06 August 2015 1 EHN1 civil engineering project status (JULY) Summary: Updating of the activities carried out on-site (Done) in JULY List activities on.

Slides:



Advertisements
Similar presentations
CFS TIME SCHEDULE EDR - CFS Europe – Kick-Off Meetings Kick-Off Meetings, CERN, 3, 4, 5 September ILC PROJECT ENGINEERING DESIGN REPORT CFS Europe.
Advertisements

Bridge over BNSF Railroad 7 km East of Windham - East Bridge Replacement Project Using Accelerated Bridge Construction.
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
Jan 28, 2009CFS-GBL meeting 1 PM report Jan 28, 2009: Reviews –AAP –PAC (May 9 and 10, 2009) Meetings –TILC09 FALC –Madrid, Jan 19, 2009.
Plasma Wakefield (AWAKE) Project Meeting 18 October 2012 Civil Engineering Feasibility Issues for the West Area EDMS : John Osborne GS-SE.
CENF – Civil Engineering Extension B887 CERN: An accelerator complex unique in the world -Prevessin site complex- -EHN1 Extension Area- EHN1 Extension.
Development of the Wastewater Collection and Treatment System in Szombathely County Town Implementation of sewage-sludge Composting Plant 2003/HU/16/P/PE/021.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
John Osborne GS/SE March 2013
Briefing to the Central Valley Flood Protection Board on Status of the FCSA July 12, 2013 Central Valley Integrated Flood Management Study.
LBT Q Engineering Review PSPI: PEPSI installation preparation, includes all of the pier modifications.
LBT Q Engineering Review PSPI: PEPSI installation preparation, includes all of the pier modifications.
NSW SG 19 Nov Nov 2014 S. Zimmermann, NSW SG 1.
Fermilab 1 AP Dept. Activities Report September 20, 2006Dixon Bogert AP Dept. - Activities Report Dixon Bogert - AP Dept. Meeting September 20 th, 2006.
SuperB. SuperB has been approved as the first in a list of 14 “flagship” projects within the new national research plan. The national research plan has.
Department of Civil Engineering,
Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History.
19 February Summary: Updating on the activities completed (Done) since the last meeting List activities on going (Next steps) and related Actions.
EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06.
09 July EHN1 civil engineering project status (JUNE) Summary: Updating of the activities carried out on-site (Done) in JUNE List activities on going.
GIF in EHN1- layout, construction and schedule Adrian Fabich, EN-MEF-LE GIF users meeting, 12 th February 2014.
CENF – Civil Engineering Extension B887 Status – 02 October 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.
PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.
Tevatron BPM Upgrade Stephen Wolbers CD Accelerator Coordination Meeting August 3, 2004.
7 November 2003 Status of CNGS NBI presented by K. Elsener 1 Status of CNGS Konrad Elsener CERN – Accelerators+Beams Division.
LIU external beam dump review External beam dump option A: branching off from LSS6 J.L. Abelleira Thanks to: F. Velotti, B. Goddard, M. Meddahi, H. Vincke,
22 October Summary: Updating of the activities carried out on-site (Done) in SEPTEMBER List activities on going (Next steps) and scheduled for OCTOBER.
15 January Extension of Building Neutrino Platform General Meetings N.Lopez – M.Manfredi EHN1 civil engineering project status Summary: Updating.
Functional/Budget specification EHN1 Extension: Infrastructure (WG2) Mats Wilhelmsson EN/MEF 4 November 2015.
CENF – Civil Engineering Extension B887 Status – 18 September 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
V. Bobillier1 Cable installation status.
1 MICE PM Report Infrastructure/integration progress Electrical work AFC, diffuser, etc Help with project control & staffing issues Worries & problems.
MDI 9 th Meeting - 22 nd January 2016 FCC Experimental Caverns - Feasibility and Excavation C. Cook (GS), J. Osborne (GS),
CENF meeting 5 th February STATUS CE engineering contract running : – phase 1 : tender drawings – phase 2 : execution drawings – Phase 3 (option)
FCC-hh MDI 5 th Meeting Friday 13 th March 2015 Civil Engineering Layouts for Experimental Caverns – First Draft Charlie Cook (GS), John Osborne (GS)
Community Engagement to Advance Mitigation Action.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/21.
EHN1 – EN/EL Progress update J. Devine G. Gross 11/02/16.
19 February Extension of Building Neutrino Platform General Meetings N.Lopez – M.Manfredi EHN1 civil engineering project status Summary: Updating.
Town of East Greenbush Waste Water Treatment Plant Project Monthly Update – September 2014.
WP 17.1 Civil Engineering Platform height / vs option Status on M. Manfredi on behalf of WP17.1 team.
Infrastructure EHN1 extension Lau Gatignon, 7 March 2016.
UK Project Plan (Finance & Risk) Alan Grant STFC DL RLSR 5 th April 2016.
21 January Summary: Updating of the activities carried out on-site (Done) in DEC + ½JAN List activities on going (Next steps) and scheduled till.
10 December Summary: Updating of the activities carried out on-site (Done) in NOVEMBER List activities on going (Next steps) and scheduled for DECEMBER.
Rob Connatser NSS Instrument Work Packages and XLPM.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
WP 17.1 Civil Engineering Point 1 - Networks LS2 COMMITTEE – CERN – Pieter Mattelaer (SMB-DI)
25 June EHN1 civil engineering project status (MAY) Summary: Updating of the activities carried out on-site (Done) in MAY List activities on going.
September 5, Burkhard Schmidt Integration and Installation Outline: Integration and Infrastructure issues -Suspended platforms -Cable chains -Beam.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/14.
Pier Partial GMP Proposal for Marine Structural June 1, 2017
Plaistow BOS Meeting 7/24/2017
FCC Underground Infrastructure
FCC Civil Engineering John Osborne, Jo Stanyard, Matt Stuart(SMB - Site Engineering - FAS Section) Cost & schedule Phase 3 - specification 10th May 2017.
FCC Civil Engineering John Osborne & Jo Stanyard (SMB - Site Engineering - FAS Section) FCC week outline 10th May 2017.
CE Status: Activities executed until 03/08 and ongoing
EHN1: CE Integration process updating
CLIC Civil Engineering Update
Lake Apopka North Shore Update
US 50 SLOPE STABILIZATION PROJECT
اصول گودبرداری و ایمن سازی
Wellborn Underpass Update
Construction Considerations
A133 IPSWICH ROAD SCHEME COMMUNICATION UPDATE ( )
A133 IPSWICH ROAD SCHEME COMMUNICATION UPDATE ( )
Three Bridges Estates HOA Meeting
eSPS 2nd CDR meeting – 17th June 2019
Presentation transcript:

