1 Rehabilitation of 188 th Street over Grand Central Parkway PIN: X051.63.121 Contract #: D262985 Deck Replacement October 2015.

Slides:



Advertisements
Similar presentations
Replacement of the Queens Approach Bronx-Whitestone Bridge
Advertisements

Gordons Corner Road Over US Route 9 Mahesh Patel, P.E. George Afful, P.E. Gregory Bitsko, P.E.
Projects in the Forest Grove area Presented by: David Kim, ODOT Metro West Area Manager August 13, 2012.
SR Lititz Pike Bridge Replacement Note: Dates indicated in this presentation are estimated based on the contractors current schedule and does.
Caltrans, District 11 LAUREL STREET OVERCROSSING 1/16/2014.
1 1 Pre Bid Conference JGB Lobby Level Meeting Room December 12, :00 am IFB FQ12210 Rehabilitation of Parking Garages at Vienna (South), Southern.
Highway 61/147th Street Intersection Business Meeting April 20, 2010.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION I-390 Interchange Improvements Design-Build Project (PIN ) City of Rochester & the Town of Brighton,
ROUTE 72 BRIDGE IMPROVEMENTS TP 708 Pre-Proposal Meeting May 2, 2008.
DDI Traffic Informational Session Town of Cornelius Lake Norman Chamber of Commerce June 11, 2014.
Fill in Agency Name on Master
Maryland State Highway Administration Office of Structures Maryland State Highway Administration Office of Structures West Nursery Road over MD 295 (Baltimore-
Bridge over BNSF Railroad 7 km East of Windham - East Bridge Replacement Project Using Accelerated Bridge Construction.
Lander Streets and Utilities 2015 Public Meeting No. 2 McDougall & Cliff Project Area.
Dillon and Christina Project Area Lander Streets and Utilities 2015 Public Meeting No. 2.
Route 50 Widening Design/Build Project. 2  Virginia Department of Transportation  Shirley Contracting Company  Dewberry  Fairfax and Loudoun Counties.
New York State Department of Transportation Kendrick Road Bridge Over I-390 Design-Build Project Request for Qualifications Informational Meeting June.
Newmarket Viaduct Replacement STAGED VIADUCT CONSTRUCTION / DECONSTRUCTION PROCESS PROJECT DELIVERY BY NGA NEWMARKET.
75 Express Lanes Segment D Construction From South of Sheridan Street to North of Griffin Road Presentation to Ivanhoe Community August 27, 2014.
Water Quality Improvements Riverglen Subdivision Valve Replacements April 4, 2013.
Design/Build Team for the US 36 Express Lanes Project.
3 June Rapid Replacement of the Hood Canal Bridge Approach Spans Joseph Merth, P.E. Bridge Design Engineer 3 June 2008.
Presentation to Maxwell Place Homeowners Association 1.
1 WELCOME TO PRE-PROPOSAL CONFERENCE ON RFP FOR REI SERVICES CONTRACT HBCR00A FOR COMPONENT REHABILITATION OF TWELVE BRIDGES CITYWIDE NYC DEPARTMENT OF.
Reconstruction of the Eads Bridge Highway Deck
Clinton Street Bridge over the Maumee River ODOT Project DEF December 2, 2014 Stakeholder’s Meeting.
ROUTE 7 TRAFFIC FLOW IMPROVEMENTS POTOMAC VIEW ROAD TO AUGUSTA DRIVE LOUDOUN COUNTY DEPARTMENT OF CONSTRUCTION AND WASTE MANAGEMENT A. MORTON THOMAS &
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Region 1 Traveler Information on 2010 Construction Route 7 over I-87 (Exit 6) Bridge Replacement Town of Colonie.
Clinton Street Bridge over the Maumee River ODOT Project DEF April 1, 2015 Stakeholder’s Meeting.
Pedestrian OC Does Not Cross Amador St 1 Safety Issues Riverside Elementary School Amador St.
Route 28 South of I-66 Corridor Safety and Operations Study Technical Committee Meeting #2 June 25,
Bridge Rehabilitation W Interstate 290 over CSX Railroad and 4 City Streets I-290 Viaduct Reconstruction.
ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)
4 TH STREET BRIDGE Pueblo, Colorado December 2006 Project Overview.
Public Information Meeting Rehabilitation of Bridge No Flat Rock Hill Road over I-95 Old Lyme, Connecticut Rehabilitation of Bridge No Flat.
Clinton Street Bridge over the Maumee River ODOT Project DEF May 14, 2015 Public Meeting.
Page 1 MINISTRY OF TRANSPORTATION Cyrville Road Bridge Replacement at Highway 417 (Ottawa Queensway) Detail Design Study Group Work Project
Enosburg BRO 1448(40) Bridge 48 on TH 2 Over the Tyler Branch Alternatives Presentation.
St Johnsbury BF 7000(20) Bridge 6 on VT Route 2B over the Lamoille Valley Rail Trail Presenter: John Byatt, PE Consultant Project Manager.
STATE ROUTE 1 ALAMITOS BAY BRIDGE IMPROVEMENT PROJECT SCOPING MEETING AUGUST 5, :00 p.m.Open House 6:30 p.m.Presentation 7:00 p.m.Public Comment.
Roosevelt Road: State to Columbus Public Meeting September 22, 2015.
Office of Traffic, Safety and Technology Module 4 Work Zone Applications Traffic Control Plan Development Course.
Enosburg BRO 1448(40) Bridge 48 on TH 2 Over the Tyler Branch Public Information Meeting.
I-495 NORTHERN SECTION SHOULDER USE PROJECT State Project No , P101, C501 CITIZEN’S INFORMATION MEETING UPC NOVEMBER 19, 2013.
September 15, 2011 Presented by: Clay Harris, PMP - City of Austin Federico Mendoza, PE, PTOE – Brown & Gay Engineers, Inc. Todd Lane Alternative Geometric.
VT 100 over the Mad River Bridge Replacement July 13, 2015.
US 36 Commuting Solutions Northwest Rail Westminster Segment/Eagle P3 Oct. 14, 2014.
Route 1 Olden Avenue & Mulberry Street Hyperbuild Project.
SFOBB East Span Seismic Safety Project San Francisco-Oakland Bay Bridge East Span Seismic Safety Project March 12, 2002 Contractor Outreach.
Grand Valley Metropolitan Council March 3, 2016 Erick Kind Region Engineer MDOT-Grand Region.
I-5/Genesee Avenue Interchange Project. Project Purpose Improve east and west traffic flow on Genesee Ave. Enhance access to and from I-5 Replace and.
GEORGE WASHINGTON HIGHWAY WIDENING PROJECT E.V. WILLIAMS, INC.
Public Information Meeting St. George Road - Oak Hill Road Intersection Reconstruction Project.
Project Purpose and Objective
Aaron Crowley, Ph.D. KSWA Travis Smith, P.E. TDOT Biloxi, Mississippi
Project Headlands, Phases 1 and 2
New Bridge Construction
Board of Commissioners Meeting
Safety Tip FQ18086 RHODE ISLAND AVENUE METRO STATION TRACK DECK AND PRE-CAST PANEL REHABILITATION Please use full fall Protection gear when using 6’ or.
Highway 169 Bridge Replacement & Pavement Resurfacing
The Construction team appreciates this opportunity to discuss the work that will begin in October on State Road 397 over Toms Bayou. My name is Mike Sasser,
Coffee & Construction Developer Meeting
Contract 60X10 Informational Meeting Weber I-55
Work Hours: Monday – Saturday, 5:00 a.m. – 3:30 p.m.
Harbour Island Force Main Replacement
Utility Relocation: 11th/Mill
Naval Complexes Meeting April 15, 2019
Access Hatch Replacement Phase 4
Access Hatch Replacement Phase III
Presentation transcript:

