11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design.

Slides:



Advertisements
Similar presentations
WBS: Lowest level OBS: Lowest level
Advertisements

Developing a Project Plan CHAPTER SIX Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Developing a Project Plan CHAPTER SIX Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Chapter 6: Developing a Project Plan
Project Management 6e..
Developing the Project Plan
PRJ566 Project Planning and Management Lecture: Network Diagrams.
PRJ566 Project Planning and Management Lecture: Dependencies and Network Diagrams.
Project Management Project Management
Developing a Network Plan
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
Network Diagramming Network Analysis  The common term for network analysis is PERT  PERT stands for Program Evaluation and Review Technique  The word.
Project Management Project  A series of related jobs usually directed toward some major output and requiring a significant time to perform Project management.
Developing a Project Plan
PROJECT MANAGEMENT. Outline What is a “project”? Project Management Objectives and tradeoffs Planning and Control in Projects Scheduling Methods Constant-Time.
Gantt Chart Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule Slack amount.
CSSE 372 Week 6 Day 2 Constructing and Analyzing the Project Network Diagram  PERT Chart PERT was invented for the Nautilus submarine project. Ok, maybe.
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
Chapter 4: Schedule, cost, and situation analysis (pt. 1) ISE 443 / ETM 543 Fall 2013.
Tutorial 2 Project Management Activity Charts (PERT Charts)
Creating the Project Plan
MGMT 483 Week 8 Scheduling.
5/4/20151 NETWORK SCHEDULING TECHNIQUES. 5/4/20152 Network Diagrams  PMI defines the scheduling process as: “the identification of the project objectives.
Project Networks. A,4 B,3 C,4 D,6 E,3 H,6 F,5 G,4 I,2 St,0 Fin,0 Example Network - terminology C,t Activity Duration of Activity (ES, LS) Early Start.
Project Management OPER 576 Project Networks Greg Magnan, Ph.D. April 29, 2004.
Project Management: A Managerial Approach
Project Scheduling: Networks, Duration Estimation, and Critical Path
PERT/CPM Models for Project Management
Projects: Critical Paths Dr. Ron Lembke Operations Management.
Importance of Project Schedules
Roberta Russell & Bernard W. Taylor, III
OM480 Defining the Project Parameters – Scheduling 101 (With Material from the Text Authors)
Time Management Ahmed Awad, Ph.D., PMP. Time Management It includes the processes required to ensure timely completion of the project. b Activity Definition.
Operations Management Contemporary Concepts and Cases Chapter Fourteen Project Planning and Scheduling Copyright © 2011 by The McGraw-Hill Companies,
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall o P.I.I.M.T o American University of Leadership Ahmed Hanane, MBA, Eng, CMA, Partner.
Where We Are Now. Where We Are Now Developing the Project Plan The Project Network A flow chart that graphically depicts the sequence, interdependencies,
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Developing a Project Plan Chapter 6.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
ENGM91 ACTIVITY PLANNING Unit 2
1 Project Management Chapter Lecture outline Project planning Project scheduling Project control CPM/PERT Project crashing and time-cost trade-off.
Project Management: A Managerial Approach
Project Scheduling Project Management 517 Chapter 8 Prof. M. Anvari
1 Project Planning, Scheduling and Control Project – a set of partially ordered, interrelated activities that must be completed to achieve a goal.
IENG 248 D. H. Jensen 6/2/2016Engineering Graphics & 3-D Modeling1 Lecture 08 Working Drawings.
Project Management Chapter 16. MGMT 326 Foundations of Operations Introduction Strategy Managing Projects Quality Assurance Facilities Products & Processes.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
University of Sunderland CIFM02 Unit 2 COMM02 Activity Planning Unit 2.
Dependencies and Network Diagrams. Agenda Dependencies Milestones The Network Early/Late Start/End dates Slack/Float Critical Path.
Project Management – Part 1. Overview What is a project? Project management techniques Activity lists Network diagrams Critical path analysis Gant charts.
Project Planning & Scheduling What is a “project”? Objectives and tradeoffs Planning and Control in Projects Scheduling Methods Constant-Time Networks.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Scheduling Scheduling : is the process of converting a project action plan into an operating time table. Why scheduling ? To answer the following questions:
Project Management: PERT/CPM
Project Scheduling KULIAH 10 Magister Sistem Informasi
Project Planning & Scheduling
Project Scheduling KULIAH 10 Magister Manajemen
Project Planning & Scheduling
Project Scheduling Chapter 14.
Project Time Management.
Chapter 6: Project Time Management
Projects: Critical Paths
Project Management CPM Method Tutorial-p2
Developing a Project Plan
Project Scheduling: networks, duration estimation, and critical path
CHAPTER 8: SCHEDULING (PENJADUALAN)
Exercise – A small building.
Scheduling.
Presentation transcript:

11/13/2015 IENG 471 Facilities Planning 1 IENG Lecture 03 Product & Process Design

11/13/2015IENG 471 Facilities Planning 2 Agenda Assignments Product Design Parts Lists / Bills of Material (BOM) Part Drawings Product Structure Indented BOM Process Design Routing Sheets Operations Process Charts Data for Facilities Planning Design Questions & Issues

11/13/2015IENG 471 Facilities Planning 3 Product Design Must meet the needs of the customer QFD Must be communicated (internally) Product Drawings (Assembly, Detail) Parts List Part Structure Indented BOM covers both the parts list and part structure

11/13/2015IENG 471 Facilities Planning 4 Indented Bill of Materials A “BOM” is a document that: Lists all parts in an assembly Shows the quantity of all components Allows for the roll-up of costs Shows the sequence of assembly Each indentation shows the components of the sub-assembly

11/13/2015IENG 471 Facilities Planning 5 Example: Manual Juicer

11/13/2015IENG 471 Facilities Planning 6 Example: Manual Juicer

11/13/2015IENG 471 Facilities Planning 7 Example: Manual Juicer Function of the product: Obtain seed-free juice from produce Principle(s) of operation: Lever (Class 2) to provide pressure Grating to stop seeds Gravity to drain the juice

11/13/2015IENG 471 Facilities Planning 8 Example: Manual Juicer Materials of construction: Aluminum (sandcast) body Rubber feet Cost of the artifact: $ 0.32 in aluminum $ 0.04 in rubber $ ??? in labor, shipping, packaging, etc.

11/13/2015IENG 471 Facilities Planning 9 Indented BOM & Cost Roll-up: (1) Juicer Assembly$ 0.36 (1) Body Sub Assembly$ 0.18 (1) Body Casting$ 0.14 (4) Rubber Feet$ 0.01 (1) Strainer Casting$ 0.05 (1) Lever Casting$ 0.10 (1) Hinge Pin$ 0.03 Example: Manual Juicer

11/13/2015IENG 471 Facilities Planning 10 BOM Example in Excel QuantityDescriptionCost 1 Juicer Assembly $ Body Sub-Assembly. $ Body Casting.. $ Rubber Feet.. $ Strainer Casting. $ Lever Casting. $ Hinge Pin. $0.03.

11/13/2015IENG 471 Facilities Planning 11 Process Design Steps in Process Identification 1. Define elemental operations 2. Identify alternative process(es) for each operation 3. Analyze alternative processes for each operation 4. Standardize processes for each operation 5. Evaluate alternative processes for overall production 6. Select processes for overall production

11/13/2015IENG 471 Facilities Planning 12 Routing Example ROUTING PART NAME:Shaft, VisePREPARED BY: DATE: PART NUMBER: DRAWING NUMBER: GT CODE: MATERIAL:Brass LABOR RATE: TOTAL COST: Process Parameters Estimated Op.SpeedFeedDepthLaborSetup No.Operation Descriptionft/minrpmipripmin.Machinehrs.hrsCostRemarks 1Cut material from bar150 band saw0.10 Leave extra for machining 2Face 1st end of shaft lathe take minimal needed for cleanup 3Face 2nd end of shaft lathe cut to length per print 4Turn diameter to length, rough lathe leave.03 for finish cut 5Turn diameter to length, finish lathe0.10 6Cut groove lathe Chamfer end of shaft lathe Turn diameter to length, rough lathe leave.03 for finish cut 9Turn diameter to length, finish lathe Chamfer end of shaft lathe Center drill end of shaft lathe Drill hole in end lathe drill extra deep 13Tap hole lathe0.10 hand tap, lots of oil 14Center drill for cross hole mill Drill cross hole mill Chamfer cross hole mill0.05 both sides

11/13/2015IENG 471 Facilities Planning 13 Operation Process Chart Circles represent operations Number in circle represents standard operation Prefix in circle identifies: Subassemblies (SA) – child levels Assemblies (A) – parent level in this view Circles are annotated with operation description Boxes represent inspections Number in box represents standard operation Boxes are annotated with inspection description Arcs (lines) represent component(s) Arcs are annotated with part number & description for introduced components (See Figure 2.12 in text, p. 44)

11/13/2015IENG 471 Facilities Planning 14 Example: Manual Juicer Operations-Process Chart Body Casting 4001 Rubber Feet 4021 Strainer Casting 4002 Lever Casting 4003 Hinge Pin Trim, sand, inspect 0102 Trim, inspect 0101 Trim, sand, inspect 0101 Trim, sand, inspect 0101 Trim, sand, inspect A1 A2 Plastic Bag 4031 SA1 I1

11/13/2015IENG 471 Facilities Planning 15 Standard OPC Symbols

11/13/2015IENG 471 Facilities Planning 16 Process Design Result The result of the process design can be a precedence diagram: Take the OPC and turn it on its’ side. Connect the component arcs with a single operation (START), and you have a Precedence Diagram The precedence diagram can be converted to a PERT chart for SCHEDULE DESIGN

11/13/2015IENG 471 Facilities Planning 17 Example: Manual Juicer Precedence Diagram A1A SA1 I1 0100

18 PERT: Scheduling Terminology Activity - A specific task or set of tasks that are required by the project, use up resources, and take time to complete Event - The result of completing one or more activities. An identifiable end state occurring at a particular time. Events use no resources. Network - The combination of all activities and events define the project and the activity precedence relationships Meredith, J. R. & Mantel, S. J. (2006) 11/13/2015IENG 471 Facilities Planning

19 PERT: Scheduling Terminology Path - The series of connected activities (or intermediate events) between any two events in a network Critical - Activities, events, or paths which, if delayed, will delay the completion of the project. A project’s critical path is understood to mean that sequence of critical activities that connect the project’s start event to its finish event Meredith, J. R. & Mantel, S. J. (2006) 11/13/2015IENG 471 Facilities Planning

20 PERT: Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (2) ABC A is preceded by nothing B is preceded by A C is preceded by B (1) J K L M J, K, & L can all begin at the same time, if you wish (they need not occur simultaneously) All (J, K, L) must be completed before M can begin but XZ AA Y (3) (4) Z is preceded by X and Y AA is preceded by X and Y Meredith, J. R. & Mantel, S. J. (2006) 11/13/2015IENG 471 Facilities Planning

21 PERT: Activity on Node Notation Early Start (ES)Early Finish (EF) Activity Duration (D) Late Start (LS)Late Finish (LF) 11/13/2015IENG 471 Facilities Planning

22 PERT: Calculating ES and EF Forward Pass Through Network: Move left to right, covering each simultaneous activity in order ES = maximum of EF for all immediate predecessor activities (0 for START activity) EF = ES + Duration Critical Time = EF of the END activity 11/13/2015IENG 471 Facilities Planning

23 PERT: Calculating LS and LF Backward Pass Through Network: Move right to left, covering each simultaneous activity in order LF = minimum of LS for all immediate successor activities (Critical Time for END activity) LS = LF – Duration Slack (Float) Time: LS – ES Note: Slack = 0 for Critical Activities 11/13/2015IENG 471 Facilities Planning

PERT: Critical Path Example 24 A 1 B 3 C 3 D 2 F 1 E 4 G 1 H 1Z Critical Time = 11 sec Critical Path = A, C, E, H, ZSlack B, F, G = 2 sec Slack D = 1 sec 11/13/2015IENG 471 Facilities Planning

25 PERT: Critical Path Management CP are those activities where ES = LS Any delay in these activities will delay production! Wrong to say that these activities are the most important, though: Frequently, activities with slack are put off until too late if not monitored! Other paths may be near-critical, and will also delay the project if not monitored! 11/13/2015IENG 471 Facilities Planning

11/13/2015IENG 471 Facilities Planning 26 Tying Critical Path to Facilities Critical Path is connected to Makespan If this were a repetitive operation environment: Makespan is the total time for a single, physical unit to go through all operations In manufacturing, the time difference between the start and finish of a sequence of jobs or tasks In health care, the duration of a patient’s medical experience for a treatment episode Team exercise Suppose that you had to schedule people to produce a product What would you do to operations on the CP? What might you do with non-CP operations? Skorin-Kapov, J. & A. J. Vakharia

11/13/2015IENG 471 Facilities Planning 27 Questions & Issues HW 2: Hands on assignment to develop: BOM Operations Process Chart Precedence Diagram Team exercise Teams must be different from Project Teams Semi-randomly assigned 4 people per team (5 people, if necessary) Other tools are in MIL Lab (IER 310) Leave the tools there, but OK to take the product parts