09 July 2015 1 EHN1 civil engineering project status (JUNE) Summary: Updating of the activities carried out on-site (Done) in JUNE List activities on going.

Slides:



Advertisements
Similar presentations
Project Planning: Assembling a Mortenson “Integrated Work Plan”
Advertisements

Beta Testing: The Contractor’s Perspective Trns·port User Group Meeting October 2005.
CFS TIME SCHEDULE EDR - CFS Europe – Kick-Off Meetings Kick-Off Meetings, CERN, 3, 4, 5 September ILC PROJECT ENGINEERING DESIGN REPORT CFS Europe.
Bridge over BNSF Railroad 7 km East of Windham - East Bridge Replacement Project Using Accelerated Bridge Construction.
CONSTRUCTION OF SOIL NAILING WALLS
Hargrave Street Pumpstation – Site Preparation July 2014.
Public Information Meeting #6 City of Fargo Flood Risk Reduction Projects Rose Creek Coulee October 9, 2012.
MARS Taskforce RMS Update March 10, Interim Settlement Solution 03/10 Status Report 2 Execution MilestonesBaseline DateRevised DateStatus Stabilization.
1 BROOKHAVEN SCIENCE ASSOCIATES Central Chilled Water Facility – Phase II Alan Raphael MPO Project Manager CFAC Committee Review November 9, 2009 Sub-basement/Pipe.
Plasma Wakefield (AWAKE) Project Meeting 18 October 2012 Civil Engineering Feasibility Issues for the West Area EDMS : John Osborne GS-SE.
Proactive Management of Project Schedule Shimon Zeierman Rafael Advanced Systems Ltd.
CENF – Civil Engineering Extension B887 CERN: An accelerator complex unique in the world -Prevessin site complex- -EHN1 Extension Area- EHN1 Extension.
Development of the Wastewater Collection and Treatment System in Szombathely County Town Implementation of sewage-sludge Composting Plant 2003/HU/16/P/PE/021.
Industry information day INDUSTRY INFORMATION DAY Assembly & Installation Laurent Schmieder Buildings Infrastructure and Power Supplies Project.
John Osborne GS/SE March 2013
MFP – Installation using a Jack up Rig
Project X RD&D Plan Conventional Facilities (Civil Construction) Russ Alber AAC Meeting February 3, 2009.
Briefing to the Central Valley Flood Protection Board on Status of the FCSA July 12, 2013 Central Valley Integrated Flood Management Study.
AASHTO SCOD Task Force Report Preconstruction Engineering Management (PCEM) June 2003 Robert Pratt, Vice Chairman.
Software Engineering Chapter 15 Construction Leads to Initial Operational Capability Fall 2001.
National Energy Technology Laboratory U. S. Department of Energy Project Kickoff Presentation December 16, 2003 Ken H. Green Principal Investigator Development.
NSW SG 19 Nov Nov 2014 S. Zimmermann, NSW SG 1.
TECHNICAL OVERSIGHT MONITORING AND SUPPORT VISITS ON REGIONAL PROJECTS: 2014/15 Prepared by: R. Gillmer Chief Engineer : Technical Support 21 August 2014.
SuperB. SuperB has been approved as the first in a list of 14 “flagship” projects within the new national research plan. The national research plan has.
Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History.
19 February Summary: Updating on the activities completed (Done) since the last meeting List activities on going (Next steps) and related Actions.
Cargo Dock 16: Pre-Bid Meeting Presentation June 13, 2013.
EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06.
1 RMS Update - ERCOT June 10, Supporting Reports Section.
Vertical Test Stand in IB1 C.M. Ginsburg (Fermilab) for the IB1 VTS Group SRF R&D Meeting 6.July 2006.
06 August EHN1 civil engineering project status (JULY) Summary: Updating of the activities carried out on-site (Done) in JULY List activities on.
GIF in EHN1- layout, construction and schedule Adrian Fabich, EN-MEF-LE GIF users meeting, 12 th February 2014.
CENF – Civil Engineering Extension B887 Status – 02 October 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.
G. Carboni - Muon Meeting – Muon Meeting 12/ Agenda IntroductionGiovanni (30’) GEM and TDR AddendumWalter (20’) Update on M1 ratesAlessia.
22 October Summary: Updating of the activities carried out on-site (Done) in SEPTEMBER List activities on going (Next steps) and scheduled for OCTOBER.
15 January Extension of Building Neutrino Platform General Meetings N.Lopez – M.Manfredi EHN1 civil engineering project status Summary: Updating.
CENF – Civil Engineering Extension B887 Status – 18 September 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.
1 MICE PM Report Infrastructure/integration progress Electrical work AFC, diffuser, etc Help with project control & staffing issues Worries & problems.
CENF meeting 5 th February STATUS CE engineering contract running : – phase 1 : tender drawings – phase 2 : execution drawings – Phase 3 (option)
Community Engagement to Advance Mitigation Action.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/21.
EHN1 – EN/EL Progress update J. Devine G. Gross 11/02/16.
CALIFORNIA DEPARTMENT OF EDUCATION Jack O’Connell, State Superintendent of Public Instruction CELDT Program Update Bilingual Coordinators Network June.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
19 February Extension of Building Neutrino Platform General Meetings N.Lopez – M.Manfredi EHN1 civil engineering project status Summary: Updating.
Town of East Greenbush Waste Water Treatment Plant Project Monthly Update – September 2014.
WP 17.1 Civil Engineering Platform height / vs option Status on M. Manfredi on behalf of WP17.1 team.
Infrastructure EHN1 extension Lau Gatignon, 7 March 2016.
21 January Summary: Updating of the activities carried out on-site (Done) in DEC + ½JAN List activities on going (Next steps) and scheduled till.
10 December Summary: Updating of the activities carried out on-site (Done) in NOVEMBER List activities on going (Next steps) and scheduled for DECEMBER.
January 2009 Phase IVB Construction Photographs by Brent Anderson.
Rob Connatser NSS Instrument Work Packages and XLPM.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
WP 17.1 Civil Engineering Point 1 - Networks LS2 COMMITTEE – CERN – Pieter Mattelaer (SMB-DI)
25 June EHN1 civil engineering project status (MAY) Summary: Updating of the activities carried out on-site (Done) in MAY List activities on going.
September 5, Burkhard Schmidt Integration and Installation Outline: Integration and Infrastructure issues -Suspended platforms -Cable chains -Beam.
Pier Partial GMP Proposal for Marine Structural June 1, 2017
Plaistow BOS Meeting 7/24/2017
FCC Underground Infrastructure
FCC Civil Engineering John Osborne, Jo Stanyard, Matt Stuart(SMB - Site Engineering - FAS Section) Cost & schedule Phase 3 - specification 10th May 2017.
FCC Civil Engineering John Osborne & Jo Stanyard (SMB - Site Engineering - FAS Section) FCC week outline 10th May 2017.
Tunnel Cross Section Studies
EN-CV Progress EHN1 Extension Project
CE Status: Activities executed until 03/08 and ongoing
EHN1: CE Integration process updating
CLIC Civil Engineering Update
Cost & Schedule between Shaft and Adit for Access of Detector Hall
اصول گودبرداری و ایمن سازی
A133 IPSWICH ROAD SCHEME COMMUNICATION UPDATE ( )
FASER LS2 work coordination meeting
Presentation transcript:

09 July EHN1 civil engineering project status (JUNE) Summary: Updating of the activities carried out on-site (Done) in JUNE List activities on going (Next steps) and scheduled for JULY Final consideration Extension of Building th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi

(1) MICRO PILES Vertical & inclined drilling along TT85: (100% completed) EHN1 civil engineering project status (JUNE) Crown beam execution: (100% completed). Done (1/4): 09 July Extension of Building th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi

(2) DIAPHRAGM WALLS -73 panels- Execution EAST side: (91% completed) EHN1 civil engineering project status (JUNE) Execution SOUTH/WEST side: (50% completed) Done (2/4): 09 July Guide walls allowing DW excavation: (87% completed) Execution NORTH/WEST side: (100% completed) ~79% TOTAL PANELS EAST N/W S/W Extension of Building th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi

Done (3/4): (3) TECHNICAL GALLERY -70 meters- EHN1 civil engineering project status (JUNE) Earthworks: (100% completed). After excavation of Type 3 portion Execution TG: (35% completed). Type 3 portion started Backfilling: (25% completed). Type 2, facing TT85 enlargement 09 July Extension of Building th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi

Done (4/4): (4) PITS EXECUTION EHN1 civil engineering project status (JUNE) Crown beam execution: (0% completed). Excavation first ties level: (0% completed). 09 July Excavation head DW level: (15% completed). Started with the East side Excavation second ties level: (0% completed). Only for certain DW panels …Others First ties level execution: (0% completed). -step by step- Task in “cohabitation” with the DWs last panels execution!! Extension of Building th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi

Next Steps: Activities scheduled for July (2) DW: Prepare new lower guide walls close to EHN1 allowing panels excavation. Whole panels completion within end-July (3) TG: Advancement on Type 3 portion. Work site preparation for Type 1 execution (4) PITS: Excavation/Execution crown beam + Excavation/Execution for ties installation  East side portion EHN1 civil engineering project status (JUNE) 09 July /07/2015 Extension of Building th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi

Final Consideration: -New long-term schedule received updated with the current on-site situation. -The compatibility/duration of the upcoming tasks will be assessed. -CE tasks have to be carried out in parallel. Execution of the two pits launched before DWs panels completion to avoid further delays. -Likely (but too early to say) CE first phase completion while metallic contractor are already on-site. Risky, but feasible thanks to the Consortium. -CE Handover unchanged for the moment (Jul-2016) -Next status of the works end-July. EHN1 civil engineering project status (JUNE) 09 July Extension of Building th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi