“Remediation of Historically Polluted Areas in Sarkandaugava” Progress from April 2013 till March 2014
2 Topics of Presentation The territories of the Project Project Budget Progress - Site I and Site II Progress - Site III Proposal for 2nd Tranche Factors impacted Project implementation Publicity and Swissness
3 The territories of the Project Site I (2,6 ha) - territory of “WOODISON TERMINAL” Ltd, “Ovi” Ltd and “Eko Osta” Ltd Site II (2,9 ha) - territory of “VL Bunkerings” Ltd Site III (2,5 ha)- territory of “OVI Riga” Ltd
4 Project Budget Project budget according to actual Project Proposal (November, 2013) Total eligible project costs, Requested grant, CHF Grant % of total eligible costs Co-financing CHF Site I and Site II Site III Total
5 Progress - Site I and Site II Till June, 2013 technical design for pilotproject accomplished In July, 2013 construction permit received, pilotproject construction works done, technological equipment supplied and installed Till December, 2013 pilotproject works were done In December report about pilotproject was received by Contractor On 28th December Engineer approved submitted pilot stage final report and recommended to continue the preparation for the further implementation of the remediation project According to agreement and FIDIC regulations construction supervision was performed all period Till March, 2014 remediation work technical design accomplished
6 Progress - Site III Prepared Project Proposal amendments according works in Site III (Ovi Riga Ltd territory) On 13th November the amendments nr.1 for individual project CH05 were signed On 13th November there was signed an agreement with "PB Inženiertehniskais birojs" Ltd about the project procurement documentation development for works in Site III In February there was announced procurement for remediation works and in 10th May there was announced winner. Period of possible complaints ends on 20th May In March there was announced procurement for remediation work supervision and in 29th April there was announced winner. No complaints were received
7 Alternative proposal for 2nd Tranche TerritoryMeasureCHF SIA „Ovi Rīga”Pilotproject SIA “Trans Quadrant Rīga”, A/s “Start Rīga”, SIA “Letors” un A/s “Rikon” Pilotproject Additional research AS “BLB Baltijas Termināls”, SIA “Vega Stividors”, SIA “Kortex” un SIA “Grand” Pilotproject Additional research Total Additional researches and pilotprojects in Sarkandaugava and Vecmilgravis polluted areas
8 Factors impacted Project implementation Procurement for remediation works in Site I and II is closed tender Complain about procurement for remediation works in Site I and II was submitted by participant which was rejected in first phase It is planned that remediation work agreement for Site III will be signed till June, 2014
9 Publicity and Swissness There was TV story in Swiss TV about the Project In April, 2013 – Swiss Environmental Engineering students visited the Project site Publications made in SES’s and MoEPRD web page Swiss expert provided consultations about procurement documentation of remediation works
10
Thank You for attention! Contact information Klāvs Brangulis State Environmental Service E ‐ mail: