Magnet & services projects P. Tropea 9 Nov 2011 – CMS upgrade workshop.

Slides:



Advertisements
Similar presentations
Status of Cryogenics at point 4 following the power cut L. Tavian 20 August 2011.
Advertisements

André Augustinus 16 June 2003 DCS Workshop Safety.
CMS Pixel Technical Board Meeting – Dec. 16, Forward Pixel Cooling System Information Joe Howell.
Electrical Installation CM39 Andy Gallagher & Ian Mullacrane.
Saverio MINUTOLITIG meeting, 10 February Report on T1 installation activities and achievements made during this shutdown.
SPD Cooling workshop: PLC item details. ups upgrade: 10-12' after trigger 24V - what to do in 10 minutes Present situation: In case of “normal power”
M. Battistin – 1 st September 2009 EN/CV/DC 1 M. Battistin (EN/CV/DC) 1 st October 2009 ATLAS cooling Group - Thermosiphon solution for ATLAS ID cooling.
For more information, please contact 19/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
Point 5 - Cooling Network - Key Primary Water Chilled Water Mixed Water Eau Bruite Standard Power Diesel Backup Comp Air Primary Water at 20-25C – Produced.
CRYOGENICS AND POWERING
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
CMS Pixels upgrade CO 2 cooling transfer lines Introduction to the two projects P.Tropea 5 Dec 2012.
Claudio Bortolin. 1 st June: PT100 electrical connection failure (Temp Chiller water In&Out) 1) it required an access to the cavern to be fixed 2) access.
19 May 09P. Tropea1 Fluorocarbon systems –SS1 hydraulics completed, now under commissioning –SS2 connections and sensors installation done –Pixels ready.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
1 H. Pernegger/CERNIBL cooling review 15/5/2012 IBL Cooling Requirements H. Pernegger.
TOF Gas System Project Overview. Content Prototype for Aging tests done for RPC’s TOF Gas System: parameters and module layouts. Special Technology: channel.
European Organization for Nuclear Research - Organisation européenne pour la recherche nucléaire SSD/SDD Proposal Upgrade 30/08/2012
19/02/2014A. D'Auria CERN/PH-DT-DI Maintenance ID flushing system:  Maintenance 2 dryers  Installation 2 flow meters  Maintenance of several hygrometers.
26 May 2010Hans Postema - CERN Status and plan for the development and construction of CO2 Cooling System for Pixel Upgrade 1.
J. Direito - M. Battistin – 28 th May 2010EN/CV/DC J. Direito, M. Battistin (EN/CV/DC) 28 th May 2010 Detector Cooling Project III Thermosiphon Workshop.
TK Dry Gas System Operation  System overview  Dry Gas Consumption  Interlocks and thresholds  Documentation  Operational model  Final comments.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.
CMS Proposal for a Maintenance & Operation agreement with EN/CV/DC for fluorocarbon detector cooling circuits v.2 P. Tropea For the CMS experiment.
All CMS 30 May07 TSV1 All CMS 3 30 May 2007 LHC machine CMS Progress Overall Schedule.
Computing Facilities CERN IT Department CH-1211 Geneva 23 Switzerland t CF CERN Computer Centre Consolidation Project Vincent Doré IT Technical.
Cooling plant upgrade Jose Botelho Direito, Michele Battistin, Stephane Berry, Sebastien Roussee 2 nd SPD Cooling Workshop 30/11/201112nd SPD.
The Building 180 Cryogenic infrastructure water cooling system Status Update Stefano Moccia, EN-CV Coordination meeting 14/10/15.
5 th May 20061M. Battistin CERN LEAF Committee 2/R-030 8h30 - May 5 th 2006 Michele Battistin (TS/CV/DC) TS M&O agreement for Detector Cooling installations.
R. Boyd 1 February  Dr. M. Saleem  D. Jana  M. R. Meera Labbai  R. Boyd.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
CMS Pixels upgrade CO2 cooling transfer lines Draft spec – for introduction Paola Tropea & Hans Postema 5 December 2012.
Cooling System Solutions
TS-CV-Detector Cooling 22-Jan-04P. Tropea - JCOV1 Design, construction and installation of a double loop fluorocarbon 150 kW cooling plant for the CMS.
CMS consolidation activities of detector cooling system Detector cooling project P. Tropea.
CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Update ME4/2 Chambers and Tooling A construction of new ME4/2 prototype at CERN Factory tooling,
CMS-GEM gas system GEMs for CMS High Eta Muons - Workshop III, CERN April R.Guida PH-DT-DI.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
CO2 Cooling For the CMS Pixel detector 11 November 20081Hans Postema & Antti Onnela.
LHCb-UT and Velo Upgrade Road to a system EDR in Q June 2015 Bart Verlaat 1.
Claudio Bortolin. pump: replaced outlet filter: replaced demineralized cartridge: replaced mechanic filter on air control: replaced SSD chilled water.
Tracker cooling plant refurbishment Project status Revised plan Financial impact.
Tracker cooling status General status Production: Manifolds, Distribution lines Work at P5 Plan Conclusions 19/05/091E. Focardi.
A two-stage system for the future cooling system.
110 th November 2010EN/CV/DC Detector Cooling Project - advancement status of Work Package N3 Thermosiphon project Michele Battistin 18 May 2011.
August 2007Andrea Gaddi, CERN Physics Dept. Detectors Infrastructures & Services Baseline to design detectors infrastructures. Tentative arrangement of.
CMS TK II cooling Brainstorming P. Tropea (update after meeting on June 13 th with Duccio, Antti, Hans, Jerome, Paolo, Bart) 20 June 2016.
1. Road to the EDR 2 Requirements Safety system Transfer line concept Plant concept design Requirements Evaporator concept and performance Transfer line.
CV works in the non- LHC accelerator complex during 2008 and plans for 2009 ATOP days 2009.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
V Thermo-siphon Workshop Test protocol Jan Godlewski PH/DT-PO On behalf of thermo-siphon working group
Arnd Meyer (RWTH Aachen) Sep 8, 2003Page 1 Integrated Luminosity Total data sample on tape with complete detector > 200pb -1.
A. Perin, TE/CRG, Page 2 CERN-GSI FAIR Project integration/coordination meeting 5 14 th October 2015 A. Perin, H. Derking, L. Stewart, M. Chesi,
Detector Safety System overview DSS is a PLC based system designed to protect ATLAS detector from damages. Front end (hardware) 2 redundant PLC ~700 input.
CO 2 Cooling Plants for the LHCb upgrade LHCb infrastructure workshop February Burkhard Schmidt With input from Bart Verlaat, Paolo Petagna and Lukasz.
S A Griffiths CM42 June 2015 Electrical & Control.
1M. Battistin M. Battistin CERN EN/CV/DC 9 th July 2009 CO2 kick-off NIKHEF - Cooling activities organization at CERN 9 th July 2009.
For the CMS Pixel detector
CMS Area Working Group Meeting
Forum on Tracking Detector Mechanics - Bonn, May 2016
Tracker cooling loop “check out” draft for discussion
M. Battistin CERN EN/CV/DC 9th July 2009
Keeping LHC cold during LS periods Preliminary proposal
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
the CERN Electrical network protection system
Status of the cryogenic system for B180
For the CMS Pixel detector
Aziz AMAMOU EACM – 21th May 2019
Presentation transcript:

Magnet & services projects P. Tropea 9 Nov 2011 – CMS upgrade workshop

CMS Upgrade Workshop 9 November 2011 P. Tropea Contents CONSOLIDATION Magnet infrastructure Water & Fluorocarbon cooling General services UPGRADE Pixel phase I CO 2 cooling RE4 cooling 2

CMS Upgrade Workshop 9 November 2011 P. Tropea Magnet (courtesy B. Cure) Magnet operation in 2011 (since Feb restart till Oct 2011): 84.8% of total time at 3.8T 11.6% of total time with planned magnet stops 3.6% of total time with unexpected magnet stops 100% available for physics at LHC. Three faults, both recovered in 4 days: faulty valve position controller mismatch of cryo parameters (operator mistake), following intervention on cryoplant during the July TS and the following power cut Switch off of all magnet power converters (procedural problem) Increase reliability & redundancy of services to reduce failure impact & limit the magnet cycling, in order to maintain expected magnet availability and lifetime! 3

CMS Upgrade Workshop 9 November 2011 P. Tropea Magnet cryo & cooling (courtesy B. Cure) Cryo compressors: standard revision demands several months with magnet off. Any failure would imply long waiting time, since compressors are not off-the- shelf components. Low efficiency (still within specs) due to the non optimal lubricant separation system  2 new compressors to be installed in order to guarantee full redundancy: scheduled for LS1, critical parts already ordered (rotor, casing, bearings, motors)  Issue with lubrication separation system addressed (common issue with LHC machine cryoplants) : helium dryer (+ purifier, to be confirmed) to be installed during LS1 Busbar cooling: coupled through buffer tank to Yoke and Endcap cooling (possible stoppage during maintenance operation on the latters). Requirements on EDMS , project launched with EN/CV for LS1 4

CMS Upgrade Workshop 9 November 2011 P. Tropea Magnet safety & control system, power (courtesy B. Cure) 1.MSS chassis: new spare units shall be built with up-to-date electronics 2.MSS powering: modification of the 55V batteries, to replace the chargers and their supervision: increase the charger reliability and improve the supervision and alarm to the ANS 3.Transformer 18kV / 400V: no spare transformer reserved for CMS on the magnet power line, backup plan is to temporarily connect on adjacent transformer in USC55 before a new transformer is delivered. 5

CMS Upgrade Workshop 9 November 2011 P. Tropea Water cooling: consolidation Consultation with EN/CV in October, agreement to plan all activities and finalize studies by beginning of Operation improvements Additional monitoring & verification of DSS cabled alarms Action matrix on humidity level alarms to be updated (stop of rack circuit incident on August 3 rd ) Backup chiller during maintenance/major incidents? Ecal cooling system Slow response of T regulation to changes of load or primary cooling T Too high sensitivity to small flow/temperature changes on CMS side Review with CMS and CV people to be organized asap 6

CMS Upgrade Workshop 9 November 2011 P. Tropea Water cooling: leak risk mitigation Since Jan 2010: 24 leaks (all detected by inspections, except one spotted by leak detection cable). Rack circuit is the most critical (19 leaks), followed by the Muon circuit. 1.Modify critical racks (Tracker) to make connections accessible: on- going study 2.Improve leak detection system: calibration of leak sensors to retrieve leak position graphic interface to have a faster feedback (DSS team, cooling team, Sensors 4CMS team) 7

CMS Upgrade Workshop 9 November 2011 P. Tropea Fluorocarbon circuits: “go cold” & reliability Tracker cooling working group (Chair: A. Onnela, members: Tracker, EN/CV/DC, PH/DT) is in charge for evaluation of main interventions towards long term improvements on cooling system and implications of running at much lower temperatures after LS1 -Performance test: to assess the capacity of the system to cope with low T and demanded power, including Pix CO 2 plant (ETS 2011/2012) -Dryness of cooling cabinets & environment for Tk maintenance -Pneumatic cabinet revamp to increase reliability -Backup chiller full commissioning for Thermal Screen and Preshower plants -Additional monitoring instrumentation (vibration, fast pressure transducers, etc.) 8

CMS Upgrade Workshop 9 November 2011 P. Tropea General services Gas nitrogen for detector dryness Additional N 2 gas flow needed. Full picture on EDMS To be completed with updated Tracker needs once humidity issues assessed SHL5 Pixels lab Climatic chamber: T and RH regulation ranges defined, structure being prepared and HVAC works to be done in 2012 UXC55 Temperature/Humidity control Cavern temperature above 20°C all year long Huge sensitivity of RPC to ambient temperature Additional load to the cavern from ECAL cables Need for understanding present system limits and possible cures, project launched with EN/CV Rack cooling turbines -Mandatory to replace all turbine motors in magnetic field in LS1 -Considering replacement of turbine motors in USC as well 9

CMS Upgrade Workshop 9 November 2011 P. Tropea Pixels phase I CO 2 (see talk by H. Postema for further details) On-detector cooling design ongoing -Definition of cooling loops length (PSI, FNAL) -Thermal performance tests and simulations (PSI, FNAL, CERN) Conceptual design mostly ready for cooling plant -Components being selected (CERN/Lyon) -3D modeling started (Lyon) -Control system studies started (CERN) Qualification of copper pipes -Resistance to high pressure approved by CERN safety 240 bar) -Full scale mock-up for flow regime investigation ready, tests to start in few weeks (CERN) Installation studies -Two possible locations: USC or UXC -Radiation protection studies ongoing 10

CMS Upgrade Workshop 9 November 2011 P. Tropea RE4 cooling manifold (courtesy D. Loveless) RE Proposal –Design Xmas towers in accessible location –Run laterals from the towers to the chambers Use hoses, not copper pipe RE chambers have pigtails, connect via O-rings –Design should take 3-4 weeks –Production of stainless piping can be done by local firm CSC Connections exist –Purchase fittings 11 Main issues to be addressed: integration, coordination of installation works and commissioning Same design to be considered for YE1 possible consolidation…

CMS Upgrade Workshop 9 November 2011 P. Tropea Summary Infrastructure consolidation, even if not so fancy, is mandatory to guarantee a good data taking reliability A number of projects are well defined and already in the pipeline for LS1 Some other projects need time and resources to advance: N 2 plant… Consolidation projects strongly influence also upgrade (see primary circuit for Pix CO 2 plant) Cooling for upgrade is in good shape: projects are progressing and resources are well allocated 12