1 DELEGATES FROM JAPAN. 2 INDIA POLITICAL MAP POPULATION :- 103 CRORES AREA :- 3,419 (‘000 SQ KM) STATES :- 29 UT :- 6 BIGGEST CITY :- MUMBAI WE ARE HERE.

Slides:



Advertisements
Similar presentations
AVAILABILITY BASED TARIFF SCHEDLING PROCEEDURE AND SETTLEMENT MECHANISM UNDER ABT REGIME T. SRINIVAS MANAGER,SRLDCBANGALORE.
Advertisements

1 PROJECTS IN THE PIPELINE IN SOUTHERN REGION. 2 PROJECTS IN PROGRESS IN SOUTHERN REGION 400 KV MADURAI-TRIVANDRUM LINE WITH 400 KV SS AT TRIVANDRUM 400.
PROJECTS IN THE PIPELINE IN SOUTHERN REGION. PROJECTS IN THE PIPELINE IN SR GENERATION EVACUATION PROJECTS GENERATION EVACUATION PROJECTS GENERATION EVACUATION.
INDIAN POWER SECTOR. ADMINISTRATION AND MANAGEMENT As per Constitution of India, Electricity comes under concurrent list i.e. the development and management.
1 THE INDIA ELECTRICITY MARKET TIME LINE REAL TIME 15 MT BLOCKS LONG TERM LOAD FORECAST FUND MOBILISATION 10-5 YEARS POWER PURCHASE AGREEMENTS CAPACITY.
POWER GRID CORPORATION OF INDIA LTD SOUTHERN REGIONAL LOAD DESPATCH CENTRE in 3rd SRPC MEETING 19 th February 2007 Bangalore GRID EVENTS AND ISSUES.
POWER GRID CORPORATION OF INDIA LTD
INDIAN POWER SECTOR. Presentation Contents: Power Sector Structure in India Transmission Planning Criteria RLDC ’ s Management System Restoration Procedures.
 POWERGID – PERSPECTIVE PLAN. POWERGRID – Introduction  POWERGRID, the Central Transmission Utility, is responsible for  Establishment and Operation.
FREQUENCY PATTERN DURING JAN 2007 Freq Profile 1-11 Freq Profile Freq Profile
Section 7.5 –4 – ii of Indian Electricity Grid code (IEGC): “The summation of station-wise ex-power plant drawal schedules for all ISGS after deducting.
WELCOME TO K. SWAMINATHAN, CHAIRMAN K. SREERAMA MURTHY, MEMBER
1 WORLD BANK MISSION. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 31,230 MW EASTERN.
CMD VISIT ON 16-JAN-03 DAILY FREQ COMPARISION JAN-02 & JAN DAYS FREQ COMPARISION JAN-02 & JAN DAYS FREQ JAN DAYS FREQ JAN-02 TYPICAL.
1 POWER GRID CORPORATION OF INDIA LIMITED BANGALORE.
Load Forecast T SRINIVAS MANAGER SRLD C. LINKS PREAMBLE GENERATION ANALYSIS GROWTH OF I/C GROWTH OF I/C Vs DEMAND PHYSICAL INTERPRETATION ELECTRIC CONSUMPTION.
POWER GRID CORPORATION OF INDIA LTD SOUTHERN REGIONAL LOAD DESPATCH CENTRE in 139 TH SREB MEETING 19 TH DECEMBER 2005 HYDERABAD GRID EVENTS AND ISSUES.
PETITION BY TNEB TO INVESTIGATE ANY GAMING BY THE GENERATORS PETITION NO:- 90/2005 CERC HEARING ON 06-OCT-05.
PRESENT CONDITIONS. FREQUENCY DURATION CURVE , , &
W E L C O M E Power Grid Corporation of India Limited.
EVACUATION STRATEGIES FOR KARWAR ULTRA MEGA THERMAL POWER PROJECT SOUTHERN REGIONAL LOAD DESPATCH CENTRE.
1 ALL INDIA GENERATION COMPOSITION Total Market Size = BU 1,27,110 MW.
1 REGIONAL GRIDS QUICK FACTS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 34,207.
SRLDC WELCOMES SHRI VISHNUVARDHAN REDDY DIRECTOR(F) KPC.
1 PRESENTATION ON “OPEN ACCESS – ELECTRICITY ACT 2003” TO THE OFFICERS OF KARNATAKA ELECTRICITY BOARD On POWER ENGINEERS’ DAY 23 RD January, 2005 by V.K.
WELCOME TO CIGRE MEMBERS
S.P.KUMAR CM(SCADA-IT) SRLDC, POWER GRID
1 Technical and Commercial Aspects K.RAMAKRISHNA DGM, SRLDC DGM, SRLDC.
CHALLENGES IN INTEGRATING SR WITH NEW GRID V.S.Verma Member(CERC )
IMPACT OF ABT, NETWORK STRENGTHENING ON GRID OPERATION IN KARNATAKA SOUTHERN REGIONAL LOAD DESPATCH CENTRE POWER GRID CORPORATION OF INDIA LIMITED ADVANTAGE.
1 Operating the Power Grid: Current Scenario and Challenges Ahead V. K. AGRAWAL General Manager SRLDC, Bangalore 8 th November, 2006.
POWER GRID CORPORATION OF INDIA LTD.
1 INTRA – STATE AVAILABILITY BASED TARIFF (ABT) A Presentation on INTRA – STATE AVAILABILITY BASED TARIFF (ABT)
G1 G2 SERC SLDC SEB/STU State Govt. RLDC REB CTU CERC Central Govt. CEA ISTS ISGS Load L1L2 Intra State System IEGC to Operate on the periphery X=- GLG.
LANDMARK EVENTS AVAILABILITY BASED TARIFF AVAILABILITY BASED TARIFF AVAILABILITY BASED TARIFF AVAILABILITY BASED TARIFF ULDC SCHEME ULDC SCHEME ULDC SCHEME.
AVAILABILTY BASED TARIFF. AVAILABILITY BASED TARIFF A RATIONAL TARIFF STRUCTURE A RATIONAL TARIFF STRUCTURE SCIENTIFIC SETTLEMENT SYSTEM …..COMPLEMENTS.
POWER SECTOR REFORMS Grid Operation and Control in the changed Scenerio.
Overall National Grid Development: Constraints & Options
SOUTHERN REGION EXPERIENCE
CONFIRMATION OF MINUTES (AMENDED PARA) Director (Transmission ), KPTCL stated that on account of DC current entering the neutrals of various transformers.
WELCOME SHRI A. MANGLIK TO EXECUTIVE DIRECTOR
WELCOMES & CHAIRMAN & MEMBERS POWER GRID CORPORATION OF INDIA LIMITED
Availability Based Tariff (ABT) in Northern Region.
1 SOUTHERN REGIONAL LOAD DESPATCH CENTRE POWER GRID CORPORATION OF INDIA LIMITED WELCOME TO V MADHU, MD, KPTCL.
AVAILABILITY BASED TARIFF AND SCHEDULING MECHANISM.
1 AUDITORS. 2 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 31,230 MW EASTERN :-
SYSTEM OPERATION AVG, MAX & MIN DRAWAL SHARE ALLOCATION INTER-REGIONAL IMPORTS 3D FREQ OCT-03 3D SR DEMAND FREQ COMPARISION OCT-02 & OCT-03 GENERATION.
FREQUENCY EVENTS NTPC (INJECTION - DC) ISSUES NLY – II STAGE 1 (INJECTION - DC) NLY – II STAGE 2 (INJECTION - DC) NLY TPS I (Exp) (INJECTION - DC) ULDC.
1 ABOUT 7000 MW OF CAPACITY IS BELOW 100 Ps ABOUT14200 MW OF CAPACITY IS BELOW 200 Ps ABOUT MW OF CAPACITY IS BELOW 300 Ps CUM. INS. CAP.
SOUTHERN REGIONAL GRID ▀ Centre Generating Stations in the Region are Ramagundam Super Thermal Power Stn. : 2,600 MW (200x x4) Neyveli Lignite Corporation.
SPECIFIC IMPROVEMENT IN SR IN RECENT PAST FREQUENCY IN NORMAL BAND % OF TIME FREQUENCY IN NORMAL BAND % OF TIME FREQUENCY IN NORMAL BAND.
1 SOUTHERN REGIONAL LOAD DESPATCH CENTRE POWER GRID CORPORATION OF INDIA LIMITED PRESENTATION ON ROLE OF REGULATORS IN SELLING EXCESS POWER FROM CPPs 31ST.
SPECIFIC IMPROVEMENT IN SR IN RECENT PAST FREQUENCY IN NORMAL BAND – % OF TIME NORMAL VOLTAGES THROUGH OUT THE GRID SYSTEM STRENGTHENING –GAZUWAKA.
1 PRESENTATION ON FREQUENCY CONTROL AND FREE GOVERNOR OPERATION TO THE OFFICERS OF CENTRAL ELECTRICITY AUTHORITY On 4 th April, 2005 by V.K. Agrawal SRLDC,
SOUTHERN REGIONAL LOAD DESPATCH CENTRE
LINKS ACHIEVEMENT SELF STARTING STATIONS SYNCHRONISING SUB-STATIONS SYNCHRONISING SUB-STATIONS.
INJECTING UTILITYSTATEEXPORT (MU) TNEBTAMILNADU673 KPTCLKARNATAKA205 KSEBKERALA1792 APPCCANDHRA PRADESH426 JINDALKARNATAKA274 KPCLKARNATAKA593 JSWELKARNATAKA1058.
Southern Regional Power Committee Central Electricity Authority.
MERIT ORDER SCHEDULING AND DESPATCH V. K. AGRAWAL NRLDC.
1 SOUTHERN REGIONAL LOAD DESPATCH CENTRE POWER GRID CORPORATION OF INDIA LIMITED WELCOME TO SHRI U. C. MISRA Director (Personnel )
1 ABT WORK SOUTHERN REGION EXPERIENCE. 2 "If a path to the better there be, it begins with a full look at the worst." -- Thomas Hardy.
LOAD FLOW STUDIES TO DURING THE ABOVE PERIOD FOR EACH YEAR AND EACH QUARTER IN EACH YEAR MAXIMUM AND MINIMUM FREQUENCY OF A DAY.
Grid Operation --- Role of RLDC. Contents Load Generation Balance Electricity Accounting Real Time Trends ABT Feedback Inter Regional Exchanges Loading.
ENERGY CONSERVATION IN SR - A CASE STUDY
REACTIVE POWER MANAGEMENT IN SOUTHERN GRID
REGIONAL GRIDS IN INDIA – QUICK FACTS
UNIFIED LOAD DESPATCH SCHEME IN THE SOUTHERN REGION
KADAMPARAI PUMP OPERATION
GRID STATUS – PRE - ABT Very wide Frequency fluctuations
THE RPUF SCHEME KHAMMAM VIJAYAWADA NAGARJUNASAGAR HYDERABAD RAICHUR
Presentation transcript:

1 DELEGATES FROM JAPAN

2 INDIA POLITICAL MAP POPULATION :- 103 CRORES AREA :- 3,419 (‘000 SQ KM) STATES :- 29 UT :- 6 BIGGEST CITY :- MUMBAI WE ARE HERE GARDEN CITY SILICON VALLY

3 SOUTHERN REGION WESTERN REGION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION INSTALLED CAPACITY NORTHERN :- 31,230 MW EASTERN :- 17,697 MW SOUTHERN :- 31,931 MW WESTERN :- 32,354 MW NORTH-EASTERN :- 2,357 MW TOTAL 115,569 MW

4 SOUTHERN REGION WESTERNRE GION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION ‘ ELECTRICAL’ REGIONS SAME FREQUENCY FROM GUJARAT TO ARUNACHAL PRADESH WITH EFFECT FROM MARCH 2003 ABOUT 2800 KMS! APART

5 SOUTHERN REGION WESTERNRE GION EASTERN REGION NORTHERN REGION NORTH- EASTERN REGION ‘ELECTRICAL’ REGIONS 1 2 WITH THE COMMISSIONING OF THE TALA PROJECT CONNECTING THE EASTERN AND NORTHERN GRIDS, INDIA WILL HAVE ONLY TWO GRIDS

6 SOUTHERN REGION – GEOGRAPHY ANDHRA PRADESH TAMIL NADU KARNATAKA KERALA POPULATION : CRORES ( 22% OF INDIA) AREA :- 651 (‘000 SQ KM)(19% OF INDIA) INSTALLED CAPACITY:- 31,931 MW(27.6%) WEATHER :- South-west monsoon North-east monsoon SEA COAST :- AROUND 4000 KM

7 ANDHRA PRADESH POPULATION :- 7.6 CRORES AREA :- 275 (‘000 SQ KM) NO OF CONSUMERS :- 162 LAKHS PER CAPITA CONS. :- 560 UNITS MAIN AGRICULTURE CROP :- RICE CLIMATIC CONDITION :- HOT AND HOT & HUMID SR STATES – GEOGRAPHY KARNATAKA POPULATION :- 5.3 CRORES AREA :- 192 (‘000 SQ KM) NO OF CONSUMERS :- 105 LAKHS PER CAPITA CONS. :- 389 UNITS MAIN AGRICULTURE CROP :- COFFEE & RAGI CLIMATIC CONDITION :- HOT AND HOT & HUMID KERALA POPULATION :- 3.2 CRORES AREA :- 39 (‘000 SQ KM) NO OF CONSUMERS :- 61 LAKHS PER CAPITA CONS. :- 300 UNITS MAIN AGRICULTURE CROP :- COCONUT & SPICES CLIMATIC CONDITION :- HUMID TAMIL NADU POPULATION :- 6.2 CRORES AREA :- 130 (‘000 SQ KM) NO OF CONSUMERS :- 152 LAKHS PER CAPITA CONS. :- 586 UNITS MAIN AGRICULTURE CROP :- SUGAR CANE & OIL SEEDS CLIMATIC CONDITION :- HOT AND HOT & HUMID PONDICHERRY POPULATION :- 9.7 LAKHS AREA :- 492 SQ KM PER CAPITA CONS. :- 165 UNITS CLIMATIC CONDITION :- HOT & HUMID

8 SR STATES – POWER SYSTEM STATISTICS ANDHRA PRADESH INSTALLED CAPACITY – 9531 MW MAX DEMAND MET – 7441 MW DAILY CONSUMPTION MAX – 166 MU DAILY CONSUMPTION AVG – 130 MU CONSUMER PROFILE – DOM INDU AGRI COMML OTHERS 22% 29% 34% 5% 10%. KARNATAKA INSTALLED CAPACITY – 5802 MW MAX DEMAND MET – 5445 MW DAILY CONSUMPTION MAX – 107 MU DAILY CONSUMPTION AVG – 84 MU CONSUMER PROFILE – DOM INDU AGRI COMML OTHERS 37% 26% 33% 3% 1%. KERALA INSTALLED CAPACITY – 2617 MW MAX DEMAND MET – 2426 MW DAILY CONSUMPTION MAX – 39 MU DAILY CONSUMPTION AVG – 34 MU CONSUMER PROFILE – DOM INDU AGRI COMML 76% 2% 6% 16%. TAMIL NADU INSTALLED CAPACITY – 7074 MW MAX DEMAND MET – 7228 MW DAILY CONSUMPTION MAX – 147 MU DAILY CONSUMPTION AVG – 126 MU CONSUMER PROFILE – DOM INDU AGRI COMML OTHERS 21% 33% 27% 9% 10%.

9 GROWTH OF INSTALLED CAPACITY OF SR IN MW

10 INSTALLED CAPACITY IN SR STATESHYDROTHERMALNUCLEARDIESEL/GASWINDOTHERSTOTAL % AP % KAR % KER % TN % C.S % IPP % TOTAL %34%50%3%12%1% NOTE:---- TAMILNADU HAS ABOUT 1344 MW OF WINDMILL POWER WHICH IS NOT INCLUDED IN THE INSTALLED CAPACITY. --- LIKEWISE MICRO AND CAPTIVE CAPACITIES ARE NOT INCLUDED

11 SOURCE-WISE INSTALLED CAPACITY OF SR IN MW 31,931 MW HYDRO THERMAL WIND NUCLEAR OTHERS GAS

12 AGENCY-WISE INSTALLED CAPACITY OF SR IN MW 31,931 MW ANDHRA PRADESH KARNATAKA TAMIL NADU CENTRAL SECTOR IPP KERALA

13 TYPICAL LOAD CURVE OF SR WINTER MONSOON SUMMER EVENING PEAK WEATHER RESERVOIRCONSUMPTION SCROLL DEMAND

14 LOAD COMPOSITION IN SOUTHERN GRID Domestic Industry Commercial Agriculture Others

15 LOAD MW LOAD MW TYPICAL LOAD SPREAD IN SR

16 SR GRID - HIGHLIGHTS WIDE SPREAD TRANSMISSION NETWORK HIGHEST CAPACITY HVDC LINK IN COUNTRY GENERATING UNITS OF VARIED TYPE & CAPACITYGENERATING UNITS OF VARIED TYPE & CAPACITY 32 Nos. of 400 KV SUB-STATIONS MVA TRANSFORMATION CAPACITY INTER-REGIONAL LINKS WITH ALL NEIGHBOURING REGIONSINTER-REGIONAL LINKS WITH ALL NEIGHBOURING REGIONS

17 GRID OPERATION IN THE PAST LOW FREQUENCY PROBLEMS –FREQUENCY AT 48 HZ AND BELOW FOR MOST TIME LOW VOLTAGE OPERATION –VOLTAGE AT BANGALORE DIPPED TO AS LOW AS 300 Kv!!!! FREQUENT GRID DISTURBANCES –LOADS FREQUENTLY CUT OFF DUE TO RELAY OPERATION INCREASED ELECTRICAL LOSSES –INEFFICIENT OPERATION OF ELECTRIC EQUIPMENTS

18 GRID OPERATION PRESENT  STABILISED SYSTEM FREQUENCY STABILISED SYSTEM FREQUENCY  IMPROVED VOLTAGES IMPROVED VOLTAGES  MERIT ORDER OPERATION MERIT ORDER OPERATION  INTER REGIONAL EXCHANGES INTER REGIONAL EXCHANGES  IMPROVED GRID SECURITY IMPROVED GRID SECURITY JAN - 02OCT - 04

19 LANDMARKS UNIFIED LOAD DESPATCH SCHEME AVAILABILITY BASED TARIFF TALCHER-KOLAR HVDC LINK OPERATIONAL EXCELLENCE SPECIFIC ACTIONS BY SRLDC FINANCIAL DISCIPLINE SCHD DRWL

20 EXPANSION GENERATION ADDITION & SYSTEM STRENGTHENINGGENERATION ADDITION & SYSTEM STRENGTHENING FUTURE PROJECTSFUTURE PROJECTS

21 ISSUES OF IMPORTANCE HIGH VOLTAGE CONTROL DURING OFF-PEAK PERIODHIGH VOLTAGE CONTROL DURING OFF-PEAK PERIOD TALCHER-KOLAR SPECIAL PROTECTION SCHEMETALCHER-KOLAR SPECIAL PROTECTION SCHEME LOAD-GENERATION BALANCE INTRA-STATE ABTINTRA-STATE ABT 3D FREQNTPCHYDRO

22

23 MONSOONS SOUTH WEST MONSOON NORTH EAST MONSOON

KHAMMAM VIJAYAWADA NAGARJUNASAGAR VISAKHAPATNAM (POWERGRID) HYDERABAD RAICHUR GOOTY HOODY SALEM UDUMALPET TRICHUR MADURAI TRICHY MADRAS NEYVELI CUDDAPAH DAVANAGERE KAIGA RSTPP BHADRAVATI 130x2 164x x2 PONDICHERY BANGALORE SIRSI MUNIRABAD P P P P P P P P P P P P P P P N KOLAR PALLOM KAYANKULAM EDAMON TALCHER JEYPORE x78 2x HOSUR KADRA KODASAALY Nagjhari MAPS P SSLMM MMDP THIRUVANATHAPURAM ALMATHI NELLORE 400 KV LINE PRESENTLY OPERATED AT 220 KV NELAMANGALA KURNOOL GAZUWAKA(AP) SIMHADRI NTPC HIRIYUR x x2 221x2 146x2 52x2 197x2 301x2 8x4 15x ABOUT CKM 400KV TRANSMISSION TALGUPPA GRID MAP TYPICAL FLOWS ARE FROM NORTH TO SOUTH GRID FOCAL POINT SHIFTED TO KOLAR AFTER COMMISSIONING OF HVDC QUANTUM CHANGES IN FLOW PATTERN LIKELY AFTER COMMISSIONING OF KOODANKULAM 2000 MW KOODANKULAM THIRNELVALI

25 TRANSMISSION IN SOUTHERN INDIA ABOUT 2800 CKM OF 400 KV LINES ADDED IN THE PAST 2 YEARS VOLTAGE LEVELAPKARKERTNCGS TOTAL 400 KV /230 KV /110 KV TOTAL

26 Kolar Chintamani Cudappah Hoody Hosur Salem Udumalpet Madras B’lore +/- 500 KV DC line 1370 KM Electrode Station Electrode Station TALCHER 400kv System 220kv system KOLAR TALCHER KOLAR SCHEMATIC

GENERATING UNITS IN SOUTHERN REGION A.P KAR TNKER GENERATORS ABOVE 1000 MW GENERATORS 500 – 1000 MW GENERATORS BELOW 500 MW TYPICAL GENERATOR SPREAD IN SR UNIT CAPACITYAPKARKERTNCGSTOTAL THERMAL (500 MW) 279 THERMAL ( MW) GAS/THERMAL ( MW) HYDRO (>50 MW) TOTAL HYDRO - THERMAL - GAS / NAPTHA - NUCLEAR

28 GENERATING UNITS AND CAPACITY UNIT CAPACITY APKARKERTNCGSTOTAL THERMAL(500 MW) 279 THERMAL ( MW) GAS/THER( MW) HYDRO(>50 MW) TOTAL

KHAMMAM VIJAYAWADA NAGARJUNASAGAR GAZUWAKA HYDERABAD RAICHUR GOOTY HOODY SALEM UDUMALPET TRICHUR MADURAI TRICHY MADRAS NEYVELI CUDDAPAH DAVANAGERE RAMAGUNDAM BANGALORE MUNIRABAD P P P P P P P P P P P P P P P KOLAR 63 HOSUR 1 60 P NELLORE NELAMANGALA KURNOOL KALPAKKA SIMHADRI HIRIYUR TALAGUPPA MAMIDIPALLY SRI SAILAM -- OF NTPC -- OF ANDHRA PRADESH -- OF KARNATAKA -- OF NLC -- OF POWERGRID 400KV SUB-STATIONS IN SR NEYVELI TPS I (EXP) POWERGRIDSTATEOTHERSTOTAL AP KAR 45 9 KER 1 1 TN 6 28 TOTAL

30 ICT SUMMARY IN SOUTHERN INDIA VOLTAGE RATIOAPKARKERTNCGS TOTAL 400/230 or 400/220 KV /132 or 400/110 KV TOTAL

31 POWERGRID SRLDC A.P KAR T.N KER MAH ORISSA RAMAGUNDAM NEYVELI MAPS GOA PONDICHERRY CHANDRAPUR JEYPORE GAZUWAKA KOLHAPUR BELGAUM U.SILERU L.SILERU BALIMELA BARSUR CSEB AMBEWADI INTER REGIONAL LINKS HVDC BI POLE HVDC B2B STATION CENTRAL GEN.STATION 220 kV LINE 400 kV LINE 110 kV HVDC LINE KOLAR TALCHAR KAIGA

Inter Regional Links Present IR Capacity = 9,000 MW 700 MW 1200MW 2000MW 900 MW 30,500 MW 16,000 32,700 MW 30,500 MW MW 1650 MW

MW 1000 MW 6450 MW 4600 MW 1300 MW 3200 MW 30,000 MW OF INTER- REGIONAL POWER BY 2012 EASTERN REGION SOUTHERN REGION WESTERN REGION NORTHERN REGION NORTH- EASTERN REGION INTER-REGIONAL TRANSFER BY END OF 11 th PLAN (2012)

34 STABILISED SYSTEM FREQUENCY TYPICAL FREQUENCY CURVE SCATTER DIAGRAM HISTOGRAM OF FREQUENCY FREQUENCY DURATION CURVE Df/dT CURVE RECORD FVI OF 0.04

35 FREQUENCY PROFILE 2002, 2003 & 2004

< & < & < & Above MaxMinAvgFVISt. Dev

37 REALITY BITE: FARMERS IN KARNATAKA ARE HAPPY WITH FEWER HOURS OF QUALITY POWER!!. EFFICIENCY OF PUMPS AT TG HALLI WATER WORKS IMPROVED! COMPARISION OF BANGALORE VOLTAGE-TYPICAL DAY BETTER VOLTAGE PROFILE MEANS LESS ELECTRICAL LOSSES

38 WATER SUPPLY TO BANGALORE LOW VOLTAGE PROBLEMS AROUND BANGALORE HAMPERED WATER SUPPLY EARLIER WITH BETTER VOLTAGE NOW, PUMPING EFFICIENCY HAS IMPROVED 400 KV STATION AT MYSORE BEING COMMISSIONED ON WAR FOOTING TO FURTHER FORTIFY THIS PART OF THE GRID PUMPING LOSSES REDUCED ENORMOUS SAVINGS TO THE STATE MOTOR BURNING AND MAINTENANCE COSTS ALSO CAME DOWN DRASTICALLY

39 ABOUT 7000 MW OF CAPACITY IS BELOW 100 Ps ABOUT14200 MW OF CAPACITY IS BELOW 200 Ps ABOUT MW OF CAPACITY IS BELOW 300 Ps CUM. INS. CAP.

40

41 MERIT ORDER : UNITS BOXED UP POWER STATIONSTATE CAPACITY(MW) FUEL VARIABLE COST TATA DIESELKARNATAKA 79 DIESEL308 RAYALSEEMA DGPPKARNATAKA 27 DIESEL360 YELEHANKA DIESELKARNATAKA 128 DIESEL314 THANRBHAVIKARNATAKA 220 NAPTHA325 SUB-TOTAL 454 BRAHAMPURAM DPPKERALA 107 DIESEL275 BSESKERALA 157 NAPTHA308 KASARGODE PCLKERALA 22 NAPTHA298 KAYAMKULAMKERALA 360 NAPTHA322 SUB-TOTAL 646 BASIN BRIDGETAMIL NADU 120 NAPTHA584 P.P.NALLURTAMIL NADU 330 NAPTHA415 SUB-TOTAL 450 TOTAL 1550

42

43 (+) IMPORT / (-) EXPORT INTER REGIONAL UI (WR): MU – 211 MU INTER REGIONAL UI (ER): MU – 21 MU AVG RATE OF IMPORT FROM WR IN PS/U –134 –247 AVG RATE OF EXPORT TO WR IN PS/U –163 –287 AVG RATE OF IMPORT FROM ER IN PS/U –145 ER –212 SR INTER – REGIONAL(01/01/03 TO 10/10/04)

44 MAJOR AND MINOR DISTURBANCES SINCE 1994 NO DISTURBANCES DESPITE LOSING ENTIRE SUPER GENERATING PLANTS LIKE RAMAGUNDAM,VIJAYAWADA,KOTHAGUDEM, NORTH CHENNAI, SHARAVATHY ETC SPS

45 DEEP VALLEY SHARP PEAK

46 KADAMPARAI PUMP OPERATION GENERATOR MODE PUMP SAVINGS OF RS 40 LAKHS EVERY DAY INVESTMENT OF 1600 CRORES SAVED

47 OPTIMAL RESERVOIR UTILISATION IDUKKI IN KERALA KERALA SAVED RS 50 CRORES BY EFFICIENT UTILISATION OF THE RESERVOIRS AT IDUKKI! POWERGRIDs 400 KV MADURAI- TRIVANDRUM LINE WILL HELP KERALA SAVE EVEN MORE ENERGY IN THE COMING YEAR PLANT OPERATORS AT IDUKKI THINK OF THE RESERVOIR LEVEL IN RUPEES RATHER THAN IN FEET!!! Rs.

48 FREQUENCY CURVE FOR 9 th SEPTEMBER 2004 FVI = 0.04 Avg Freq = 49.99Hz 10 * ∑ (F – 50) 2 FVI = * 60

49 SPECIFIC ACTION BY RLDC  LOSS REDUCTION TAP CO-ORDINATION FILTER CO-ORDINATION REDUCED LINE OPENING HVDC SET POINT CHANGES VAR MANAGEMENT  REVIVAL OF DORMANT INTER-STATE LINES  100% DISBURSEMENT IN SETTLEMENT SYSTEM  OPTIMISATION OF INTER-REGIONAL EXCHANGES  MERIT ORDER OPERATION

50 TALCHER-KOLAR INTER –TRIP SCHEME (STAGE-1) IN THE EVENT OF TRIPPING OF TALCHER-KOLAR POLE/BIPOLE, INSTANTANEOUS AND IMMEDIATE 500MW LOAD RELIEF IS OBTAINED FROM THE FOLLOWING SUBSTATIONS : -KARNATAKA: HOODY, KOLAR -TAMILNADU: SRIPERAMBADUR, HOSUR -ANDHRA PRADESH: CHINKAMPALLI Note: This scheme is already in vogue

51 TALCHER-KOLAR INTER –TRIP SCHEME (STAGE-2) IN THE EVENT OF TRIPPING OF TALCHER-KOLAR BIPOLE ADDITIONAL 1000MW LOAD RELIEF TO BE OBTAINED FROM THE FOLLOWING SUBSTATIONS : -KARNATAKA: SOMANAHALLI -TAMILNADU: MADURAI,THIRUVARUR,INGUR,KAIRAKUDDY -ANDHRA PRADESH: SOMAYAJULAPALLI, GOOTY, ANANTAPUR, KARNOOL -KERALA: TRICHUR NORTH, KOZHI-KODE

52 GENERATION ADDITION & SYSTEM STRENGTHENING ( RECENT PAST ) GENERATION ADDITION 500MW TALCHER U # 5 ON COMMERCIAL OPERATION W.E.F 1 ST NOV MW U#7 AT NTPC, RAMAGUNDAM TEST SYNCHRONISED ON 26-SEP-04. SYSTEM STRENGTHENING 220KV INTER-STATE LINES OF AP – KAR IN PARALLEL –SEDAM – TANDUR FROM 18-AUG-04 –GOOTY – ALIPUR FROM 10-SEP-04 40% FIXED SERIES COMPENSATION COMMISSIONED AT –GOOTY OF GOOTY-HOODY LINE ON 19/OCT/04 FLOW INCREASED FROM 110MW TO 140MW. –CUDDAPAH OF N’SAGAR-CUDDAPAH D/C LINE ON 20-21/OCT/04 FLOW INCREASED FROM 270MW TO 355MW. 400KV RAMAGUNDAM – HYDERABAD III & IV ON COMMERCIAL OPERATION FROM 01-NOV-04.

53 Components of inter-utility tariff (Pre – ABT Mechanism)  Fixed charges  Interest on loans  Depreciation  O & M charges  Return on equity  Interest on Working Capital  Energy charges (fuel cost)  Incentives  Surcharge & other levies  No charge for reactive energy

54 Payment to Inter State Generating Stations (ISGS) from beneficiaries under Availability Based Tariff (ABT)  Capacity charges  Energy charges  Unscheduled Interchange (UI)

55

56 CAPACITY CHARGE Capacity charge will be related to ‘availability’ of the generating station and the percentage capacity allocated to the state. ‘Availability’ for this purpose means the readiness of the generating station to deliver ex-bus output expressed as a percentage of its rated ex-bus output capability.

57 ENERGY CHARGE Energy charges shall be worked out on the basis of a paise per kwh rate on ex- bus energy scheduled to be sent out from the generating station as per the following formula Energy charges = Rate of energy charges (paise/kwh) x Scheduled Generation (ex-bus MWh)

58 UNSCHEDULED INTERCHANGE (U I) :  Variation in actual generation / drawal with respect to scheduled generation / drawal shall be accounted for through Unscheduled Interchange (UI).  UI for generating station shall be equal to its total actual generation minus its scheduled generation.  UI for beneficiary shall be equal to its total actual drawal minus its total scheduled drawal.

59 UNSCHEDULED INTERCHANGE (U I) :  UI shall be worked out for each 15 minute time block.  Charges for all UI transactions shall be based on average frequency of the time block.  UI rates shall be frequency dependent and uniform throughout the country.

60 UI RATE Rate of Unscheduled Drawal/Injection Frequency (Hz)Rate (p/u) Above and below570

61 AVAILABILITY BASED TARIFF (A)CAPACITY CHARGE (B)ENERGY CHARGE (C)ADJUSTMENT FOR DEVIATIONS (U I CHARGE) (A) = a function of the Ex-Bus MW availability of Power Plant for the day declared before the day starts x SEB’s % allocation from the plant (B) = MWh for the day as per Ex-Bus drawal schedule for the SEB finalised before the day starts x Energy charge rate (C) = Σ (Actual energy interchange in a 15 minute time block – scheduled energy interchange for the time block) x UI rate for the time block TOTAL PAYMENT FOR THE DAY = (A) + (B) ± (C)

62 FEATURES :  ( A) and (B) do not depend on actual plant generation / drawal. No metering required for this as they are based on off-line figures. All deviations taken care of by (C)  No complication regarding deemed generation.  Perpetual incentive for maximizing generation and reducing drawal during deficit, but no incentive to over generate during surplus.

63 TALCHER-KOLAR INTER –TRIP SCHEME (STAGE-1) IN THE EVENT OF TRIPPING OF TALCHER-KOLAR POLE/BIPOLE, INSTANTANEOUS AND IMMEDIATE 500MW LOAD RELIEF IS OBTAINED FROM THE FOLLOWING SUBSTATIONS : -KARNATAKA: HOODY, KOLAR -TAMILNADU: SRIPERAMBADUR, HOSUR -ANDHRA PRADESH: CHINKAMPALLI Note: This scheme is already in vogue

64 HIGH SPEED INTER-TRIP SCHEME AT KOLAR GOOTY HOODY SALEM TRICHUR MADURAI TRICHY SPBDR NLC II CUDDAPAH PONDICHERY SOMANHALLI KOLAR HOSUR NLC -1 EXP. KOZIKODE UDUMALPET NLC II EXP BAHOOR KURNOOL ANANTPUR KARAIKUDI THIRUVARUR INGUR SOMYAZULA PALLI TO TALCHER

65 TALCHER-KOLAR INTER –TRIP SCHEME (STAGE-2) IN THE EVENT OF TRIPPING OF TALCHER-KOLAR BIPOLE ADDITIONAL 1000MW LOAD RELIEF TO BE OBTAINED FROM THE FOLLOWING SUBSTATIONS : -KARNATAKA: SOMANAHALLI -TAMILNADU: MADURAI,THIRUVARUR,INGUR,KAIRAKUDDY -ANDHRA PRADESH: SOMAYAJULAPALLI, GOOTY, ANANTAPUR, KARNOOL -KERALA: TRICHUR NORTH, KOZHI-KODE NOTE : NECESSARY WIDE BAND AND PLCC COMMUNICATION LINKS AND OTHER LOGISTICS TO BE PROVIDED AND IMPLEMENTED BY POWERGRID AND RESPECTIVE STATES

66 APKARKERTNPONDY Net UI exported(-) / Imported(+) in MUs Net amount paid in Crores Rs Average rate of UI in paise/unit SUMMARY OF UI – 93 WKS (FROM 01/JAN/03 TO 10/OCT/04)

67 UI IN SR (FROM 01/01/03 TO 10/10/04) TOTAL UI TURNOVER : MU TOTAL UI AMOUNT DISBURSED: CR AVG WEEKLY TRANSACTION:- 60 MU AVG WEEKLY UI AMOUNT DISBURSED: CR

68 PAYMENT STATUS IN REGARD TO UI UPTO 93 WKS ( TILL 10/10/04) 1.NET ENERGY TRANSACTION IS 146 MU (IMPORT BY SR). 2.AMOUNT ACCRUED IN SREB – IRE DUE TO DIFF. IN WR A/C = 41.83Crs 3.AMOUNT TO BE ACCRUED IN WREB – IRE DUE TO DIFF. IN SR A/C = 27.71Crs 4.AMOUNT DUE TO SR CONSTITUENTS ON 50:50 BASIS = 34.73Crs 5.AMOUNT ALREADY DISBURSED TO SR CONSTITUENTS = 33.39Crs FOR INTER-REGIONAL TRANSACTIONS FOR INTRA-REGIONAL TRANSACTIONS THE UI SETTLEMENT WITHIN THE REGION IS UP-TO-DATE

69

70 G1 G2 SERC SLDC SEB/STU State Govt. RLDC REB CTU CERC Central Govt. CEA ISTS ISGS Load L1L2 Intra State System IEGC to Operate on the periphery X=- GLG

71 COORDINATES/ RLDC REGIONAL GRID IPP STATE GENR. SHARE CENTRAL

72 HOW DID THE LOSSES GET REDUCED IN THE SOUTHERN REGION? VOLTAGE IMPROVEMENT IS THE MAIN REASON POWER = VOLTAGE X CURRENT LOSS ≈ CURRENT 2 FOR EXAMPLE –440 W = 220 VOLTS X 2 AMPS –LOSS ≈ 4 WATTS –440 W = 160 VOLTS X 2.75 AMPS ( AT REDUCED VOLTAGE) –LOSS ≈ 7.6 WATTS ( NEARLY DOUBLE!)

73 PROJECTS IN PROGRESS IN SOUTHERN REGION 400 KV MADURAI-TRIVANDRUM LINE WITH 400 KV SS AT TRIVANDRUM 400 KV NELAMANGALA-MYSORE LINE WITH 400 KV SUBSTATION AT MYSORE 400 KV KAIGA-NARENDRA LINE ALONG WITH 400 KV SUB STATION AT NARENDRA 400 KV HYDERABAD-KURNOOL-GOOTY LINE 400 KV 2 nd GOOTY-BANGALORE LINE 400 KV RAICHUR-GOOTY D/C QUAD LINE 400 KV RING MAIN AROUND BANGALORE 400 KV RING MAIN AROUND CHENNAI

74 PROJECTS IN SOUTHERN REGION 400 KV RAMAGUNDAM – HYDERABAD-GOOTY- NELAMANGALA LINE: RS 390 CRORES ADDITIONAL 500 MW HVDC POLE AT GAZUWAKA: WORTH Rs 770 CRORES ENHANCEMENT OF CAPACITY OF TALCHER POLES BY 500MW (FROM 2000 MW TO 2500 MW FOR UTILISATION DURING EMERGENCY ONLY): Rs 90 CRORES SYSTEM AUGMENTATION SCHEMES : Rs 415 CRORES KOODANKULAM NUCLEAR PLANT EVACUATION SCHEME – 2000 MW CAPACITY- WORTH ABOUT Rs 1700 CRORES ANOTHER HVDC LINK TO SR FROM ER/WR SYSTEM EXPANSION SCHEMES WORTH Rs 1233 CRORES

75 THE FIRST SCHEME: 1996

76 THE FIRST SCHEME: 1996 CONDITIONS Line NameFrequency Below (Hz) POWER FLOW(MW) Time delay (second) Type of Relay CUDAPPA-MADRAS UF SALEM- BANGALORE 47.81UF CUDAPPA-MADRAS MW towards CUDAPPA 0.5RPUF SALEM- BANGALORE MW towards BANGALORE 1RPUF

77 SPECIAL PROTECTION SCHEMES DEFINITION PROTECTION SCHEME DESIGNED TO DETECT ABNORMAL SYSTEM CONDITIONS AND TAKE DETECT ABNORMAL SYSTEM CONDITIONS AND TAKE PREDETERMINED CORRECTIVE ACTION (Other than isolation of faulty element) (Other than isolation of faulty element)TO PRESERVE SYSTEM INTEGRITY AND PROVIDE ACCEPTABLE SYSTEM PERFORMANCE

78 WHY SPS? OPERATIONAL REASONS OUTAGE OF HIGH CAPACITY GENERATING UNITS,HVDC INTERCONNECTION OF LARGE TRANSFER CAPABILITY OUTAGE OF HIGH CAPACITY GENERATING UNITS,HVDC INTERCONNECTION OF LARGE TRANSFER CAPABILITY WIDE SEASONAL FLUCTUATION IN LOADING PATTERN WIDE SEASONAL FLUCTUATION IN LOADING PATTERN STAGGERING AND ROSTERING OF LOADS STAGGERING AND ROSTERING OF LOADS SUDDEN IMPACT ON LARGE GRIDS DUE TO SYATEM DYANAMICS AND SWINGS. SUDDEN IMPACT ON LARGE GRIDS DUE TO SYATEM DYANAMICS AND SWINGS.

79 WHY SPS? COMMERCIAL REASONS SKEWED GENERATION AND LOAD PATTERN AND PRESSURE ON RELIABILITY MARGINS DUE TO SKEWED GENERATION AND LOAD PATTERN AND PRESSURE ON RELIABILITY MARGINS DUE TO DRIVEN BY COMMERCIAL MECHANISMS DRIVEN BY COMMERCIAL MECHANISMS OPEN ACCESS INCREASE IN TRADE VOLUME OPEN ACCESS INCREASE IN TRADE VOLUME INCREASE IN COMPETITION INCREASE IN COMPETITION MERIT ORDER OPERATION MERIT ORDER OPERATION

80 WHY SPS? PLANNING ISSUES ECONOMY OF SCALE ECONOMY OF SCALE THE SYSTEM PLANNERS TEND TO UTILIZE THE EXISTING NETWORK THE SYSTEM PLANNERS TEND TO UTILIZE THE EXISTING NETWORK DELAYS IN NETWORK EXPANSION DUE TO ENVIRONMENTAL PROBLEMS DELAYS IN NETWORK EXPANSION DUE TO ENVIRONMENTAL PROBLEMS SEASONAL OVER LOADS SEASONAL OVER LOADS LINES AND GENERATORS NOT COMING IN TANDEM LINES AND GENERATORS NOT COMING IN TANDEM

81 WHY SPS? Mission of power system engineers is to provide Stable Secured and Reliable power supply at least possible cost to the end consumer. SPS is an important tool in achieving this Mission of power system engineers is to provide Stable Secured and Reliable power supply at least possible cost to the end consumer. SPS is an important tool in achieving this For System Planner It reduce the compromise between cost and quality For System Planner It reduce the compromise between cost and quality For operational planner It enables to manage severe contingencies like tripping of generators multiple outage of transmission lines etc For operational planner It enables to manage severe contingencies like tripping of generators multiple outage of transmission lines etc

82 POSSIBLE SYSTEM PROLEMS UNIT FAILURE INSUFFICIENT GENERATION TRANSFORMER/ LINE FAILURE LOSS OF LOAD REDUCED NETWORK REDUNDANCY LINE OVERLOAD OR UNSATISFACTORY BUS VOLTAGE BUS ISOLATED LOSS OF GENERATION ISLANDING SYSTEM COLLAPS E

83 RESTORATIVE NORMAL A L E R T EMERGENCY DISTURBANCE

84 RESTORATIVE NORMAL A L E R T EMERGENCY DISTURBANCE

85 INDUSTRY EXPERIENCE WITH SPS INDUSTRY EXPERIENCE WITH SPS REPORTED SCHEMES111 REPORTED SCHEMES111 FIRST SPS INSTALLEDIN 1930 FIRST SPS INSTALLEDIN 1930 SCHEMES REPORTED BY GEOGRAPHICAL REGIONS SCHEMES REPORTED BY GEOGRAPHICAL REGIONS GEOGRAPHICALREGION % OF SCHEMES GEOGRAPHICALREGION USA20.7%EUROPE16.2% JAPAN20.7%AUSTRALIA9% CANADA19.8%OTHERS13.6% SURVEY IS ONLY INDICATIVE

86 HIGH SPEED INTER-TRIP SCHEME AT KOLAR GOOTY HOODY SALEM TRICHUR MADURAI TRICHY SPBDR NLC II CUDDAPAH PONDICHERY SOMANHALLI KOLAR HOSUR NLC -1 EXP. UDUMALPET BAHOOR KURNOOL SOMYAZULA PALLI TO TALCHER

87 HIGH SPEED INTER-TRIP SCHEME AT KOLAR MODE OF OPERATION POWER LEVEL FOR GENERATING INTERTRIP SIGNAL MONO POLAR >400 MW AND THE POLE TRIPS BI-POLAR IF BOTH POLE ARE CARRYING > 800 MW EACH AND ONE POLE TRIPS IF EACH POLE IS CARRYING POWER IN THE RANGE OF 400 TO 800 MW AND ONE POLE TRIPS AND AFTER THE DELAY OF 2 SECS THE POWER ON SURVIVING POLE IS LESS THAN 600MW IF POWER FLOW ON EACH POLE > 200 MW AND BOTH POLES TRIP WITH IN 2 SECS

88 KAIGA EVACUATION PROBLEM SPS BASED SOLUTION KAIGA 440 MW SIRSI KADRA 150 MW KODASHALLI 120 MW GUTTUR NAGJHERI 855 MW HUBLI 400 KV LINE OPERATED AT 220 KV PROBLEM OF OVERLOADING WHEN HIGH GENERATION AT KALI COMPLEX THESE LINES ARE TRIPPED IF >600 AMPS FOR 1SEC OR > 900 AMPS FOR 300 MSEC,

89 PROPOSED SPS AT RAICHUR RAICHUR N ’ SAGAR MUNIRABAD DAVANGERE HIRIYUR NELAMANGALA HOODY GOOTY CUDDAPAH KOLAR HVDC LINES FROM ER SOMANAHALLY TRIPPING OF THESE LINES INCREASES THE FLOW ON RAICHUR-N ’ SAGAR LINE LOAD CENTRE PROPOSED SPS BASED SOLUTION RTPS UNITS TO BACK- DOWN BASED ON FLOW ON RAICHUR-N ’ SAGAR LINE

90 ULDC PROJECT HIGHLIGHTS MOU signed with each constituent of SR MOU signed with each constituent of SR Last quarter 1992 Last quarter 1992 CEA Clearance – Feb 1993 CEA Clearance – Feb 1993 PIB Clearance – March 1993 PIB Clearance – March 1993 Environmental clearance – May 1993 Environmental clearance – May 1993 Engaged M/s KEMA-ECC, USA, an Internationally reputed Consultants towards consultancy services Engaged M/s KEMA-ECC, USA, an Internationally reputed Consultants towards consultancy services CCEA – February 1995 CCEA – February 1995 AWARDED IN JAN 1998 AWARDED IN JAN 1998 COMPLETED ON SCHEDULE :- JAN 2002 COMPLETED ON SCHEDULE :- JAN 2002

91 Packages under ULDC scheme Sl No: PackageContractor Contract Value 1 EMS/SCADA System GE Harris, USA Rs. 148 Crores 2 Fibre Optic System PIRELLI, Italy Rs.100 Crores 3 Microwave System ALSTOM, France Rs. 63 Crores 4PLCC/PABX Puncom, Punjab Rs. 4 Crores 5 Auxiliary Power supply package TATA LIEBERT, Mumbai Rs.6 Crores 6 Control Centre Facilities renovation/construction Awarded separately by each Constituent

92 RLDC,Bangalore KalamasseryHyderabad Bangalore Chennai Cuddapah Warangal Vijayawada Kalam’erry Kannur Trivandrum Chennai Erode Madurai Bangalore Lingusugur Hubli CPCC SCC, Pondy Hyderabad Hierarchy of The ULDC Scheme in Southern Region Andhra KeralaTamilnaduKarnataka

93 EMS/SCADA Package … Contd Sl No: Constituent RTUs supplied RTUs supplied Existing RTUs integrated Control Centres 1.0APTRANSCO TNEB KPTCL KSEB UT of Pondy Central Sector Total RTUs Grand Total : 280 RTUs Grand Total : 280

94 Andhra Pradesh Karnataka Kerala Tamilnadu UT of Pondy Vijayawada Warangal HYDERABAD Ghanapur Chinkampalli CHENNAI Pondy Madurai Kannur-B KALAMASSERY Vydyuthi Bhavanam Erode MW Link FO Link State owneed Link Sub-LDC SLDC RCLDC Hubli Davangeree Bangalore Information Flow to Control Centres Satellite Ramagundam

95 Communication Channel for Information flow Sub-LDC SLDC RLDC SLDC Sub-LDC RTU Wide Band / PLCC Commn Wide Band Commn Wide Band Commn (MW / FO) RTU

96 ULDC TRAINING SLNAME OF THE TRAININGFROMTO ParticipantsMan days 1 CISCO ROUTER & NETWORKING XA-21 USER LEVEL RTNA WORKSHOP AIX OPERATING SYSTEM XA-21 USER LEVEL DATABASE ADMINISTATION

97 Annual Inter-Regional Energy Transfer ≈10,000MU Transformation Capacity ≈ MVA Transformers (220kV and above) 480 nos. Installed Capacity ≈31870 MW Integrated Opn of Ten Power Utilities Dynamic Grid Conditions Southern Region Grid Complexities in Monitoring & Control Generators –Hydro, Thermal,Gas/IPP 422 nos. Transmission Network 400/220kV ≈ Ckm 40,000 POINTS Active Power, Reactive Power, Voltage, Frequency, Transformer Tap Position, Circuit Breaker Position, Isolator Position etc.

98 B ouquet of B enefits Integrated System Operation with improved system visibility Enhanced Operation Efficiency Quality Power - Frequency and Voltage Control Merit Order and Economic Load Dispatch Fewer System Collapses & Faster Restoration First Step towards Sub-station Automation Adaptability to the ever growing Power System

99 HVDC STATION KOLAR (KARNATAKA ) TALCHER ORISSA ) TALCHER KOLAR HVDC LINE LENGTH:1400 KMS

100 TALCHER KOLAR LINK ONE OF THE LONGEST HVDC LINES IN THE WORLD ONE OF THE LONGEST HVDC LINES IN THE WORLD DESIGNED TO EVACUATE 2000 MW DESIGNED TO EVACUATE 2000 MW COMMISSIONED IN ADVANCE TO UTILISE NON-PEAK SURPLUS POWER OF EASTERN REGION COMMISSIONED IN ADVANCE TO UTILISE NON-PEAK SURPLUS POWER OF EASTERN REGION COMMISSIONED 9 MONTHS AHEAD OF SCHEDULE COMMISSIONED 9 MONTHS AHEAD OF SCHEDULE THE PROJECT HAS USED APPROXIMATELY 90,000 TONNES OF STEEL AND 16,000 KM OF CABLES THE PROJECT HAS USED APPROXIMATELY 90,000 TONNES OF STEEL AND 16,000 KM OF CABLES

101 TALCHER KOLAR HVDC LINK BENEFITS TO SOUTHERN REGION SUBSTANTIAL IMPROVEMENT IN THE VOLTAGE PROFILE FOR THE REGION. SUBSTANTIAL IMPROVEMENT IN THE VOLTAGE PROFILE FOR THE REGION. TRUNK LINE LOADINGS EASED – INCREASED TRANSFER MARGIN. TRUNK LINE LOADINGS EASED – INCREASED TRANSFER MARGIN. MAX IMPORT FROM ER 1600 MW MAX IMPORT FROM ER 1600 MW MORE DEMAND IS BEING MET. MORE DEMAND IS BEING MET. DEPLETED HYDRO RESERVES IS BEING CONSERVED. DEPLETED HYDRO RESERVES IS BEING CONSERVED. AVERAGE COST OF POWER IS BROUGHT DOWN AVERAGE COST OF POWER IS BROUGHT DOWN SURPLUS IN ER EFFECTIVELY UTILISED SURPLUS IN ER EFFECTIVELY UTILISED PERFORMANCE IMPROVEMENT OF POWER STATIONS IN EASTERN REGION PERFORMANCE IMPROVEMENT OF POWER STATIONS IN EASTERN REGION INCREASED STOA TRANSACTIONS INCREASED STOA TRANSACTIONS

102 TALCHER-KOLAR IMPORT OF 12728MUs FROM ER THROUGH TALCHER-KOLAR UPTO OCT-04 YEAR ---> MONTHS TOTAL ENERGY (IN MU) MAX FLOW (IN MW) TOTAL ENERGY (IN MU) MAX FLOW (IN MW) TOTAL ENERGY (IN MU) MAX FLOW (IN MW) JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC TOTAL MAX

103

104

105 RESERVOIR LEVEL - COMPARISON LEVEL IN MTS LEVEL30-Nov-03LEVEL30-Nov-04 JALAPUT LINGANMAKKI SUPA IDUKKI KAKKI NILGIRIS TOTAL ENERGY30-Nov-03ENERGY30-Nov-04 RISE IN MU % RISE Only 7500MUs Reserve till next monsoon (6 Months) 40 MUs/day could be generated as against about 70 MUs/day at present.

106 GRID OPERATION: A TIGHT ROPE WALK BLACK-OUT VOLTAGE COLLAPSE IN-ECONOMIC OPERATION INSTABILITY POWER SWINGS INCREASED LOSSES