Earth berm thickness Normal Operation 5 m earth berm - max 8 μSv/h (limit is 3 μSv/h) Berm will be fenced! -Linac length – 450 m. -Proton beam energy 5 MeV – 2 GeV. -Loss distribution: 1 W/m upwards at 3 mrad angle on a 2 mm stainless steel beam pipe. -Tunnel concrete roof thickness – 70 cm. 13

Accidents – Analytical solution -Point beam loss is considered: -H=H 0 /R 2 e(-t/λ) -H 0 is a source term, representing a dose equivalent per interacting proton, at 1 m from the interaction point and no attenuation, equals to 1.2 Sv/h. -λ is a hadron attenuation mean free path -t is a thickness of a shield -R is a distance from beam loss to outside of the shield. -5 m earth berm μSv/MJ max dose rate outside of earth berm. -Equivalent to 0.31 Sv/h for full point beam loss. 14

Accidents – Monte-Carlo results -Point beam loss upwards with a shallow angle at 2 GeV proton beam energy μSv/MJ max dose rate outside of earth berm. -Equivalent to 2.3 Sv/h for full point beam loss. DET (mSv/h) Side view 15

Shielding results - summary NameDescriptionWith 5 m berm (Anal.) With 5 m berm (MC) Exposure limit Normal operation 1 W/mNo limit1250 h limit10 mSv/y Anticipated events 30 MJ/event0.5 mSv/event3.8 mSv/event 20 mSv/event Unanticipated events 150 MJ/event2.6 mSv/event19.2 mSv/event 50 mSv/event Design basis accident (DBA) 600 MJ/event10.3 mSv/event76.8 mSv/event 50 mSv/event No Access on top of berm during operation! 16

Earth berm thickness Current observations. -From the accidental prompt dose rate consideration point of view: -The top of the berm has to have no access during operations! -Or the amount of earth berm thickness has to be increased. 17

Skyshine Close to public limit (5.7 nSv/h or 50 µSv/y) at the site boundary. Skyshine radiation around ESS site (contribution from the linac, excluding the A2T, 2013) 18

Earth berm thickness Current observations. -From the accidental prompt dose rate consideration point of view: -The top of the berm has to have no access during operations! -Or the amount of earth berm thickness has to be increased. -From the skyshine prompt dose rate consideration point of view: -The amount of earth berm thickness might need to be increased. -We are building an accelerator tunnel allowing placement of up to 7 meters of earth berm on top of it if necessary! 19

Preliminary to detailed shield design -Things that affect the final shielding configuration: -Level of details in the geometry description. -Accelerator component and shield material - material’s composition. -Beam loss assumptions. -We expect the total berm thickness to decrease in the detailed design stage, but as a back-up strategy we have a possibility of increasing the thickness to 7 meters. 20

Sensitivity to linac components (Example) DET (mSv/h) Side view across the tunnel. 2 mm stainless steel 20 cm copper A factor of 5-10 less total dose equivalent outside of berm shielding when a bulk copper is considered! 21

Shielding towards the klystron gallery DET (mSv/h) Top view at 2 m < 0.1 µSv/h with no penetrations. 54 µSv/h max – with penetrations and no extra shield. 3 µSv/h max – with penetrations and extra shield block. Equivalent to 28.8 mSv/event for DBA (limit – 50 mSv). 22

Outcome of the recommendations 1.Beam spill limits for all event classes H1 – H5 (normal operations – incidents of various types) – ESS “Beam Spill Limits for Various Event Classes”. – ESS “Hands-on Maintenance Conditions at ESS Accelerator”. Both documents reviewed and approved at SAG. Next/final step – get an approval at EPG. 2.Shielding reports. Normal operations: Technical note ESS “ESS Linac Shielding Strategy and Calculations” – reviewed and approved internally and externally (March, 2013). Accidental cases: Technical note ESS ” Earth berm shielding for accidental beam losses” – reviewed internally. 23

Summary Recommendation about establishing accident scenarios and assigning beam spill limits to them. (ESS & ESS ) Recommendation about verifying that the earth berm shielding is enough for accident scenarios. (ESS & ESS ) 24

Thank you!