STABLE Kick-off meeting Torino – October 25 th - 26 th,2012 WP5 Assembly and optimization of complete cell Iratxe de Meatza CEGASA STABLE kick-off meeting Torino - October 25 th - 26 th, 2012 Description on 1 st year work
STABLE Kick-off meeting Torino – October 25 th - 26 th,2012 Summary Overview o First-stage goals o Workplan o Tentative timeline
STABLE Kick-off meeting Torino – October 25 th - 26 th,2012 Overview Start date: M6 (April 2013) Materials development from WP1,2,3 Integration & testing in full cell
STABLE Kick-off meeting Torino – October 25 th - 26 th,2012 Summary oOverview First-stage goals oWorkplan oTentative timeline
STABLE Kick-off meeting Torino – October 25 th - 26 th,2012 First-stage goals Design and assembly of complete cell: Identification of first candidate components from WP1-WP3 to propose cell designs Characterization & Testing: Identification of testing protocols and characterization techniques available for development of testing program
STABLE Kick-off meeting Torino – October 25 th - 26 th,2012 Summary oOverview o First-stage goals Workplan oTentative timeline
STABLE Kick-off meeting Torino – October 25 th - 26 th,2012 Workplan – overall target Milestone MS11 - Assembling of complete cells (M32) Cell assembly and test at lab-scale: Expected specific capacity should be >2000 mAh/g Life cycle = cycles
STABLE Kick-off meeting Torino – October 25 th - 26 th,2012 Workplan - tasks T5.1: Assembling obtained materials into a complete cell (M6-M32) CEGASA (14PM) T5.2: Analysis of the performance impact of different assembly techniques with different electrolytes (M6-M32) CEG (8PM) UCC (5PM) Development of full cell from coin-type to pouch-type Li-air concept cell operated in ambient conditions Transfer data/samples from - Candidate materials (substrates, electrolyte, membrane) - Preparation procedures of the lithium and catalytic air electrodes) Note: slurry development needs > 100g active material
STABLE Kick-off meeting Torino – October 25 th - 26 th,2012 Workplan T5.3: Characterization and evaluation of the performance of the cells assembled (M6-M32) ELAPHE (22 PM), UCC (10PM), CEG (8PM) Define electrochemical testing program and parameters (current rates, DoD,…) comparability of results for different cell types M6 with compilation of existing and proposed testing programs: - Applicable International Standards - Internal know-how of partners – Modelling inputs M6 first samples for: - Electrochemical testing (charge/discharge…) - In-situ mechanical & optical tests - Electrical connections, internal resistance - Post mortem surface morphology & phase identification (previous cycling needed)
STABLE Kick-off meeting Torino – October 25 th - 26 th,2012 Summary oOverview o First-stage goals o Workplan Tentative timeline
STABLE Kick-off meeting Torino – October 25 th - 26 th,2012 Tentative timeline 1 st year Proposal M6 Set-up exchange of data/samples with WP1, WP2 & WP3 for first candidate materials Start compilation of existing testing protocols/parameters (take into account WP4 simulation/modelling needs) Prepare list of techniques and equipment/resources brought into STABLE for electrochemical testing and advanced characterization help in definition on testing program before M12 Identify requirements to focus development of full Li-air cell (inputs from Elaphe on different vehicle applications vs. materials development)