1 Rehabilitation of 188 th Street over Grand Central Parkway PIN: X Contract #: D Deck Replacement October 2015

2 188 th Street Bridge over Grand Central Parkway Elevation (Looking West) Top of Bridge (Looking North)

3 Existing Bridge Cross-Section - (Looking North) Built in ’ wide x 193’ long 4 simple spans 12 steel girders 2 lanes in each direction ’ wide sidewalks Has two (2) watermains under the southbound sidewalk Carries multiple electrical and telephone conduits Project Goal: Replace the deteriorated concrete deck with a new deck which will extend the useful life of the structure for 30+ years

4 Accelerated Bridge Deck Construction Pre-Cast Deck Panel  The accelerated bridge deck construction uses pre-cast deck panels (cast off site) which are placed on the bridge over four weekends during the summer, when traffic on the bridge is reduced.  One sidewalk will be open to pedestrians at all times.

5 Accelerated Bridge Deck Construction (Stage 1) 3 MONTH DURATION WORK ZONE 188 TH STREET SIDEWALK OPEN 2 LANES NORTHBOUND 2 LANES SOUTHBOUND SIDEWALK CLOSED  Work will include bearing replacement, substructure repairs, steel repairs and Verizon utility repairs as well as the installation of the East sidewalk panels.  The west sidewalk will remain open to pedestrians.  All four (4) lanes will remain open to traffic. Temporary off-peak lane closures.

6  Work will include replacement and installation of roadway deck panels in the Northbound direction.  The West sidewalk will remain open and traffic will be reduced to one lay in each direction during the two weekend closure periods. Lane reduction hours are from Friday 10 PM thru Monday 5 AM.  All four lanes of traffic will be open between weekend closures.  Traffic Enforcement Agents will be present from 9 PM Friday thru 6 AM Monday for the weekend closures. WORK ZONE WEEKENDS #1 and #2 Accelerated Bridge Deck Construction (Stages 2 & 3) 188 TH STREET 1 LANE SOUTHBOUND 1 LANE NORTHBOUND SIDEWALK CLOSED SIDEWALK OPEN 3A 2A

7  Work will include replacement and installation of roadway deck panels in the Southbound direction.  The west sidewalk will remain open and traffic will be reduced to one lay in each direction during the two weekend closure periods. Lane reduction hours are from Friday 10 PM thru Monday 5 AM.  All four lanes of traffic will be open between weekend closures.  Traffic Enforcement Agents will be present from 9 PM Friday thru 6 AM Monday for the weekend closures. WEEKENDS #3 and #4 Accelerated Bridge Deck Construction (Stages 4 & 5) WORK ZONE 188 TH STREET 1 LANE SOUTHBOUND 1 LANE NORTHBOUND SIDEWALK CLOSED SIDEWALK OPEN 4A 5A

8 Accelerated Bridge Deck Construction (Stage 6) 188 TH STREET 2 LANES NORTHBOUND 2 LANES SOUTHBOUND SIDEWALK CLOSED SIDEWALK OPEN  Work will include replacement of the West sidewalk and water main.  The east sidewalk will remain open during this stage.  All four (4) lanes will remain open to traffic. Temporary off-peak lane closures.  Traffic Enforcement Agents will be present from Monday to Friday (daytime). WORK ZONE 3 MONTH DURATION

9 Accelerated Bridge Deck Construction 8 Months: Preliminary Work Work performed on underside of bridge Lane closures only on Grand Central Parkway 3 Months: Stage 1 Northbound sidewalk closure on 188 th St. No reduction of traffic lanes during peak hours. Temporary off-peak lane closures. Southbound sidewalk remains open 4 Weekends of Lane Reductions over 2 Summer Months: Stages Two lanes and one sidewalk closure on 188 th Street each weekend for 4 weekends One lane in each direction will be maintained during weekend closures Alternate routes will be in place with use of traffic enforcement agents to facilitate traffic flow 3 Months: Stage 6 Southbound sidewalk closure on 188 th St. Replace watermains beneath bridge under Southbound sidewalk Northbound sidewalk remains open No reduction of traffic lanes during peak hours. Temporary off-peak lane closures. 2 Months: Miscellaneous Work Miscellaneous items – lighting, striping, painting during off peak closures Site restoration TOTAL DURATION FOR DECK REPLACEMENT: 2 MONTHS TOTAL DURATION OF 188 TH STREET TRAFFIC IMPACTS: 4 WEEKENDS

10 Accelerated Bridge Deck Construction Summary Total duration for roadway deck replacement: 2 months Total duration for 188 th Street traffic impacts: 4 summer weekends Overall construction duration reduction of 6-7 months over conventional construction Lane closures on 4 summer weekends – Two lanes in each direction will be reduced to one lane in each direction – Alternate routes will be in place with the use of traffic enforcement agents to facilitate traffic control – Weekdays between weekend closures all lanes and sidewalks will be opened 20% additional construction cost over conventional cost Minimum of one sidewalk on the bridge open at all times

11 Current Schedule Construction Contract Letting: October 2015 Construction Contract Award: December 2015 Construction Completion April 2017 Contact Information: New York State Department of Transportation Mr. James Romanovsky, P.E. (718)