06 August EHN1 civil engineering project status (JULY) Summary: Updating of the activities carried out on-site (Done) in JULY List activities on going (Next steps) and scheduled for AUGUST Final consideration Extension of Building th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi

(1) MICRO PILES Vertical & inclined drilling along TT85: (100% completed) EHN1 civil engineering project status (JULY) Crown beam execution: (100% completed). Done (1/4): 06 August Extension of Building th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi

(2) DIAPHRAGM WALLS -73 panels- Execution EAST side: (91% completed) EHN1 civil engineering project status (JULY) Execution SOUTH/WEST side: (67% completed) Done (2/4): 06 August Guide walls allowing DW excavation: (100% completed) Execution NORTH/WEST side: (100% completed) ~85% TOTAL PANELS EAST N/W S/W Extension of Building th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi

Done (3/4): (3) TECHNICAL GALLERY -70 meters- EHN1 civil engineering project status (JULY) Earthworks: (100% completed). Execution TG: (72% completed). Type 3 almost done. Type 1 started Backfilling: (25% completed). 06 August Extension of Building th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi

Done (4/4): (4) PITS EXECUTION EHN1 civil engineering project status (JULY) Crown beam execution: (22% completed). Start with E side. Excavation first ties level: (22% completed). 06 August Excavation head DW level: (50% completed). Start with E and N/W side areas. Excavation second ties level: (0% completed). Only for certain DW panels …Others First ties level execution: (13% completed). Not yet in tension -step by step- Task in “cohabitation” with the DWs last panels execution!! Extension of Building th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi

Next Steps: Activities scheduled for August (2) DW: Whole panels completion within 1 st half of August (3) TG: Entire length, including connection with the EHN1, within end-August. (4) PITS: Excavation/Execution crown beam + Excavation/Execution for ties installation  East side portion EHN1 civil engineering project status (JULY) 06 August /08/2015 => Extension of Building th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi

Final Consideration: -New long-term schedule received updated with the current on-site situation. -The compatibility/duration of the upcoming tasks will be assessed. -CE tasks have to be carried out in parallel. Execution of the two pits launched before DWs panels completion to avoid further delays. -Likely (but too early to say) CE first phase completion while metallic contractor are already on-site. Risky, but feasible thanks to the Consortium. -CE Handover unchanged for the moment (Jul-2016) -Next status of the works end-August. EHN1 civil engineering project status (JULY) 06 August Extension of Building th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi