ATLAS SCT End-Cap C Integration 1.Introduction: to the SCT within ATLAS 2.End-Cap C Reception at CERN 3.Final Assembly 4.Integration with the TRT 5.Combined.

Slides:



Advertisements
Similar presentations
Endcap assembly update C Buttar UK-SCT-MB RAL 2 nd Sept 04.
Advertisements

Status of EC-C assembly at Liverpool C Buttar EC PAR, Nikhef Nov 04.
Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
ATLAS SCT Endcap Detector Modules Lutz Feld University of Freiburg for the ATLAS SCT Collaboration Vertex m.
18th March Richard Hawkings Humidity control in the ATLAS ID Richard Hawkings (CERN) JCOV meeting 18/3/04  Overview of humidity and associated gas.
AMS-02 tracker mechanics status of assembly and integration at UniGe Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop.
Mechanical Status of ECAL Marc Anduze – 30/10/06.
The LHCb Inner Tracker Marc-Olivier Bettler SPS annual meeting Zürich 21 February 2007.
Atlas SemiConductor Tracker Andrée Robichaud-Véronneau.
4/25/2006 Puneeth Kalavase, UC, Santa Barbara On behalf of US Tracker Outer Barrel group Construction and Testing of CMS “Rods”
1.ATLAS and ID 2.SCT 3.Commissioning 4.Integration 5.Latest Runs 6.Conclusions Commissioning the ATLAS Silicon Microstrip Tracker IPRD08 - Siena Jose E.
Module Production for The ATLAS Silicon Tracker (SCT) The SCT requirements: Hermetic lightweight tracker. 4 space-points detection up to pseudo rapidity.
Shulamit Moed Vertex 2004, Como, September 20041page EndCap Module Production of the ATLAS semiconductor tracker (SCT) ATLAS SCT layout and specifications.
Performance of the DZero Layer 0 Detector Marvin Johnson For the DZero Silicon Group.
Experimental Area Meeting V. Bobillier1 Good connection to earth (in many points) of every metallic parts to be installed in the cavern is very.
SR1 ongoing workH.Pernegger21/2/02 Ongoing work in SR1 and preparations for detector macro assembly Heinz Pernegger.
March 20, 2001M. Garcia-Sciveres - US ATLAS DOE/NSF Review1 M. Garcia-Sciveres LBNL & Module Assembly & Module Assembly WBS Hybrids Hybrids WBS.
CMS FPIX Reinstallation/Commissioning Lorenzo Uplegger 4/20/091.
Chiho Wang ATLAS TRT Duke University CERN, Feb TRT Barrel assembly status & schedule Feb. 9, 2005.
ATLAS SLHC UPGRADE ENGINEERING – LIST OF DECISIONS which will affect the design of auxiliary systems layout and routing BASIC LAYOUT FOR BARREL and WHEELS.
Construction and quality control of the end-cap Transition Radiation Tracker for the ATLAS experiment Vasiliki A. Mitsou CERN HEP 2003, April, Athens,
Pixel Support Tube Requirements and Interfaces M.Olcese PST CDR: CERN Oct. 17th 2001.
ATLAS Upgrade ID Barrel: Services around ‘outer cylinder’ TJF updated According to the drawing ‘Preparation outer cylinder volume reservation’
HEP GROUP MEETING work on the ATLAS UPGRADE T.J.Fraser.
Ron Madaras, LBL U.S. Pixel Meeting, SCIPP, July 9-10, 2003 Patch Panel 1 (PP1) Brief Review Cost and Effort Estimate.
Barrel SCT Material Budget By Alessandro Tricoli RAL ATLAS Physics meeting, 18 th March 2008.
V. Cindro, Jožef Stefan Institute, Ljubljana, Slovenia DAQ, DCS, Power Supply and Cables Review CERN, March Electrical PP1 Basic features Electrical.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
W. Karpinski, Nov CMS Electronics week CMS Microstrip Tracker grounding & shielding of the CMS Tracker R. Hammarstrom (CERN EP/CMT) & W. Karpinski.
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
SCT Week 2 Oct 2002N.P. Hessey NIKHEF1 Status ATLAS SCT 2002 NIKHEF Contributions to ATLAS: Magnets – discussed by Frank Trigger DCS Muon MDT and alignment.
RPC Upscope : An overview with Indian perspective L. M. Pant Nuclear Physics Division Bhabha Atomic Research Centre L. M. Pant India-CMS Meeting, BARC.
18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page
Design Discussion of Mechanical / Electrical Interfaces Bill Cooper (Fermilab) (Layer 1) VXD.
October 05, 2005D. Ferrère, RD05 Florence1 From the ATLAS SCT endcap module production to the commisionning D. Ferrère, University of Geneva in behalf.
The ATLAS Inner Detector Steve McMahon / RAL. Welcome to CERN Geneva Airport LHC accelerator CERN main site SPS accelerator CERN 2nd site It is your laboratory.
Sils ATLAS Meeting 18-9 October 2003 Mechanics for the Barrel SCT.
Neil JacksonUK-V RAL 8th September Module to Disc Assembly Infrastructure –Services and test box –Evaporative cooling system –Disc Handling Tests.
M. Bianco On behalf of the ATLAS Collaboration
IoP HEPP Lancaster 31/03 – 02/04/08 Gavin Davies Dr. Athanasios Hatzikoutelis Dr. Laura Kormos Lancaster University T2K UK Collaboration  DS-Ecal Design.
LHCf: installation & commissioning Measurement of Photons and Neutral Pions in the Very Forward Region of LHC Oscar Adriani INFN Sezione di Firenze - Dipartimento.
Chiho Wang Duke University 1 TRT Barrel integration Status / Schedule Chiho Wang.
UCSC August 12, 2008 U.S. Upgrade R&D Meeting: Strip Detector  Seiden.
Neil Jackson University of Liverpool Hiroshima Symposium June THE ATLAS SEMICONDUCTOR TRACKER (SCT) A PRESENTATION ON BEHALF OF THE ATLAS.
ATLAS 1 Beam Pipe Support Structure (BPSS) Interface and Assembly Final Design Review, April 2003 E. Anderssen, N. Hartman LBNL.
ATLAS 1 Beam Pipe Support Structure (BPSS) Services Interface and Assembly Final Design Review, April 2003 E. Anderssen, N. Hartman, A Smith, LBNL S. Coelli,
1 The ATLAS SemiConductor Tracker commissioning at SR1 APS and JPS joint conference October 30, 2006 Ryuichi Takashima ( Kyoto Univ. of Education ) For.
D. Greenfield CLRC1 UK-V End-cap Engineering 15 July 2003 Debbie Greenfield, RAL.
D. M. Lee, LANL 1 07/10/07 Forward Vertex Detector Overview Technical Design Overview Design status.
M. TYNDEL 1 LHCC Interactions May 2003 ATLAS SCT SCT Production Status ‘Snap-shot’ of the status of the SCT production (May 2003) 1. Barrel Modules 2.
The Detector Performance Study for the Barrel Section of the ATLAS Semiconductor Tracker (SCT) with Cosmic Rays Yoshikazu Nagai (Univ. of Tsukuba) For.
ATLAS: Hardware and Upgrades Liverpool, HEP Christmas Meeting 17 December 2007 Paul Dervan.
The CMS Silicon Strip Tracker Carlo Civinini INFN-Firenze On behalf of the CMS Tracker Collaboration Sixth International "Hiroshima" Symposium on the Development.
Executive Committee, Toronto August 3, 2005 TRT Barrel WBS 1.2/3.2 Harold Ogren Indiana University.
Upgrade PO M. Tyndel, MIWG Review plans p1 Nov 1 st, CERN Module integration Review – Decision process  Information will be gathered for each concept.
August 04 Jason Tarrant CCLRC1 SCE EC Design & Manufacture l Progress of SCT EC »Support Structure (Required for Disc Assembly 2004) »Services (Required.
Endcap assembly update C Buttar, R French UK-V Cluster RAL 8 th Sept 2004.
PH/DT2 Scientific Tea PH-DT2 Scientific Tea, 29 April 2005 : The CMS Tracker - Mechanical Aspects Antti Onnela, PH-DT2: 1. CMS Tracker and.
Chiho Wang ATLAS TRT Duke University CERN, Sep Barrel integration status.
Steinar Stapnes, LHCC June The ATLAS inner detector TRT endcap A+B TRT endcap C TRT barrel SCT barrel SCT endcap Pixels uWhole ID sits inside bore.
`` ATLAS inner detector JV Els KoffemanAtlas - Inner Detector1 Tracking in solenoid 2 Tesla field – 3 pixel layers with 50 um x 400 um cells – 4.
Short summary of ATLAS week. Really a lot has happened since the last ATLAS Plenary in Paris! Giant steps in the detector hardware construction, assembly,
Straw Working group Ferrara 4/9/2014. Outline Status and Plans Installation of Chambers 1-3 Chamber 4 Vacuum test SRB Readout, monitoring and software.
Atlas SemiConductor Tracker final integration and commissioning Andrée Robichaud-Véronneau Université de Genève on behalf of the Atlas SCT collaboration.
EC: 7 DISK concept Preliminary considerations
5 November 2002J.Pater - Systemtest Report1 Endcap Systemtest Current Grounding/Shielding status Recent Upgrades to sector Measurements with 6 Modules.
Update of MVD services and requests
End-cap Mechanics FDR Overview of the Project
Integration and alignment of ATLAS SCT
L H C A T L A S International Collaboration on the LHC Project
Presentation transcript:

