Giovanni Polese1 RPC Detector Control System for MTCC Pierluigi Paolucci, Anna Cimmino I.N.F.N. of Naples Giovanni Polese Lappeenranta University.

Slides:



Advertisements
Similar presentations
JCOP FW Update ALICE DCS Workshop 6 th and 7 th October, 2005 Fernando Varela Rodriguez, IT-CO Outline Organization Current status Future work.
Advertisements

The Control System for the ATLAS Pixel Detector
SPD DCS Status Report Ivan Amos Calì a,b, S.Ceresa a,c, C.Torcato de Matos a a CERN-AIT a CERN-AIT b Università degli studi di Bari b Università degli.
P. Paolucci - I.N.F.N. di Napoli / Joint RPC-Trigger meeting HV-LV-DCS Status DCS barrel:G. Polese and P. Paolucci DCS endcap:A. Cimmino and.
Il sistema di HV del sottorivelatore DT S. Braibant, P. Giacomelli, M. Giunta, E. Borsato Bologna, 20/01/2007.
P. Paolucci - I.N.F.N. di Napoli / Joint RPC-Trigger meeting EASY Crate board/cratechannel/crate (max power) power/crate# crate/rackpower/rack#
Detector Control System at the GIF++ A. Polini, M. Romano (AIDA+INFN Bologna) on behalf of WP group Gif++ User Meeting 11/07/2014 Outline Status.
RPC Trigger Software ESR, July Tasks subsystem DCS subsystem Run Control online monitoring of the subsystem provide tools needed to perform on-
HV for SM surface testing 2 nd Workshop on the Detector Control System for TRD University of Tsukuba Kengo Watanabe.
A. Cimmino - P. Paolucci - G. Polese / DCS meeting DQM tool for the DCS data What the RPC community needs: 1.Make online/offline DCS data.
Calo Piquet Training Session - Xvc1 ECS Overview Piquet Training Session Cuvée 2012 Xavier Vilasis.
RPC Readiness for Data-taking RPC Collaboration 1.
MDT PS DCS for ATLAS Eleni Mountricha
Clara Gaspar, October 2011 The LHCb Experiment Control System: On the path to full automation.
XXVI Workshop on Recent Developments in High Energy Physics and Cosmology Theodoros Argyropoulos NTUA DCS group Ancient Olympia 2008 ATLAS Cathode Strip.
ATLAS MDT Power Supply DCS Anastasios Iliopoulos 15/08/2006.
P. Paolucci - I.N.F.N. di Napoli 1 MTCC meeting May 06 HV & LV status DELIVERED AT BLG /60  67% of the A3009 (LV) 6/40  15% A3512N (HV) 10/10 
ALICE DCS Meeting.- 05/02/2007 De Cataldo, Franco - INFN Bari - 1 ALICE dcsUI Version 3.0 -dcsUI v3.0 is ready and will be soon posted on the ACC site.
Controls EN-ICE Finite States Machines An introduction Marco Boccioli FSM model(s) of detector control 26 th April 2011.
1 Outline Firmware upgrade of the HV_LED_DAC boards. HV Status Bits board. Status of the board integration into the LHCb TFC system. CALO HV system and.
1 ECS CALO HV Control CALO Piquet Training Session Anatoli Konoplyannikov /ITEP/ Outline  ECS HV control of the ECAL/HCAL sub-detectors.  Introduction.
André Augustinus 16 September 2002 PVSS & Framework How to get started.
1 Status and Outlook of the RPC Commissioning Marcello Maggi/INFN-Bari.
Bruno Belbute, October 2006 Presentation Rehearsal for the Follow-up meeting of the Protocol between AdI and CERN.
CERN, O.Pinazza: ALICE TOF DCS1 ALICE TOF DCS Answers to DCS Commissioning and Installation related questions ALICE week at CERN O. Pinazza and.
FOPI – Slow Control Content 1.FOPI experiment - Overview 2.GUIs for FOPI 3.System Design.
RPC DQM status Cimmino, M. Maggi, P. Noli, D. Lomidze, P. Paolucci, G. Roselli, C. Carillo.
DT Shifter Training Infrastructure A. Benvenuti, M.Giunta 07/07/2010.
CMS ECAL DCS 10.Oct S.Zelepoukine ICALEPCS CMS ECAL DCS 1 The Detector Control System for the Electromagnetic Calorimeter of the CMS Experiment.
P. Paolucci - I.N.F.N. of Napoli 1 RPC workshop, 2 march 07 RPC Power system P. Paolucci, G. Polese and D. Lomidze I.N.F.N. di Napoli.
P. Paolucci - I.N.F.N. di Napoli / Joint RPC-Trigger meeting EASY Crate board/cratechannel/crate (max power) power/crate# crate/rackpower/rack#
Clara Gaspar, April 2006 LHCb Experiment Control System Scope, Status & Worries.
1 ECS CALO HV Control CALO Piquet Training Session Anatoli Konoplyannikov /ITEP/ Outline  ECS HV control of the ECAL/HCAL sub-detectors.  Introduction.
S.Sergeev (JINR). Tracker consists of  4 stations of 4 views (planes) each In total ~7200 drift tubes (~450 per view) To be controlled/monitored 
T0 DCS Status DCS Workshop March 2006 T.Karavicheva on behalf of T0 team.
22/May/02 JCOP meeting G. De Catatldo-A.Franco INFN Bari Italy 1 The Control System of the HMPID up to the end of 2001 ; 2002: The FSM toolkit, Hierarchy.
DCS Meeting - 17/6/2002 G. De Cataldo, A.Franco - INFN Bari - 1 The implementation of the HMPID DCS in the PVSS-JCOP Framework The Liquid Circulation and.
JCOP Framework and PVSS News ALICE DCS Workshop 14 th March, 2006 Piotr Golonka CERN IT/CO-BE Outline PVSS status Framework: Current status and future.
20OCT2009Calo Piquet Training Session - Xvc1 ECS Overview Piquet Training Session Cuvée 2009 Xavier Vilasis.
Detector Control System
09/02/2006 Muon week HV and LV systems status for Magnet Test S. Braibant, P. Giacomelli, M. Giunta.
ATLAS MDT HV – LV Detector Control System (DCS)
RPC Barrel HV & LV system Lappeenranta University
HV & LV status LV system in W+1 and W+2 is OK
RPC Configuration DataBase Pierluigi Paolucci - I.N.F.N. of Naples.
Pierluigi Paolucci - I.N.F.N. Naples
Pierluigi Paolucci - I.N.F.N. Naples
RPC Manufacturing Review - Pierluigi Paolucci - I.N.F.N. Napoli
Pierluigi Paolucci - I.N.F.N. Naples
RPC HV&LV status Introduction HV power supply tender
23 Barrel chambers and 12 Endcap chambers
HV Imon in 1th MTCC period
RPC Detector Control System
RPC Detector Control System
RPC Detector Control System
HV-LV-DCS Status NEWS DCS Endcap Integration
RPC Detector Control System
Pierluigi Paolucci & Giovanni Polese
Pierluigi Paolucci & Giovanni Polese
RPC Detector Control System: towards the final system
RPC Detector Control System
HV & LV status LV system in W+1 and W+2 is OK
RPC Detector Control System
HV & LV status DELIVERED AT BLG /60  67% of the A3009 (LV)
Pierluigi Paolucci & Giovanni Polese
Pierluigi Paolucci & Giovanni Polese
Pierluigi Paolucci & Giovanni Polese
RPC Configuration DataBase Pierluigi Paolucci - I.N.F.N. of Naples.
23 Barrel chambers and 12 Endcap chambers
Pierluigi Paolucci & Giovanni Polese
Presentation transcript:

Giovanni Polese1 RPC Detector Control System for MTCC Pierluigi Paolucci, Anna Cimmino I.N.F.N. of Naples Giovanni Polese Lappeenranta University

Giovanni Polese2 Hardware Structure BARREL 1 Mainframe 2 branch 2 LV Easy 1-2 HV Easy 3 LV Boards ( 1 per sector) 4 HV Boards (8 ch. for sector) The final Hardware configuration for MTCC has been upload into PVSS, using the barrel hardware already delivered and tested at 904 ENDCAP 1 branch 1 LV Easy 1 LV boards 2-4 HV boards

Giovanni Polese3 FSM Hierarchy structure Endcap RPC Endcap Supervisor Disc Ring Chamber Barrel RPC Barrel Supervisor Device level Wheel Sector Chamber Channel HV/LV Sys CMS_RPC The Endcap and Barrel have two different tree structures under a single top node as required by the CMS DCS Integration guidelines. This two systems can still work completely in standalone. The endcap is up to date with the barrel and the two systems are proceeding in parallel A branch in both system trees describes the hardware view. The system is now divided in 3 parts and spitted in 2 PCs on a distributed network, as required into guidelines. Device level Channel HV/LV Sys NEW LEVEL CU LU PC01 PC02..03

Giovanni Polese4 RPC System for MTCC

Giovanni Polese5 Sector & Ring Trending Plot A set of history plot panels allow to follow the evolution of the main chamber parameters. Different history panels for HV and LV For every plot it’s possible to change axis, zoom, freeze and export the data in cvs

Giovanni Polese6 Hardware view Available from the top node Show a complete mapping of all crates connected to every branch controllers Historical plot allows to see the temperature evolution for every boards in the crates Clicking on each board it’s possible to see board details and the logic channels name

Giovanni Polese7 Configuration DB  The hardware configuration for MTCC has been upload into DB: the hardware and logical structure with settings and alarm thresholds for the entire system.  We have created two different recipes for ON and STANDBY states with different V0 settings (6000 V for standby and 9500 V for ON)  We have a problem with the JCOP Configuration db tools in the CAEN EASY Crate archiving. When we fix it, with new DB Component version, we will be able to create the CMS_RPCfwHardware Component

Giovanni Polese8 Condition DB  Now we are able to write in and read from devdb database where has been created the same Condition db structure for PVSS, thanks to Angela Brett.  We are in contact with RPC DB team and with M. Abbrescia to have to possibility to move it on final SX5 server. We hope that in a couple of days we will move to it, create the DB structure and test the performance.  Parameters to archive for all channels: V0, I0, Vmon, Imon, Actual_status (info about main alarm conditions: trip, Ovc, UnV, OvV), board temp with deadband to 1-2%

Giovanni Polese9 What we have done The DCS system is almost ready for the MTCC and it will be moved on PCs in the Green Barrack in the third week of May. Supervisor Component is ready and works correctly, the hardware component is under test All sectors and chambers for the Cosmic Challenge have been created in the hardware and logical system view. Communication and running tests have been performed at 904 using real hardware. Everything is working properly. Integration with CMS DCS is almost ready, some common problems will be fix with new JCOP framework release

Giovanni Polese10 To be done for MTCC Move to RPC condition db on SX5 and test the performance. Release the CMS_RPCfwHardware Component Help our Warsaw friends, creating a control and monitoring system of the LB low voltage, and integrate it into the RPC DCS. Do we want to integrate it in the FSM ?? It will be also discussed tomorrow in the DCS working group. Test all the system when the hardware will be ready at SX5 (June 06). Write documentation and organize training in order to have more people ready to take data.