R.Giachino / M.Albert Be/op 12 th March 2012 LHC Machine check out 1v1.

Slides:



Advertisements
Similar presentations
1 Commissioning ABT Equipment in the LHC Jan Uythoven ABT TCM 13/01/2015.
Advertisements

8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
LHC progress week 19 Monday 11 th May 2015 Coordination: Jan Uythoven, Massimo Giavannozzi, Mike Lamont.
LHC progress Thursday 30 th April 2015 Coordination: Mike Lamont, Wolfgang Hofle.
R.Giachino / M.Albert Be/op 5 April 2015 LHC Machine check out 1v1.
Mystery unable to inject: timing, BIS, SIS… 8:15 to 12: 30 Injection/LBDS studies  Fine delay adjustment of injection kickers  Synchronization of MKI.
Monday 4 th to Friday 8 th Technical stop  Coordination: Katy Foraz  Machine back to Operations Friday evening on schedule Major cryogenics intervention.
Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
Failure mode impact studies and LV system commissioning tests
LHC 30 th and 31 st July :10 Finish scrubbing fill 25 ns trains by operator dump. –No XPOC data … 08:40 Inject for another scrubbing fill 09:09.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
V. Kain, G.H. Hemelsoet AB/OP1Nov 08, 2007 LHC Injection System V.Kain, G.H. Hemelsoet, AB/OP Input from: E. Carlier, B. Goddard, J. Wenninger What do.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
“we believe the reason why the first bunch is more intense than the following 3 is that it's on that one that the SPS RF loops are locked” Philippe & Django.
LHC 23 June :07: Started injection cleaning with B1. 08:13: Fault on MKI B2. –MKI Beam 2 in P8 had a breakdown at 07:49 during the SoftStart process.
Summary of Week 30 G. Arduini, J. Wenninger Main aims: “Adiabatically” increase peak luminosity by emittance reduction Luminosity production.
Friday March 4 th LHC morning report the short story: from a global point of view we had basically only one access !!!
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
1 Beam Dumping System MPP review 12/06/2015 Jan Uythoven for the ABT team.
Status of ABT beam tests preparation 9-Oct-14. Preparation of sector test without beam I MKI: – Open valves, conditioning to 55 kV, softstart – Check.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
LHC Machine Checkout & Dry Runs Strategy Acknowledgements: R.Alemany, R.Giachino M. Albert LHC Beam Operation Workshop June 2014.
Monday :00 Injection for physics fill # :00 Stable beams fill #1816, luminosity ~1.2x1033 cm-2s-1 11:08 Beams dumped. QPS trigger on detector.
Running scenario 2009/10 Run through components – and then synthesis.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
Last night Lhc closed 15:00 Beam on Ti 8 /Ti2 Prepulse check synchronisation ok with LHCb /RF 17:00 Open Point 4 PC’s and RF 19:00 LBDS energy tracking.
BLM update procedure: - Updated the RT software - Updated the BLETC firmware (ver _A) - Changed the firware version in the MASTER tables and generated.
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Transfer Line Test preparation meeting V. Kain, R. Alemany.
LHC progress Tuesday 28 th April 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
LBOCM. ZerlauthMarch 06 th 2012 Acknowledgements : B.Todd, C.Martin, I.Romera, E.Carlier, J.Wenninger, C.Zamantzas, S.Redaelli et al. 1v0 MPS Commissioning.
LHC 8 & 9 May :10: Injection kicker B1 faulty on oil level –Check in UA and RA. Leaks fixed, to be further checked in TS1 10:30: Pre-cycle started.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Lumi scan limits checked (in preparation for next fill VdM scans).  Trims of up to 150 um per beam in IP1 & IP2 both planes both beams were done (IP5.
04h36: Cryo problem in arc 81. Access. 09h14: Injection.  TI8 injection collimator setup.  Testing new sequence.  New version of vacuum application.
Thursday 27 th October 00:57 fill 2257 dumped during squeeze (RQTF.A67B1) 03:52 stable beams fill #2258 4:33 Dumped, problem of LBDS dilution kicker power.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
Tuesday 3 rd October STABLE BEAMS until 12:25 when we switched to ADJUST for a EOF test for Tobias  dump B2 first and then B1.  Dump at EOF test because.
AWAKE p+ beam line HWC C. Bracco, J. Schmidt Acknowledgment: MCS, EPC, MPE, SPS-OP, BI, ABP (survey),STI, EA, ACE, RP.
LHC Status Sat Morning 30-June Bernhard Holzer, Jan Uythoven Status Friday Late: preparing restart some issues... LHCb dipole tripped / router problem.
LHC Beam Commissioning Meeting V. Kain & R. Alemany
DRY RUNS 2015 Status and program of the Dry Runs in 2015
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Summary of week 7 Hardware Commissioning:
Monday 11/07: Recovery Plenty of accesses.
Last 24 hours RQ5.L1 RQ4.L1 RF trip Line4B LHC status.
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Tue :25 Beams dumped due to RF vacuum interlock
LHC Morning Meeting - G. Arduini
Thursday morning – optics correction
Wednesday 31 October: Morning
Week 35 – Technical Stop and Restart
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
Friday AM Some oscillations of the cryo conditions in MSR8 perturbed the setup for injection. RF frequency interlock fixed – required a reset of RF controls.
Wednesday 09 March …:09:00: beta* measurement (1.5 m) by K-modulation and with AC-dipole excitation. 1/17/2019 LHC 8:30 meeting.
Aims for the week Recover from technical stop and precycle at 10A/s
Monday 24 October hours of 25ns MD
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Wednesday 23/2 Thanks CRYO!!!.
Thursday Aperture studies (foreseen until ~ midday, nothing done) Problems with single bunch B2 from SPS (extraction kicker not enabled) Setting.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Thursday 10:00 Fill 1986 in stable beams.
Presentation transcript:

R.Giachino / M.Albert Be/op 12 th March 2012 LHC Machine check out 1v1

Summary of week 10 Aims of the week – Finish HWC – Prepare machine for first beam LHC 8:30 meeting Machine checkout: R. Giachino, M.Albert and J. Wenninger Hardware Commissioning: M. Pojer, R. Schmidt and M. Solfaroli

LHC check-out Main targets of the week: – Finish HWC, – Close the beam interlock loop, – Test the beam dump, – Test the injection kickers, – Run the LHC through a full machine cycle, – Check the control system. LHC 8:30 meeting

Progress : HWC & checkout ● From Monday to Friday HWC and machine checkout activities had to be performed in parallel. – Priorities were defined every day for HWC and for checkout activities, the focus shifting from HWC to checkout along the week. – Collaboration HWC-machine checkout, was very smooth due to a better planning of the activities. LHC 8:30 meeting

Status of powering tests In total, 8185 tests steps (including preparations of powering tests) have been done Progressive availability of cryogenic conditions

Powering status ● Heat runs: – All sectors were tested ● Pre-cycles work well. ● Several full machine cycles were performed – Without hardware powering faults. – RQT13.L8B1 increased IPNO from 400 to 450(B*.6m) LHC 8:30 meeting

Machine cycle ● HWC was completed Wednesday afternoon when the machine was ‘handed’ over to beam operation. ● The same evening, the machine was pushed through the nominal proton cycle: – Pre-cycling of the magnets, – Injection, – Ramp, – Squeeze. LHC 8:30 meeting control issues were identified – have been fixed or will be fixed in the coming days.

LHC progress : beam interlock and kickers ● To close the beam interlock loop requires a number of conditions, the most difficult ones to achieve were: – LHC closed – no access (also experiments), – No powering failures, – Vacuum valves open, – BLM system operational. >> tough constraints given parallel HWC activities. ● The BIS loop was closed the first time Friday evening. ● Saturday late night both dump and injection kicker systems were pulsing. LHC 8:30 meeting

LHC progress: LBDS & MKI tests ● BETS fully tested at 450GeV and 4GeV. ● Injection inhibitions between LBDS and MKI are OK. ● TSU clients tested : – BIS – BETS – Internal failure (frev switch off) – LBDS trigger – Circulate & dump – Inject & dump -> functionality OK issue with XPOC (see below) ● TSU synchronisation. ● TSU IPOC thresholds have been adjusted. ● MKI synchronisation – checks with beam show a shift of the kick by +160ns w.r.t. beam (to be decided how to adjust it) ● Inject & dump – status is badly returned by one of the 2 CPLDs on the TSU (to be decided) 9

Controls ● Along the week the OP teams with support from numerous equipment groups tested applications, front-ends, LSA core etc.. LHC 8:30 meeting

● The Vacuum system was operational on Friday evening after a big effort in point 2&8. ● RF was ready to ramp for the week end. ● BI was extensively tested without beam. ● Collimators setting and calibration is finished. ● The cryogenic system, has been stable all along the HWC. ● EN/EL, EN/CV at nominal configuration. LHC 8:30 meeting

Injectors and transfer lines (1) ● PSB started up with beam 20 th February. – LHC-indiv Lhc50 LHC-probe LHC25 ● PS started up with beam 23 th February. – LHC-probe, LHC-indiv. – LHC50 12b setting up ● SPS started up with beam 25 th February. – SPS aligned, probe bunch ready to be extracted to the LHC. – LHC-Indiv, LHC-probe, LHC50 multibatch – Scrubbing LHC Bunches LHC 8:30 meeting

Injectors and transfer lines (2) ● Thursday probe bunches were extracted into the TT60 & TT40. ● Saturday afternoon beams were sent down the 3 km long TI2 and TI8 transfer lines to the downstream (LHC end) dumps. ● Saturday night stability checks were performed. LHC 8:30 meeting TI2 TI8

Open issues ● TI 2 Transfer line PC RBIV26407 tripped (to be checked) ● RQT13.L8B1 increased from IPNO from 400 to 450 (b*.6m) Done ok ● RCBV27R4B1 communication lost ● RCBXH1.L1 tripped (circuit super-locked) ● RQTL11.R1B2 problem on TT893 temperature sensor ● RD34.LR3 ramp-down settings are “out of limits” ● RQX.R2 QPS controller communication problem; oscillating ● RQTD/F circuits unable to load ramp/squeeze function (Fidel on Monday) ● RQF/RQD require higher commissioning current for high beta (50 A) ● Inject & dump status is badly returned by one of the 2 CPLDs on the TSU ● MKI synchronisation checks with beam show a shift of the kick by +160ns w.r.t. beam (to be decided how to adjust it RF) 14

Access ● Radiation veto after machine closed !!! ● Access system – PAD problem PM25 – Possible intervention Monday morning ● Alfa – Monday morning Point 1 ● BT – Access point 6 for TSU inject and Dump ● R2E – Monday morning TX76 1Hr ● X ray 2 & 8 – Monday afternoon point 8 – Tuesday morning point 2

Planning 16

Summary ● Situation of the machine: – The LHC magnet and powering system is fully commissioned and the machine is in a very good state – as demonstrated by the cycling of the machine. – RF need 2-4 hrs for fine tuning before beam. – LBDS & MKI minors adjustments before declaring operational. – Essential beam instrumentation and feedbacks tested. – fine tuning with beam. – Control system operational – smaller issues will be fixed in the coming days. ● First beam hopefully Tuesday afternoon! LHC 8:30 meeting

Saturday ● 09:00 Start LBDS tests ● 09:13 Starting ramp of RF and ADT. – stay at flat top with the RF to stress the cavities. ● 15:30 Beams down TI8 & TI2 ● Application Collimator Scan is tested and worked fine. 18

Last night ● 22:30 Alfa interlock. – Tests couldn’t be performed – Problems related to the movement of their XRPs there’s presumably a problem with their logic control; experts will check it this morning ● 22:50 Etienne finished the tests on MKI. – Now left to do the circulate and dump for both Beams. ● Circulate & DUMP B1&B2 (~50 shots each) ● Short access for ATLAS to verify the cooling system; They will need to intervene this morning to fix a problem they have identified (estimate: ~4h, to be scheduled) ● Ramp of PCs (except RQTD/F) ● Squeeze – without RQT13.L8B1 (out of limits error) and RQTD/F circuits 19

Last night ● RQX.R1, RTQX1.R1 and RTQX2.R1 tripped while executing RAMPDOWN[START] function – but no fault present (only PC_PERMIT went away) ● RD34.LR3 gives a "out of limit" when loading the ramp-down function ● ALICE requested some time for a cosmic.. ● Executed ramp of PCs (without RQTD/F & RCS/O/D) & RF 20