ATLAS SCT End-Cap C Integration 1.Introduction: to the SCT within ATLAS 2.End-Cap C Reception at CERN 3.Final Assembly 4.Integration with the TRT 5.Combined Testing Paul Bell Christmas Meeting December 2006

Paul Bell Christmas 2006 The Inner Detector and the SCT Within ATLAS A side Barrel C side Z

The 9 disks of each end-cap are tiled with a total of 986 modules Modules were constructed in different sites worldwide and shipped to Liverpool (Nikhef for EC-A) for assembly to disk, and for disk insertion to the carbon-fibre support cylinder Modules consist of two silicon wafers with 768 readout strips, back to back At one end, “hybrid” circuit holds FE chips which read out the strips Readout is binary: 6 chips per side (dealing with 128 channels each) providing shaping, amplification, discrimination against threshold and pipeline memory storage awaiting L1 Background: The Construction of the SCT Paul Bell Christmas 2006

SCT End-Cap C at a Glance (as it left Liverpool)

Paul Bell Christmas 2006 Temporary Bosch profile support structure Services thermal feed through Disk 1 end (towards interaction point) “The cylinder” with copper ground sheet Low Mass Tapes Data/Command Fibres Disk 9 end (where its plugged in) SCT End-Cap C at a Glance (as it left Liverpool) Temporary Patch Panel (TPP)

February/March SCT EC-C arrived CERN Feb 23rd after a three day journey by road from Liverpool Four weeks of reception testing covered: Electrical connectivity: Resistance checks from TPP to each module Optical connectivity: All harnesses checked Cooling circuits: All 36 cooling circuits leak checked  Problems identified: Found ~100 connectivity problems at the TPP (“temporary interconnects” – not on the EC) Also found electrical disconnections at PPF0 (between disks and cylinder)  Several weeks to investigate and repair Arrival and Reception Tests Paul Bell Christmas 2006 Checking the disk alignment: A pair of telescopes positioned at the disk 1 end and precision “spectacles” at the disk 9 end defined two lines of sight, passing through apertures of decreasing size in the disks.

April For insertion to the TRT, the SCT had to be first transferred to the cantilever stand Move to Cantilever Stand Paul Bell Christmas 2006

April For insertion to the TRT, the SCT had to be first transferred to the cantilever stand Wheels were added to the Bosch support frame and it was wheeled over the stand Move to Cantilever Stand Paul Bell Christmas 2006

Move to Cantilever Stand April For insertion to the TRT, the SCT had to be first transferred to the cantilever stand Wheels were added to the Bosch support frame and it was wheeled over the stand Electrical rework was still on-going, so the EC spent several weeks half on the beam, allowing space around the TPP to work: (Had to move here to create space for end- cap A which arrived at Easter) Paul Bell Christmas 2006

May SCT operates at -7degC in a nitrogen environment; separate volume from the room temperate CO 2 of the TRT:  end-cap has its own thermal enclosure Seal at the inner diameter provided by the Inner Thermal Enclosure (ITE): carbon fibre cylinder with foam layer and copper ground sheet ITE was inserted by rolling along the cantilever beam on carriages: sealed and electrically connected at each end (forms faraday cage as well as gas seal) Construction of Thermal Enclosure

June TE completed at both ends with a gas and grounding & shielding membrane July/August Before adding the Outer Thermal Enclosure, it was found that the optical fibres needed to be relayed along the cylinder more efficiently  Complete rechecking of electrical continuity then required, several weeks delay introduced With TE complete, leak checking began: Completion of End-Cap Paul Bell Christmas 2006

Average All disks – Single Disks = -7e STDEV All disks – Single Disks = 23e Average CERN - Liverpool = 115e STDEV CERN - Liverpool = 70e Liverpool ~ 0°C CERN ~ 25°C Δσ ~ 5e / °C Electrical Testing Inside Thermal Enclosure September Ran 1/8 of a slice through all disks with cooling for proper noise studies with the modules now inside their close-to-final grounding/shielding environment Paul Bell Christmas 2006

October TRT was transferred to trolley, rails installed and aligned on the floor Rolled TRT over the SCT on the beam Transferred weight of SCT to the rails in the trolley; performed final survey of the two detectors Integration to TRT Paul Bell Christmas 2006

November/December Scintillators set up in the test area of SR1 for the cosmic trigger PS cabling, cooling and DCS prepared Connected 1 whole quadrant (quarter slice through all 9 disks) Ran cooling and performed noise scans of those 247 modules  This is where I joined the HLT… Several weeks of cosmic events collected Ahead… Cosmic data taking now finished as of 10 th December: collected ~150k events January will be spent preparing for pit installation (February?) Paul Bell Christmas 2006 SCT/TRT Combined Testing

Showed at the last Christmas meeting the plan for the SCT integration: 1. Reception testing (basic connectivity tests) 2. Transfer to cantilever beam and assembly of thermal enclosure 3. Testing inside thermal enclosure (including noise performance) 4. Integration with TRT 5. Combined testing with TRT  At that time envisaged completion mid-September 2006 We lost ~three months in total, mainly to the reworking of the fibres along the cylinder and to the early reworking of the temporary electrical connections We avoided cutting corners on the testing: an extra testing stage was effectively introduced following the fibre rework; cosmic tests were not originally foreseen Overall: no insurmountable problems, completion on a timescale compatible with the global ATLAS installation schedule. Paul Bell Christmas 2006 Summary