LBDS MKI tests ● BETS fully tested at 450GeV and 4GeV. Ramp was OK. – Error check during the ramp still to be done on Monday by Nicolas V. ● Injection inhibitions between LBDS and MKI are OK. – Response times are within specification ● TSU clients tested: – BIS -> OK – BETS -> OK – Internal failure (frev switch off) -> OK – LBDS trigger --> OK – Circulate & dump -> OK – Inject & dump -> functionnality OK issue with XPOC (see below) ● TSU synchronisation -> OK ● TSU IPOC thresholds have been adjusted All OK now ● MKI synchronisation checks with beam show a shift of the kick by +160ns w.r.t. beam (to be decided how to adjust it) ● Inject & dump status is badly returned by one of the 2 CPLDs on the TSU (to be decided) 21

LBDS tests ● BIS loop closed and arm beam dump- done ● Check injection inhibition from LBDS- done ● TSU tests for about 4 hours to test clients (BIS, BETS,…)- done ● Circulate and dump for TSU testing for about one hour. Done – Mask modules in XPOC which are not yet receiving data.- ● Check IQC- ok ● Synchronization of MKI with AGK without beam, loops closed.-Checked ● Beam down TL TI2 and TI8. Rough steering.- done ● TCDI machine protection tests done ● TCDI set-up tests.- chiara ● Direct interlock of LASS to LBDS-.>>> done ● LBDS energy tracking interlocks by trimming– only needs BETS armed, not BIS.- done ● Check BIS timestamps and redundancy of signals to LBDS (with CM, if time available)- Other tests from MP Web page. 22

Injection status ● Managed to pulse both kickers. – Need to check why only the TCDIs beam 1 are interlocking in parking and not beam. ● Problem with timing system: – hidden tables loaded in MTG. Cannot see them and cannot unload them, but they are played (injection, injection_BI). ● Inject & dump does not work currently. ● Circulate & dump is fine – (uses the hidden tables automatically). ● Running circulate & dump in a loop not possible – masking on XPOC not working anymore. (Roman). >>Done 23

MKI MPS tests ● MKI MPS tests – Toggling MKI status and checking input state on injection BIC, both beams - Verifying and adapting soft-start settings (normal and extended), both beams - adjusted operational limits around nominal value (entries 7 and 8) - changed voltage step size for extended settings (entry 14) ● Probed voltage limit for which MKIs not pulsing anymore (1 kV above nominal value, 1 kV below conditioning value), only for P8 done ● Loading kicker soft-start settings from TRIM and FESA, not possible to change without MCS role, possible with MCS role ● Changing critical settings in MKI application only possible with MCS role 24

MKI MPS tests ● Tried to do the energy tracking tests: changing LHC energy: SIS injection energy consistency check stopped us from trimming the RBs above the BETS limit of 0.96 GeV, need a workaround for the commissioning to still perform this test in the next days - changing MKI voltage: within operational limits the kickers are pulsing, need to check with limits further open (MCS role needed) MKI tests not finished. ● MPS interlock tests for collimators TCDI, TDI, TCLI and TCDD in P2 done 25

Injection status ● IQC all data collection is fine, but the soft-start buffer is pushed to PM too early before it is updated after the pulse. – -> The IQC does not find it having pulsed. Done. ● OASIS for MKI signals still needs follow up next week. Currently not fully operational. Done 26

Summary TSU test (both beams) ● Check TSU clients: - BIS triggering --> OK - BETS triggering --> OK - Internal failure triggering --> OK - LBDS slow control triggering --> OK - Inject and dump triggering --> Works fine but bad status acquisition from CPLD2 (XPOC error) - Circulate and dump --> OK ● Issues to be followed: - Inject and dump detection (TSU card CPLD2) - Spurious bad XPOC analysis on TSU (missing dump request detection, XPOC event builder synchronisation) ALL dumps properly synchronised... ● Thresholds adjusted for TSU-IPOC analysis: - re-trigger detection decreased to 199us - DBRF length detection adjusted to 1us - BRF length detection adjusted to 0.9us - BAGK length reduced to 10.9us 27

ABT Software ● ABT and BI had to adapt many FESA devices in a manner to have their PM buffers properly saved into PM data store for IQC and XPOC analysis. ● Impacted systems are:- – MKI/BETS- MKI/IPOC- LBDS/TSU- BTVDD – Now everything is fine for both IQC and XPOC. – We only miss Vacuum data for XPOC, so we had to mask the VAC module temporarily. – It seems that work is ongoing on TE/VSC side to find a solution to the problem. 28

Safe Machine Parameters System 29